Attachment C - Copy of 2019 Approval - Decision Notice · MCU19/0049.01

of 15

Text shows just the words. Original shows the document exactly as it was published.

      Works
62.   Demolition must be undertaken in a manner that causes no detrimental effect upon the
      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
      Waste management
63.   A Waste Management Plan (demolition) must be submitted in accordance with Planning
      Scheme Policy 11 - Waste Management Plan and approved by Council’s Waste Coordinator
      prior to the commencement of demolition works.
      The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
      effective reuse and recycling of such materials. Segregated wastes attract significantly
      reduced disposal fees at the landfill with some items free. Higher gate fees are charged for
      mixed waste.
      Waste storage areas must provide for adequate separation of all reusable, recyclable and
      waste materials. These must be located so that they are convenient and safe to use.
      The Plan must contain the following information:
      a. Traffic Management Plan prepared by suitably qualified person for the demolition works
         period. All required traffic control signage must be in accordance with the Manual of
         Uniform Traffic Control Devices (MUTCD);
      b. All required erosion and sediment control measures to be employed or undertaken
         during the demolition works to ensure sediment and other material from the demolition
         does not leave the site;
      c. The erosion and sediment control measures must be designed, installed and maintained
         in accordance with current best practice standards until all disturbed surfaces are
         stabilised;
      d. The areas for the storage and separation of waste shown on a site plan;
      e. A waste management table as indicated below is to be completed showing how waste
         material is to be segregated - recycled – reused or disposed;
      Table – Waste Management Table
        MATERIALS ON-SITE                                    DESTINATION
                                                 Re-use and Recycling                     Disposal
        Expected waste     Estimated  On-site                  Off-site               *specify contractor
        materials          volume(m³) *specify      proposed   *specify contractor    and landfill site or
                                         re-use or on-site     and recycling outlet   other disposal site
                                         recycling methods
        Excavation
        material
        Green waste
        Bricks
        Concrete
        Timber-please
        specify
        Plasterboard
        Metals - please
        specify
        Asbestos
        Other - please
        specify
      Note * If a demolition contractor is undertaking works, then the Waste Management table is
      to be completed by the demolition contractor.



                                                                                        Page 9 of 15

Used in these records

About this file

File size
451 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment C - Copy of 2019 Approval - Decision Notice.pdf · 451 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.