NOOSA COUNCIL IDAS Development Application Decision Notice                                                       3




                                    Noosa Council Conditions
                                    INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION


1.    The development shall be carried out in accordance with Engineering drawing No.12051-GD-E dated 11
      October 2006 by SCG Consulting Engineers or as modified herein.

2.    The method of connection to Council’s existing drainage as shown on plan No. 12051-GD-E is not
      acceptable. The 375mm dia. Pipe must be connected Council’s existing box culvert via a 1050mm dia
      manhole.

3.    A Construction Management Plan for works in Elizabeth Street shall be submitted to Council prior to the
      “pre start” meeting. This plan shall detail any road closures, traffic control and necessary signage required
      to carry out the works.

4.    A minimum of 300mm depth of lean mix backfill must be used over the new 375mm dia pipe within the
      Elizabeth Street pavement area.

5.    New private easements for the Drainage of stormwater, minimum 1.4 m wide shall be created, (a) within
      Lot 2 SP 151420 to benefit Lot 6 RP 69150, (b) within Lot 1 SP 151420 to benefit Lot 6 RP 69150 & Lot 2
      SP 151420, (c) within Lot 6 RP 64525 to benefit Lot 6 RP 69150, Lot 2 SP 151420 & Lot 9 RP 64525. The
      easement is to be centrally located over the pipework and is to be of sufficient width to ensure all
      associated pits and pipes are wholly contained within the easement.

6.    A site control and/or compliance bond of $5,000 is to be submitted to Council prior to the pre-start meeting.
      The pre-start meeting will only be held once Council's Construction Technical Officer has confirmation that
      the bond monies have been received by Council.

      The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions
      or any additional inspections incurred for substandard work or work undertaken not in accordance with this
      permit.

7.    Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’ notice of
      intention to commence works to arrange a “pre start” meeting regarding the civil works.

8.    The principal contractor must have all the appropriate insurance and public liability documentation to carry
      out the works. The principal contractor is also responsible to ensure that any sub contractors also have the
      appropriate insurance and public liability documentation.

9.    Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council’s
      signed approved drawings and conditions by the applicant.

10.   The Consulting Engineers for the project shall be currently Registered Professional Engineers of
      Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
      Council’s Construction Technical Officer or nominated staff. Council’s Construction Technical Officer shall
      provide an inspection form for signing off by the Engineer at appropriate stages of construction, during on-
      site meetings. Construction Technical Officer will also sign the form at each stage when conditions
      required have been satisfied. The works will be accepted “On Maintenance” after this form, signed by the
      inspector for each stage is complete, together with a letter from the Engineer requesting that the works go
      “On Maintenance”.

11.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project. (This
      person will be the contact for the project).

12.   Council standards shall apply to these works unless otherwise modified herein.

13.   The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
      during the construction of the engineering works to ensure that Council property, road pavements or
      facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
      furniture etc.) are protected against any damage or interference whatsoever.



NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@80007420\@[email protected]

Used in these records

About this file

File size
38 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015D9DE.001.pdf · 38 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.