Skip to the record
Accept no substitutions.

Original source · versioned page text

RFI (rec. 5.06.26) 2567 - 18 Taylor Court, Cooroy - RFI Response Letter - 08.05.2026

of 3
Our Reference:              2567


8 May 2026


Noosa Shire Council
PO Box 141
Tewantin QLD 4565


Attention:         Georgina Schramm

Dear Georgina,

RE:      APPLICATION FOR A DEVELOPMENT PERMIT FOR RECONFIGURING A LOT,
         MATERIAL CHANGE OF USE AND OPERATIONAL WORKS

         DEVELOPMENT APPLICATION NO. MCU26/0019, OPW26/0038, RAL26/0007
         18 TAYLORS COURT, COOROY
         LOT 2 SP 197517
         FOR RMD CAPITAL PTY LTD

         INFORMATION REQUEST RESPONSE


In reference to the Information Request issued by Noosa Shire Council, dated 9 April
2026, we provide the following responses to the Civil Engineering items. The following
supporting documentation is attached to this response:

    •    Appendix A – Civil Engineering Drawings
    •    Appendix B – Site-Based Stormwater Management Plan (SBSMP) (Ver2)
    •    Appendix C – Waste Management Plan (WMP) (Ver2)


DOCUMENTATION

    •    Item 5 – Infrastructure Staging
         Refer to revised drawings and documentation included in Appendices A, B & C.

         A temporary AV loading bay is provided in Stage 1 at the location shown in the
         drawings, and will act as a temporary AV bay until the completion of Stage 4.
         The permanent AV loading bay will be delivered in Stage 4. See updated
         drawings in Appendix A.

         The proposed bioretention and detention basin is designed to suitably attenuate
         and treat the entire developed (i.e. ultimate) catchment and is proposed to be
         constructed with Stage 1 of the development.


2576 – 18 Taylor Court, Cooroy – RFI Response Letter – 08.05.2026                      1
EA/TB

Log in to download the original (RFI (rec. 5.06.26) 2567 - 18 Taylor Court, Cooroy - RFI Response Letter - 08.05.2026.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

         Due to grading constraints of the site, the piped drainage system has been
         designed to convey the 1% AEP. All undeveloped upstream catchment, with the
         exception of the small catchment naturally draining to Taylor Court, can be
         conveyed by piped drainage to the ultimate basin. Temporary diversion drains
         and field inlet pits are provided to maximise catchment diversion to the basin
         with each successive stage, as shown on revised drawings (refer Sheets C101
         and C102).

         A construction phase erosion and sediment control plan will be required to be
         prepared by the contractor and certified by a suitably qualified person prior to
         commencement of works. The contractor is required to maintain appropriate
         erosion and sediment control measures throughout construction and all interim
         stages of the works.

    •    Item 6 – Bioretention / Detention Basin
         The bioretention basin is a private asset and will not be transferred to Council.
         Maintenance is the responsibility of the body corporate.

         The requirement for dedicated maintenance access under PSP6 is directed at
         Council contributed assets. Its application to a private asset is not considered
         warranted in this instance.

         The proposed 1:3 batter from the adjacent driveway to the basin floor provides
         suitable access for maintenance purposes. This approach is consistent with
         comparable privately maintained bioretention systems constructed throughout
         the estate. This item is considered addressed.

    •    Item 7 – PWD Park
         This item has been addressed. The proposed landscape infill has been
         relocated accordingly. Refer to the revised Civil Engineering Drawings included
         in Appendix A.

    •    Item 8 – Waste
         The Waste Management Plan (WMP) and associated turning path plans have
         been amended. Refer to the updated Waste Management Plan included as
         Appendix C. The development proposes the use of 2m³ bins serviced by a front
         lift waste collection vehicle (HRV), in accordance with Noosa Council
         requirements.

         Swept path analysis has been updated to reflect the appropriate front lift vehicle,
         including the required directional travel path through the site for each stage of
         development. Manoeuvring of the vehicle has been demonstrated for each
         stage of the development and is detailed in Section 4.3 of the WMP, allowing
         for the WCV to enter and exit in a forward direction with each successive stage.

         All bin storage areas shall be constructed to meet the minimum requirements
         provided in Noosa Council PSP, Schedule 6.10.5 – Waste management design


2576 – 18 Taylor Court, Cooroy – RFI Response Letter – 08.05.2026                          2
EA/TB

Page 3

         criteria. A bunded area is to be provided for bin washdown to ensure that all
         washdown water is contained and directed to a sewer connection in accordance
         with Council requirements. A water supply, including a tap with hose connection,
         will be provided within the bin storage area to facilitate cleaning. The design of
         the internal hydraulics has not yet been completed but will be undertaken to
         meet the requirements of Noosa Council PSP. All bins shall be washed within
         the designated bunded area.


Should you have any queries with respect to the above, please contact the
undersigned.

Yours Sincerely,


AUTHORED BY




EBONY AFIOUNI – Undergraduate Civil Engineer
DipEng



APPROVED BY




TIM BURKE – Director
BEng (Civil), CPEng, MIEAust, RPEQ (25245), NER

For and on behalf of:
BARLOW SHELLEY PTY LTD




2576 – 18 Taylor Court, Cooroy – RFI Response Letter – 08.05.2026                         3
EA/TB

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.