25. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Earthworks and Retaining Walls
26. All earthworks and associated retaining structures/batters, both above and below ground,
both temporary and permanent, must be undertaken in accordance with the conditions of this
approval, be generally in accordance with SCG Consulting’s Operational Works Earthworks
Plan (00461-OW3.1) , Operational Works Earthworks Sections Sheet 1 (00461-OW3.2) and
Operational Works Earthworks Sections Sheet 1 (00461-OW3.2) dated April 2025 and
contained entirely within the subject site unless written permission from the respective
landowner(s) is provided to Council.
27. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Acid Sulfate Soils
28. All works must be carried out in accordance with an updated site-specific Acid Sulfate Soil,
Groundwater and Dewatering Management Plans.
*(Refer to Advisory Note)
29. All waters, including stormwater runoff, groundwater seepage and leachate from acid sulfate
soils must achieve the following quality prior to release from the site:
a. a pH range of 6.5-8.5 pH units;
b. 50mg/L maximum total suspended solids concentration;
c. 0.3mg/L maximum total iron concentration;
d. 0.2mg/L maximum total aluminium concentration; and
e. no visible plume at either the point of release from the site or within a waterway.
30. The basement must be designed and constructed as a water excluding structure in
accordance with Australian Standard AS3735 “Concrete Structures for Retaining Liquids” to
ensure groundwater does not enter the basement after construction is completed.
31. All treated material must undergo verification testing at the rate of one sample per 250 m3
throughout the duration of the excavation phase of the development. The verification testing
must be undertaken by a qualified person* using the SPOCAS or Chromium Reducible
Sulphur testing suite, and the results must be submitted to Council for appraisal.
Damage to Services and Assets
32. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Page 5 of 21
Document Set ID: 24087855
Version: 5, Version Date: 03/09/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority - MCU25 0054 & OPW25 0077 (As Published).pdfRelated documentApplication case desk ↗
Decision Notice - Approved by Delegation of Authority - MCU25 0054 & OPW25 0077 (As Published)Related documentApplication case desk ↗
About this file
- File size
- 211 KB (small file)
- File type
No other editions are linked here.