Attachment C -Substation Options

Attached to the e-mail Operational Works Application OPW19/0157 - Cover Letter - DA Form 1 - Sub Station Detail Sheet 1, 2 & 3 -Montage existing - Montage Proposed - Consultant Advice Notice - Tree Management Plan - The Esplanade Sunshine Beach.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

Option 2
Option 2 is a ground mounted padmount substation. A typical padmount substation site is 5m Deep x 4.8m
wide. Noting that the site is sloping an engineered retaining wall will be required.




 Advantages                                           Disadvantages
 Lower visual impact for properties on Webb and       In ground works more extensive, including impact on
 Crank street                                         adjoining trees
 Higher electrical spare capacity for the surf club   Contractor/client responsible for the civil works
                                                      associated with the padmount




                                                                                                 Page 5 of 6
Log in to download the original file

Attachment C -Substation Options.pdf · 976 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.