Attachment C -Substation Options
Option 1
Option 1 is a pole mounted transformer mounted on a new service pole. The consumer mains for the surf club
would run from the transformer to a property pole then transition to underground and run to the surf club.
Advantages Disadvantages
Minimal inground works Visual impact for properties on Webb and Crank
street
Potentially faster build/lead times Size of the pole mount transformer is limited, thus
restricting future spare capacity for the surf club
Capital contribution for service pole less than The existing street lighting will be affected by the
padmount site changes to the power poles. Evans Built responsible
for modifications to street lighting subject to council
approval.