                 Table 4: Rehabilitation Schedule
                  ACTIVITY               ACTIVITY DETAIL                                                                                          JAN    JUN    JAN    JUN
                                                                                                                                                  2025   2025   2026   2026
                  SITE PREPARATION          ▪   Spot spray planting circles near driveway.
                                            ▪   Set up 3 static photo monitoring points using star pickets.
                  WEED CONTROL              ▪   Physically remove camphor laurel biomass with chainsaw and/or stem inject – half of the trees
                                                as outlined on the Weed Management Plan.
                                            ▪   Chipped trees can be used as mulch if no seed present. Remove from site if seed present.
                                            ▪   Understory weed control – high priority species in Appendix D.
                  REVEGETATION              ▪   Plant at least 2 native tree and 2 native shrub species near each dead camphor laurel.
                                            ▪   Replace Lantana thickets with native shrubs / trees planted at 1-2m spacings.
                                            ▪   Plant a dense lining of ferns, Lomandras and sedges along banks of the main drainage channel at
                                                0.5-1m spacings.
                                            ▪   Plant a dense edge of Lomandras, grasses and sedges at 0.5-1.0m spacings on edge of
                                                driveway.
                  WATERING                  ▪   Water each plant after planting; then water twice weekly for 2 weeks and weekly for 6 weeks if
                                                conditions are dry.
                  FOLLOW UP WEED            ▪   Remove / stem inject residual camphor laurel canopy trees.
                  CONTROL                   ▪   Understory weed control – high, medium and low priority species in Appendix D.

                  REVEGETATION              ▪   Plant at least 2 native tree and 2 native shrub species near each dead camphor laurel.
                                            ▪   Infill planting as required throughout Rehabilitation Area.
                  MONITORING &              ▪   Conduct photo monitoring at 3 static monitoring points.
                  EVALUATION                ▪   Assess Rehabilitation success using Appendix D – Rehabilitation Monitoring Form.
                  CORRECTIVE ACTION         ▪   Conduct follow up weed control if required.
                                            ▪   Apply adaptive management of new weed outbreaks as required.
                                            ▪   Replant to achieve required density if required.




                                                                              Weemilah Court Environmental Restoration Plan - 17




Document Set ID: 23744376
Version: 1, Version Date: 16/05/2025
Log in to download the original file

Approved Document - Environmental Restoration Plan OPW25_0071.pdf · 4.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.