Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
4.3    Pre-Development Hydrology

Pre-development peak stormwater discharge was estimated using XPSTORM modelling
software, and compared against the results from the Rational Method. Table 4.2 presents
the comparison to validate the peak flows estimated using XPSTORM.


                                   Peak Discharge Comparison (m3/sec)
   Design Storm         Rational Method              XPSTORM                Difference   % Change
       (AEP)

       63%                    0.089                    0.088                 -0.001        -1%
       39%                    0.114                    0.118                  0.004        4%
       18%                    0.158                    0.163                  0.005        3%
       10%                    0.198                    0.191                 -0.007        -4%
        5%                    0.236                    0.221                 -0.015        -6%
        2%                    0.301                    0.275                 -0.026        -9%
        1%                    0.346                    0.306                 -0.040       -12%
                            Table 4.2 Pre-Development Stormwater Flow Validation



From Table 4.2 the Rational Method results compare well with the XPSTORM model results
for estimates of the pre-developed peak stormwater discharging from the site.


To ensure a robust stormwater detention design the Rational Method results will be used to
represent the pre-developed peak stormwater discharge from the site.




Site Based Stormwater Management Plan                                                    Page 5 of 19
2123-SBSMP-01_Version 1.0 (October 2021)
Log in to download the original file

Site Based Stormwater Management Plan.pdf · 7.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.