SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 NOVEMBER 2020
Page 123 of 131
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 NOVEMBER 2020
OPERATIONAL PLAN 2020-21 PROGRESS REPORT
LONG TERM PLANNING FOR NOOSA SHIRE
No. Project ETT Tila UF eter Status
1 Finalise the Climate Change Adaptation Plan and initiate Director Environment & Sustainable In August, Council endorsed the Project Plan and Engagement Strategy fora Behind Schedule @
implementation of actions Development Climate Change Response Plan. Stakeholder engagement in October and
November. Coastal Hazards Adaptation Plan with State and LGAQ for review.
2 Continue to implement the Noosa Transport Strategy Director Infrastructure Services Preparations underway for a full Go Noosa program during Christmas On track @
priority actions as determined by Council holidays. Translink draft MOU to be provided end October 2020. Schools
program underway.
3 Finalise the adoption of the new Noosa Planning Scheme Director Environment & Sustainable Noosa Plan 2020 commenced 31 July and has already had one Completed @
Development administrative amendment. A further Coastal Hazards Amendment is in
progress. Wide range of supporting material is available on line. Special
interest presentations have occurred.
4 Establish a Placemaking Team and commence pilot Director Environment & Sustainable Looking to establish team and commence towards end of 2020 Not started 2
project Development
5 Finalise the development of the Walking and Cycling Director Infrastructure Services The Walking and Cycling Strategy is behind schedule and due for completion Behind Schedule i)
Strategy in December 2020, subject to public consultation in early November 2020.
6 Complete Asset Management Plans for pathways and Director Infrastructure Services The Pathways and Boardwalk Asset Management Plan is being finalised for Behind Schedule @
boardwalks and for parks and playgrounds comment before going to the December round of Council meetings. The
Parks and Playgrounds Asset Management Plan is expected to be presented
to Council in April 2021.
7 Implement recommendations arising from the Noosa Spit Director Infrastructure Services Submission for approval by the Department of Environment and Resource On track @
Shoreline Erosion Management Plan (SEMP) Management for undertaking proposed activities in the SEMP has been
lodged. Once these have been approved, design and delivery options can
commence.
8 Review the Noosa Council Corporate Plan Chief Executive Officer Some preliminary work on the sequencing between a Corporate Plan anda Behind Schedule @
Community Plan has been undertaken. A project framework for a review of
the current Council Corporate Plan will be developed.
Page 123 of 131See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.