Development Assessment Report · OPW16/0016
Attached to the e-mail OPW16/0016 - Operational Works Application.
Project Urban – 15253 February 2016
The following provides an assessment of the applicable states interests identified above:
LIVEABLE COMMUNITIES STATE INTEREST
BIODIVERSITY STATE INTEREST
Assessment Criteria Comment
Development: Complies – The site is identified as being affected
(1) enhances matters of state environmental by the regulated vegetation (intersecting a
significance where possible, and watercourse) overlay by the SPP Mapping. The site
(2) identifies any potential significant adverse is not mapped as containing any significant
environmental impacts on matters of state vegetation by Council or SARA mapping and the
environmental significance, and development does not require the removal of any
(3) manages the significant adverse environmental vegetation. In consideration of the above the
impacts on matters of state environmental proposed development will not have any
significance by protecting the matters of state unreasonable adverse impact on the mapped
environmental significance from, or otherwise matter of state environmental significance.
mitigating, those impacts.
(2) ensures that the disturbance of ASS avoids or
minimises the mobilisation release of acid and
metal contaminants by:
(a) neutralising existing acidity and preventing
the generation of acid and metal contaminants,
and
(b) preventing the release of surface or
groundwater flows containing acid and metal
contaminants into the environment.
NATURAL HAZARDS, RISK AND RESILIENCE STATE INTEREST
Assessment Criteria Comment
Development: Complies - The site is within a flood hazard area
(1) avoids natural hazard areas or mitigates the and coastal hazard areas (erosion prone area,
risks of the natural hazard to an acceptable or medium storm tide inundation area and high storm
tolerable level, and tide inundation area) in accordance with the SPP
mapping. The deck is proposed to be established
at 2.2m AHD which is 1.65m above the Highest
Astronomical Tide (H.A.T). The establishment of
the deck at this level will ensure the proposed
works will achieve adequate immunity from
flooding and storm tide inundation. The proposed
deck has been designed by an RPEQ who
specializes in Marina type developments to ensure
the proposal is adequately designed to withstand
any possible erosion issues. In consideration of the
above the proposed development has mitigated
the risks of natural hazards.
(2) supports, and does not unduly burden, disaster Complies – The deck is proposed to be
management response or recovery capacity and established at 2.2m AHD which is 1.65m above the
capabilities, and Highest Astronomical Tide (H.A.T). The
establishment of the deck at this level will ensure
the proposed works will achieve adequate
immunity from flooding and storm tide inundation
so as not to burden disaster management
capacity.
(3) directly, indirectly and cumulatively avoids an Complies – The deck is proposed to be
increase in the severity of the natural hazard and established at 2.2m AHD which is 1.65m above the
the potential for damage on the site or to other Highest Astronomical Tide (H.A.T). The
properties, and establishment of the deck at this level will ensure
the proposed works will achieve adequate
Development Assessment Report Page 9 of 14
Operational Works for Prescribed Tidal Works
2 Parkyn Court, Tewantin
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Assessment Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.