                                              (c)   if a relevant planning scheme
                                                    standard is more stringent than
                                                    the standard mentioned in
                                                    paragraph (a) or (b)—the
                                                    relevant    planning    scheme
                                                    standard, to the extent the
                                                    standard is more stringent than
                                                    the standard mentioned in
                                                    paragraph (a) or (b);

                                              (d)   any other relevant planning
                                                    scheme standard that is not
                                                    inconsistent with the standards
                                                    mentioned in paragraphs (a) to
                                                    (c).
Signage
Not Applicable – No new signage is proposed within tidal works.
Earthwork and vegetation
7.1 Excavation and filling for prescribed The earthwork and filling for the              Not Applicable – No excavation or
tidal work—                               prescribed tidal work is consistent with       filling is proposed as part of the works.
                                          each     relevant     planning   scheme
a) is carried out only to the extent standard.
reasonably necessary for the work; and

b) does not have a significant
adverse effect on—

 i) the natural features of the tidal
 water under, within or over which the
 work is located; or

  ii) the level of the surface of the land
  under the tidal water under, within or
  over which the work is located, or any
  foreshores near the work.
7.2 The location of prescribed tidal work    The vegetation in the tidal water, under    Complies – No vegetation will be
ensures vegetation is cleared or             within or over which the prescribed tidal   affected by the prescribed tidal works.
disturbed only to the extent reasonably      work is located, or on land under the
necessary for the work.                      tidal water, is cleared or disturbed in a
                                             way consistent with each relevant
                                             planning scheme standard.
7.3 Any vegetation damaged, destroyed        Vegetation affected by the prescribed       Complies – No Vegetation will be
or removed by prescribed tidal work          tidal work is dealt with in a way           affected by the prescribed tidal works.
under, within or over tidal water other      consistent with the following standards—
than an artificial waterway, is replaced
with appropriate vegetation.                  (a)   subject to paragraph (b),
                                                    vegetation damaged, destroyed
                                                    or removed by prescribed tidal
                                                    work is replaced with native
                                                    vegetation for the locality within
                                                    which the work is located, to the
                                                    extent     it   is    reasonably
                                                    practicable to replace the
                                                    vegetation       with       native
                                                    vegetation;

                                              (b)   if a relevant planning scheme
                                                    standard is more stringent than
                                                    the standard mentioned in
                                                    paragraph

                                              (c)   —the relevant planning scheme
                                                    standard, to the extent it is
                                                    more     stringent   than  the
                                                    standard       mentioned     in
                                                    paragraph (a);

                                              (d)   any other relevant planning
                                                    scheme standard that is not
                                                    inconsistent with the standards
                                                    mentioned in paragraphs (a) and
                                                    (b).

Used in these records

About this file

File size
1.6 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Assessment Report.pdf · 1.6 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.