Prelim Construction Management Plan[1]

of 17

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Preliminary Construction
Management Plan
Reconfiguring a Lot (1 into 2) RAL21/0028

53-57 Rene Street Noosaville 4566 QLD
Lot 281 SP 104321


Glen Grams




                                            June 2022
Log in to download the original file

Prelim Construction Management Plan[1].pdf · 2.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 16 pages

Page 2

Table of Contents

1.     Important Note                                                                                                                                             2

2.     Introduction                                                                                                                                               3
       2.1 Purpose                                                                                                                                                3
       2.2 Scope of this Plan                                                                                                                                     3
       2.3 Proposed Works                                                                                                                                         3
       2.4 Site Location                                                                                                                                         4
       2.5 Contact Details                                                                                                                                       4

3.     Construction Management                                                                                                                                    5
       3.1 Approach                                                                                                                                               5
       3.2 Approvals                                                                                                                                              5
       3.3 Site Security                                                                                                                                          5
       3.4 Public / Worker Safety                                                                                                                                 6
       3.5 Traffic Management Plan                                                                                                                                6
       3.6 Worker Carparking                                                                                                                                      6
       3.7 Communications Protocol / Complaints Procedure                                                                                                         6
       3.8 Existing Infrastructure                                                                                                                                7
       3.9 Fencing                                                                                                                                                7

4.     Construction Methodology                                                                                                                                  8
       4.1 Demolition and Excavation                                                                                                                             8
       4.2 Construction Sequence and Planning                                                                                                                    8
       4.3 Rubbish Removal                                                                                                                                       8

5.     Environmental                                                                                                                                              9
       5.1 General                                                                                                                                                9
       5.2 Noise and Vibration Management                                                                                                                         9
       5.3 Air Quality / Dust Management                                                                                                                          9
       5.4 Stormwater and Sediment Control                                                                                                                      10




List of Figures
Figure 1: Site Location Map ...................................................................................................................................... 4



List of Attachments
Attachment A - Traffic Guidance Scheme prepared by Evolution Traffic Management




RG Strategic                                              Preliminary Construction Management Plan                                                                 1

Page 3

1.   Important Note

Apart from fair dealing for the purposes of private study, research, criticism, or review as permitted
under the Copyright Act, no part of this report, its attachments or appendices may be reproduced
by any process without the written consent of RG Strategic. All enquiries should be directed to RG
Strategic.

We have prepared this Preliminary Construction Management Plan for Glen Grams (“Client”). This
report is strictly limited to the purpose and the facts and matters stated in it and does not apply
directly or indirectly and will not be used for any other application, purpose, use or matter.

In preparing this report we have made certain assumptions. We have assumed that all information
and documents provided to us by the Client or as a result of a specific request or enquiry were
complete, accurate and up-to-date. Where we have obtained information from a government
register or database, we have assumed that the information is accurate. Where an assumption has
been made, we have not made any independent investigations with respect to the matters the
subject of that assumption. We are not aware of any reason why any of the assumptions are
incorrect.

This report is presented without the assumption of a duty of care to any other person (other than
the Client) (“Third Party”). The report may not contain sufficient information for the purposes of a
Third Party or for other uses. Without the prior written consent of RG Strategic;

       • this report may not be relied on by a Third Party; and

       • RG Strategic will not be liable to a Third Party for any loss, damage, liability or claim arising
          out of or incidental to a Third Party; and

       • publishing, using or relying on the facts, content, opinions or subject matter contained in
          this report

If a Third Party uses or relies on the facts, content, opinions or subject matter contained in this report
with or without the consent of RG Strategic, RG Strategic disclaims all risk and the Third Party
assumes all risk and releases and indemnifies and agrees to keep indemnified RG Strategic from any
loss, damage, claim or liability arising directly or indirectly from the use of or reliance on this report.

In this note, a reference to loss and damage includes past and prospective economic loss, loss of
profits, damage to property, injury to any person (including death) costs and expenses incurred in
taking measures to prevent, mitigate or rectify any harm, loss of opportunity, legal costs,
compensation, interest and any other direct, indirect, consequential or financial or other loss.




RG Strategic                          Preliminary Construction Management Plan                            2

Page 4

2.   Introduction

2.1 Purpose

This Preliminary Construction Management Plan has been prepared to describe how the Project
Management team shall implement and conduct its allocated site management responsibilities
during the Operational Works phase of the “Lot Subdivision” (the Project). A fundamental aim of this
Plan is to ensure all construction is properly facilitated, integrated, and coordinated to deliver
certainty to the objectives of the Project.

The preparation of a Preliminary Construction Management Plan was conditioned (Condition 26) by
Noosa Council as part of the higher order approval RAL21/0028 dated 30 March 2022.



2.2 Scope of this Plan

This Plan provides a holistic approach that:

       • advises how the project management team will comply with the requirements of the
          contract relating to construction;

       • defines the project objectives and targets of particular relevance to the construction
          phase;

       • describes constraints specific to the construction phase and the project in general;

       • describes the process for the identification and control of risks specific to the construction
          phase; and

       • details the proposed strategy for the construction phase, with particular regard to
          establishment resourcing, site organisation and construction controls.



2.3 Proposed Works

The proposed works require the construction of:

       • a 2.0 metre wide pedestrian footpath within the road verge for the entire length of the
          site’s frontage to Rene Street

       • kerb, footpath and verge area to match the balance of the site frontage, including the
          provision of topsoil and turf where the existing verge is grassed

       • a driveway located generally in accordance with drawing number 03-1159-C1 Sheet 1
          Revision A prepared by Lindsay Consulting dated 11 February 2022

       • a driveway crossover in generally in accordance with Council’s Standard Drawing No RS-
          051 and any associated addendum

       • landscaping generally in accordance with Council’s Decision Notice (RAL21/0028).

RG Strategic                         Preliminary Construction Management Plan                        3

Page 5

This type of construction will have several distinct phases that will require different material handling
strategies to optimise the construction works and minimise impact to surrounding streets, other
stakeholders and neighbours. Our material handling strategies and construction planning will be
consulted with stakeholders and authorities before implementation.



2.4 Site Location

The proposed development site (refer Figure 1) has direct access from Rene Street.




                                                       Subject Site




                                                                                        Belmondos




                                       Figure 1: Site Location Map
                                            Source: Near Map



2.5 Contact Details

For all on-site operational and construction matters, refer to the below contact details:

Principal Site Contractor: to be appointed.

Project Manager: to be appointed.




RG Strategic                         Preliminary Construction Management Plan                          4

Page 6

3.   Construction Management

3.1 Approach

The major external constraints on the project are:

       • Maintaining smooth traffic and pedestrians flow with minimal disruptions to Rene Street,
          and

       • Undertaking works with minimal impact on neighbours, in particular, adjoining commercial
          and industrial properties.

Upon commencement, our project team’s immediate tasks will be to:

       • Undertake a survey of the site and complete a dilapidation report of adjoining properties
          and assets,

       • Assess the existing structures on-site and prepare for removal,

       • Confirm the locations of existing services and obtain all necessary permits and licences
          and approvals, and

       • Arrange for the installation of temporary services – power, water and sewer to service the
          site works and the amenities.



3.2 Approvals

A Decision Notice for a Reconfiguring a Lot was issued by Noosa Council on 30/3/2022 (RAL21/0028).

This Preliminary Construction Management Plan has been prepared as part of the application
material for an Operational Works permit (to be assessed by Noosa Council).

Following the issuing of an Operational Works permit by Council, the below Certifications and
Approvals will be obtained:

       • Certification from the service providers (Energex, NBN and Unitywater) which certifies that
          the development has met the requirements of Council’s approval RAL21/0028 and all
          applicable legislation at the time of construction.

       • Confirmation of easement registration over the relevant service provider, public or third
          party infrastructure located on the site.



3.3 Site Security

The site will be secured using appropriate fences with access gates manned with qualified security
guards/traffic control officers. The site will be secured out of hours and patrolled by qualified
security guards. All visitors to the site will be required to report to the site office, and will be
appropriately inducted and registered in a visitor’s log book.

RG Strategic                           Preliminary Construction Management Plan                    5

Page 7

3.4 Public / Worker Safety

All site staff and subcontractors will be required to complete a site-specific induction before
commencing work on site. The induction will cover aspects relating to safety and amenity; including
access, emergency evacuation procedures, location of first aid facilities, location of amenities, site
hours, material handling, noise and dust policies and environmental management.

Prior to commencing works on site, all subcontractors will be required to submit a project specific
Safety Management Plan. This plan will be reviewed by appointed Building Contractor for
compliance with the overall Project Safety Plan.

The Project Manager will conduct regular inspections of the project and will be actively involved in
reviewing Safety Management Plans and making recommendations with regard to health and
safety issues.

The Contractor is to maintain access to all adjacent properties during the construction of these
works.



3.5 Traffic Management Plan

A Traffic Guidance Scheme (revision 00, dated 31/5/2022) has been prepared by Evolution Traffic
Management and is included in Attachment A.

All temporary traffic control to be in accordance with the MUTCD.

Safe pedestrian access is proposed and included within he attached Traffic Guidance Scheme.



3.6 Worker Carparking

During the construction, car parking for the site workers will be located on site within the existing
hardstand /carparking area.



3.7 Communications Protocol / Complaints Procedure

The appointed Contractor shall undertake a letter box drop to adjoining properties providing
contact details for the site supervisor.

The approach for resolving complaints is,

       1.   Deal with the complaint immediately. Get to the heart of the matter quickly, and you’re
            more likely to satisfy the customer. Ignoring it will not solve the problem.

       2.   Stay calm. The customer must be dissatisfied for some reason, even if you think they are
            wrong. The matter will only get worse if you respond aggressively.

       3.   Identify the problem. Listen to what the customer says and make sure you understand.


RG Strategic                          Preliminary Construction Management Plan                      6

Page 8

            Ask what they expect you to do and write it down in as much detail as possible.

       4. Decide what can be done. Even if you believe the complaint is unjustified, it may be
            worthwhile trying to make the customer happy to keep their business. All it may require is
            a simple explanation. Sometimes it is worth ‘walking the extra mile’, and doing more than
            you feel you need to, or are obliged to, for the customer.

       5.   Arrange a second opinion to confirm your view. In some instances, this second opinion
            may show up things you hadn’t noticed.

       6.   Keep records. Writing everything down reduces the chance of misunderstanding. Many
            contractual disputes arise because nothing is in writing, or the details are ambiguous.

       7.   Fix the problem. Tell the customer what solution you can offer and make sure they
            understand. If they accept the solution, act straight away and resolve the matter quickly
            and efficiently.



3.8 Existing Infrastructure

Existing infrastructure will be protected during construction. The selected Contractor shall clean off
any debris deposited on the road. Dial Before You Dig enquiries will be undertaken prior to all
excavation works.



3.9 Fencing

2 metre high temporary fencing will secure the site. Security gates will be used on all access points
onto the site.




RG Strategic                         Preliminary Construction Management Plan                         7

Page 9

4. Construction Methodology

4.1 Demolition and Excavation

Existing services within the site have been located and either capped if redundant or modified if
they are to be used as temporary services for the works.

Minor excavation work will be required on site as per the approved Operational Works Water and
Sewer Plan (03-1159-C1 revision A) contained in RAL21/0028.



4.2 Construction Sequence and Planning

The locations and types of plant may vary depending on the results of more detailed planning as
the design solidifies and the availability of plant is confirmed. There will be 3 distinct phases requiring
different material handling logic to construct the building efficiently and minimise impact on
surrounding streets and neighbours.

The phases are:

       • Phase 1: Site establishment and preparation, site excavation,

       • Phase 2: Disconnection of services, water and sewer works, driveway and crossover works,
            and connection of new works, and

       • Phase 3: Landscaping, cleaning and site reinstatement.

Each phase will not happen in isolation and the staging of them may coincide.



4.3 Rubbish Removal

A designated waste collection area will be provided for onsite that does not receive a substantial
amount of runoff from upland areas and does not drain directly to water body.

Rubbish will be removed from site by a licenced waste contractor ensuring that it is managed to
comply with Noosa Council and their contractor’s requirements. It will be taken to the to a transfer
facility.

Disposal of waste collection bins are to be clearly marked '"conventional waste”, "recyclable" and
"regulated waste".

The Principal Contractor will ensure that all containers are fitted with lids and that waste collection
is scheduled to prevent the containers from overfilling.




RG Strategic                          Preliminary Construction Management Plan                           8

Page 10

5.   Environmental

5.1 General

The objective of this section is to identify the proposed methods that will be employed to minimise
the impact of noise, vibration and air quality in the vicinity of the development.



5.2 Noise and Vibration Management

The normal hours of work will typically be 7.00am to 5.30pm, Monday to Saturday excluding public
holidays. Noise management will generally be in accordance with the QLD DEHP environmental
noise management criteria. All plant will be regularly maintained and log books kept ensuring that
there are no excess noise emissions. Where it is practical, electric machinery will be used in lieu of
mechanical devices.

All subcontractors will be responsible for managing noise and vibration in accordance with their
project specific Management Plans.

It is proposed to undertake some after hour’s works for specific tasks to minimise impacts to
pedestrians, vehicular traffic or in the interest of safety. The works that are proposed to be
undertaken outside of normal working hours include the following:

       • Fencing works;

       • Footpath works.

All after hour’s works will be subject to the engagement and communication with all identified
stakeholders. Consultation with the Noosa Shire Council will occur at all times prior to any works
being scheduled. All businesses will be given notification either via email, letter box drop and
personal contact of all the proposed after hours works prior to the works commencing which will
include details of the works and the time to undertake each activity.



5.3 Air Quality / Dust Management

Dust control measures will be implemented as required and will be in accordance with QLD
Workplace health and safety regulations and Environmental Protection Act.

Dust management will be most critical during the demolition phase of the project, with the
subcontractors for these trades specifically dealing with dust management within their project
specific management plans.

prior to commencement of construction, neighbouring residents and emergency services shall be
notified in writing by letter drop of the construction period. designated working hours and contacts
regarding complaints of excessive air quality issues.

Measures that may be employed include:


RG Strategic                        Preliminary Construction Management Plan                        9

Page 11

           •   Activities are to only be conducted during suitable weather conditions.

           •   A water truck or spray apparatus is to be provided on site if required.

           •   Exposed areas such as cleared areas and stockpiles are to be watered and kept
               damp in order to minimise erosion or the potential for dust creation.

           •   Vehicle speed is to be limited on site to minimise dust generation.

           •   Trucks entering or exiting the site shall have their loads covered

           •   All construction vehicles exiting site shall pass through a wheel wash down and/or
               drive over a shake down grid which will be located at the site entry /exit.

           •   Haulage routes shall avoid residential areas and use sealed roads where possible.

           •   Machinery shall be fitted dust filters all equipment and vehicles are to meet relevant
               emission standards.

           •   Maintenance of wind breaks and barriers where possible.



5.4 Stormwater and Sediment Control

Excavation – At the commencement of these works, screens and bunding at the perimeter of the
site where stormwater may run off will be installed. Bunding will also be implemented around
stormwater drains. Diligent housekeeping will be implemented to minimise risk of dust/debris being
washed into pits.




RG Strategic                         Preliminary Construction Management Plan                      10

Page 12

Attachment A
Traffic Guidance Scheme
Preliminary Construction Management Plan

53-57 Rene Street Noosaville 4566 QLD
Lot 281 SP 104321


Glen Grams

Page 13

                                                                                                                                                                       OPS­FORM­025 TRAFFIC GUIDANCE SCHEME (QLD) | BEST PRINTED IN A3 SIZE




   53­57 RENE STREET
      NOOSAVILLE


   PROJECT/SITE OVERVIEW
   Project/Site Description:                                                                      RENE STREET


   Location of Works:                                                             53­57 RENE STREET, NOOSAVILLE


   Anticipated Commencement Date: . . . . . . . . . . . . . . . .                                         TBA
   Estimated Duration of Works: . . . . . . . . . . . . . . . . . . . .                           NIGHT WORKS
   Working Hours: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                           TBA

   CLIENT DETAILS
   Client Name:                                                                                  RG STRATEGIC
   Client Contact Name:                                                                         TRACEY HENNIG
   Client Contact Number:                                                                          0754 743 873
   PO/Contract Number:                                                                                     2468

   Site Contact:
                                                                                                TRACEY HENNIG
   Site Contact Number:
                                                                                                   0754 743 873
   SCOPE OF WORKS
   This Traffic Management Plan has been developed to allow the client to conduct works at the above
   location and to display a commitment to Traffic and Pedestrian Management, Reporting, and Reviewing.
   These works will include, but not limited to:
   CONSTRUCTION OF DRIVEWAY


   LOCALITY MAP




                                                                                  NOOSA REGIONAL COUNCIL
                                                                                        QPS NOOSA HEADS


THIS DOCUMENT HAS BEEN DEVELOPED IN ACCORDANCE WITH THE INFORMATION SUPPLIED BY OUR CLIENT: RG STRATEGIC                                  Evolution Traffic Management
                                                                                                                                                                                                         APPROVED BY TM DESIGNER:

THE SIGNING TMD IS NOT RESPONSIBLE FOR ANY OMISSIONS OR ERRORS IN THE BASE INFORMATION SUPPLIED BY THE ABOVE MENTIONED "CLIENT"                                                                               STEVE JW ROBERTS
                                                                                                                                           572 Curtin Ave East, Eagle Farm                                       QDTMR TMD# 647
WHILE DUE CARE HAS BEEN TAKEN IN THE PREPARATION OF THIS DOCUMENT, TRAFFIC AND ON SITE CONDITIONS AT THE TIME OF THE WORKS MAY VARY FROM          Queensland 4009                                        EVOLUTION JOB NUMBER:
THOSE ESTABLISHED WITHIN THIS DOCUMENT.
THE PRINCIPAL CONTRACTOR IS RESPONSIBLE FOR UNDERTAKING OF AN EVALUATION OF THE SITE AND TRAFFIC CONDITIONS AGAINST THOSE OUTLINED
                                                                                                                                           PO Box 432 Northgate, Qld 4013                                        440432905
WITHIN THE TMP AND IN THE TGS's AS APPROPRIATE. WHERE CONDITIONS VARY FROM THOSE DOCUMENTED, ADDITIONAL INPUT FROM A TMD (TRAFFIC               Ph: 1300 880 481.                                                                   REV#   PAGE:

MANAGEMENT DESIGNER) SHOULD BE SOUGHT.                                                                                                   TMR REGISTRATION NUMBER: 0323                                                               00 01 of 04

Page 14

                                                                                                                                                                                                                                    OPS­FORM­025 TRAFFIC GUIDANCE SCHEME (QLD) | BEST PRINTED IN A3 SIZE
IMPLEMENTATION INSTRUCTIONS                                                       SITE SPECIFIC NOTES                                                             DESKTOP RISK ASSESSMENT
Before work commences, signs and devices at the approaches to and within       xx Where this symbol appears, please refer back to the coinciding note below.

the work area SHALL be implemented in accordance with the approved             01 ­ A Worker (symbolic) sign shall be used to give warning of personnel           LOCATION OF WORKS                                                                                      DATE
Traffic                                                                             engaged in short­term or long­term works on or adjacent to the travelled                         53­57 RENE STREET, NOOSAVILLE                                                              31/05/2022
Guidance Schemes and the Traffic Control Companies Safe Work Method                 path. It shall only be displayed when workers are visible from traffic.
Statements, in the following sequence:                                              (AS 1742.3 2019 Cl. 4.6.5)                                                         RISK RATING:     4 = (VERY HIGH)                            3 = (HIGH)             2 = (MEDIUM)                          1 = (LOW)
1) Traffic Controllers implementing signage are to ensure all signage is       02 ­ Access to local businesses and driveways will be maintained during
   available for implementation prior to shift.                                      works. Unless otherwise shown on the TGS(s) and site specific notes.         IDENTIFIED HAZARDS/RISKS:
                                                                                     It is the Principal Contractors responsibility to seek permission prior to
2) Signs & devices in side streets leading into the works are to be
                                                                                     blocking public and private access.
                                                                                                                                                                  1­          Clearance to traffic.
   implemented first. Where required, detours are to be in place before
   commencing any closures.                                                    03 ­ 700m traffic cones will be positioned at a maximum 4m apart.                  2­          Presence of workers at worksite.
                                                                                     (AGTTM03 Cl. 5.4 ­ Table 5.3)
3) All signage on arterial and main road alignments to be implemented with
                                                                               04 ­ Existing 3.0m lane width shall be maintained. A clearance area between
                                                                                                                                                                  3­          Cyclist / pedestrians through worksites.
   the flow of traffic.
4) Signs are to be implemented in all non affected lane(s) first and all             the edge of traffic lane and delineation SHALL be provided.                  4­          Poor observance by motorists of directions / instructions.
   conflicting signs are to be covered.                                              Measurements for this clearance are outlined under AGTTM03 Cl. 2.5.8
5) Signs in the affected lane to be implemented; Taper, Speed Reduction,             ­ Table 2.5.
   Safety buffer (if applicable), and Delineation to be implemented with the   05 ­ Traffic control to assist pedestrians and cyclists around the work area as
   traffic flow. Conflicting signs to be covered in process.                         required.
6) Ensure signs & devices are correct before works commence.                   06 ­ Workers to remain greater than 1.2m at all times.
7) Once works have finished, Traffic Control are to pick up delineation and    07 ­ Traffic control may vary length dependent on existing site conditions.
                                                                               08 ­ Signs required for works which will be in progress for longer than 14
   taper's in reverse. Then pick up advance warning signs with the flow of
                                                                                     days may be installed in a more permanent manner on posts sunk into
   traffic.
                                                                                     the ground. Check that underground utilities are not located below and
                                                                                     making holes is approved by the relevant road authority. Ensure regular      ACTIONS TAKEN :
RECORDING & MONITORING                                                               site inspection, maintenance and securing practices occur in these
Regular inspections of traffic control devices SHALL be carried out a minimum
of twice daily and recorded in The Daily Traffic Diary. These records SHALL          circumstances. (AGTTM03 Cl. 2.5.3)                                           1,2,3 ­     Placement of advance warning signs.
                                                                               09 ­ If there is only single advance warning sign on the approach, the sign be
be available for inspection during the project. These records will be held on
                                                                                     positioned at double the spacing from the worksite. (AGTTM03 Cl. 2.5.3)
                                                                                                                                                                  1,2,3 ­     Separation of works from road users through delineation (cones).
site by The Client. Details of all changes in traffic movements shall be
recorded and maintained throughout the construction period and submitted
                                                                                                                                                                  3­          Placement of advance warning signs for Cyclist / pedestrians.
within 7 days from the date of practical completion. In the event of a traffic                                                                                    1, 4 ­      Implementation of shoulder closure.
related incident with in the site, The Client SHALL immediately notify the
principal’s representative, the police, and any necessary emergency services.

PEDESTRIAN & CYCLIST MANAGEMENT
All pedestrian & cyclist control measures, for the duration of the construction
works will be monitored as required for effectiveness & improvements.
Appropriate warning signage and directional signage will be in place and
monitored throughout the works as per the provided TGS's attached to this
document. Where current documented control measures are ineffective, A
TMD qualified person(s) should be contacted to suggest changes.                                                                                                   CONTROL LEVEL REQUIRED: 1 ­ ELIMINATE 2 ­ SUBTITUTE 3 ­ ISOLATE 4 ­ ENGINEER                                     5 ­ ADMIN             6 ­ PPE
GENERAL NOTES                                                                                                                                                     FURTHER ACTION REQUIRED:
­ The TMD preparing this plan has ensured it complies with the Queensland                                                                                         ­           Traffic control to assist pedestrians and cyclists around the work area as required.
   MUTCD Part 3 (Mar 2022), AGTTM (Dec 2019), QGTTM (Mar 2022) &
   AS 1742 (Dec 2019). Any unapproved variations to the design will negate
   heir liability. Variations and amendments to this TGS are to be recorded on
   this TGS with the changes noted, along with the date and time of the           LEGEND:
   change and the accreditation details of the TMD making the change.                  LATERAL HAZARD MARKER
                                                                                                                                     PEDESTRIAN ROUTE
­ The attached TGS's SHALL be read in conjunction with this notes page                 either T5­7 (Vertical) or T5­4 (Horizontal)
   and the associated risk assessments and an on site risk assessment                  TRAFFIC CONES
                                                                                                                                     AFTERCARE
   SHALL be performed before any implementation works takes place.                     per MUTCD AS 1742.3
                                                                                                                                                                                                   4 = (VERY HIGH)                 3 = (HIGH)             2 = (MEDIUM)                          1 = (LOW)
                                                                                                                                                                      RESIDUAL RISK:
­ It is the Clients responsibility to ensure they have a copy of the permits
                                                                                       PROPOSED WORK AREA
   (in date) for the closure being implemented.                                        as advised by Client
­ This TGS SHALL only be implemented by a competent person(s) with a                                                                                                                                CONSEQUENCE
   current Traffic Management Implementation (TMI) qualification.                      PROPOSED LANE CLOSURE                                                             Likelihood
­ A toolbox talk is to take place before works commencing.
                                                                                       per AGTTM requirements / Client request                                                                       Insignif.[1]             Minor [2]         Modera. [3]         Major [4]                    Catastr. [5]
­ Work Site Safety Traffic Management Checklist to be filled out prior to
   implementation, and upon completion.                                                                                                                               Almost Certain [5]                    3                       3                 4                     4                            4
­ Traffic Controllers to identify and make note of escape routes prior to
   commencement of works.                                                                                                                                             Likely [4]                            2                       3                 3                     4                            4
­ Hand held UHF radios are to be utilised where required to communicate
   between traffic control & site vehicles.                                                                                                                           Possible [3]                          1                       2                 3                     4                            4
­ Principal Contractor to notify local Emergency Services in advance of
   commencing works.                                                                                                                                                  Unlikely [2]                          1                       2                 2                     3                            4
­ QDTMR TMC are to be contacted 1 hour before any works commence
   within a QDTMR corridor.                                                                                                                                           Rare [1]                              1                       2                 2                     3                            3
­ Advance signs SHALL be mounted at a minimum height of 200mm
   displayed as prominently as possible by selecting the longitudinal
   location of the sign for best sight distance for approaching traffic. Signs                                                                                        4 Very High [VH]              URGENT ­ Stop work immediately, the risk requires immediate attention
   continuously required for works which will be in progress for periods
   longer than 2 weeks should be erected in a permanent manner, e.g. on
   posts sunk into the ground, and duplicated on the right side of the road.                                                                                                                        Continue with supervision and control measures in SWMS or site risk
                                                                                                                                                                      3 High [H]
­ Traffic volumes should be monitored throughout the implementation of                                                                                                                              assessment
   the TGS(s). In the event queue lengths become unmanageable, works
   should cease if possible and traffic cleared before recommencing.                                                                                                  2 Medium [M]                  Use control measures to ensure risk is low as reasonably possible
                                                                                                                                                                      1 Low [L]                     Manage by routine procedures and safe practices
CLIENT: RG STRATEGIC                                                                                                                                                                               CONSTRUCTION OF DRIVEWAY
TGS REFERENCE:                         REV. DATE PAGE(S) NO# DESCRIPTION                                                                                                              TMD INIT       Evolution Traffic Management
                                                                                                                                                                                                                                                                      APPROVED BY TM DESIGNER:
                                                                                                                                                                                                                                                                          STEVE JW ROBERTS
253125                                  00 31/05/2022 ENTIRE DOCUMENT TRAFFIC MANAGEMENT PLAN DEVELOPED FOR RG STRATEGIC                                                              647   SJWR      572 Curtin Ave East, Eagle Farm                                        QDTMR TMD# 647

253126                                  01                                                                                                                                                                   Queensland 4009                                          EVOLUTION JOB NUMBER:

                                        02                                                                                                                                                            PO Box 432 Northgate, Qld 4013                                               440432905
                                        03                                                                                                                                                                 Ph: 1300 880 481.                                                    REFERENCE ID:     REV#   PAGE:

                                        04                                                                                                                                                          TMR REGISTRATION NUMBER: 0323                                     EVO NOTES 01                 00 02 of 04

Page 15

                                                                                                                                                                                                                                                                                                   OPS­FORM­025 TRAFFIC GUIDANCE SCHEME (QLD) | BEST PRINTED IN A3 SIZE




                                    50
                                                                                                                                                                                                                NIGHT SHIFT
                                                                                                                                                                                                                                                                                                                    CLIENT TO PROVIDE
                                                                                                                                                                                                            REFER TO TGS 253126                                                                                   TEMPORARY PRAM RAMP
                                                                                                                                             SHOULDER TAPER                                                   FOR AFTERCARE
                                                                             CLIENT TO PROVIDE                                                LENGTH (3­5m) 07
                                                                           TEMPORARY PRAM RAMP
                                                                                                                                             30m                               6m                                                                                                          30m
                                                                                                                               09 (27­3                                       ADD'L                                                                                                    TERMINATION
                                                                                                                                    Tole 8m)                                 WARNING
                                                                                                                                        ranc                                                                         65m                                                                      (27­38m)
                                                                                                                                             e                          TAPER AREA                                 WORK AREA                                                                  Tolerance

                                                                                                                                                                                                                                                                    05




                                                                                                         DO
                                                                                                                               05




                                                                                                           AH ORK




                                                                                                                                                                                                                                                                    FOOTPATH
                                                                                                                                                                                                                                                                                PEDESTRIANS
                                                                                                        NO




                                                                                                                                                              LONG TERM SIGN




                                                                                                                                                                                                                                                   LONG TERM SIGN
                                                                                                                                          FOOTPATH
                                                                                                                            PEDESTRIANS




                                                                                                                                                                                                                                                                     OTHER
                                                                                                            W AD




                                                                                                                                           OTHER




                                                                                                                                                                                                                                                                      USE
                                                                                                   TO

                                                                                                             EA

                                                                                                              RO




                                                                                                                                            USE
                                                                                                                D
                                                                                                      V

                                                                                                                                                                                                                 #53­57

                                                                                                                        N
                                                                                                  ER




                                                                                                                                                                                                                                                                                                                                DRIVE SAFELY




                                                                                                                                                                                                                                                                                                                                                                  LONG TERM SIGN
                                                                                                                    SIG
                                                                                             TAK




                                                                                                                                                                                                                                                                     FOOTPATH
                                                                                                                                                                                                                                                                      CLOSED
                                                                                                                                                   FOOTPATH
                                                                                                                   RM
                                                                                             E




                                                                                                                                                    CLOSED
                                                                                                                   TE                                                                                                                                                                                     02
                                                                                             08
                                                                                                  01
                                                                                                               NG




                                                                                                                                                                                                                                                                                                                                                WORK
                  TO




                                                                                                                                                                                                                                                                                                                                                ROAD
                                                                                                                                                                                                                                                                                                                                                 END
                                                                                                             LO




                                                                                                                                                                                        TC UTE
                                                                                                                                                              02
                          LE




                                                                                                                                                                                                                                                                                                                                                08
                          O
                            AL




                                                                                                                                                                                                                                    06
                                                                                                                                                                                                                     03
                                                                                                                                                                                                                               04
                               LE




                                                                                                                                                                                                                                                                                                                                                                                           50
                                                                        N
                                  YR




                                                                     SIG

                                                                                    RO ND
                                                                    M


                                                                                   WO AD
                                       D




                                                                                       K
                                                                     R




                                                                                                                                                                                                                                                                                                                                               08 01
                                                                                     E

                                                                                     R
                                                                  TE




                                                                                       LY




                                                                                                                                                                                                                                                                                                                         LONG TERM SIGN




                                                                                                                                                                                                                                                                                                                                                         DO NOT OVERTAKE
                                                               G




                                                                                     FE
                                                               N
                                                            LO




                                                                                SA
                                                                            IVE




                                                             08




                                                                                                                                                                                                                                                                                                                                          AHEAD
                                                                         DR




                                                                                                                                                                                                                                                                                                                                          WORK
                                                                                                                                                                                                                                                                                                                                          ROAD
                                                                                                                                                                                                               PEDESTRIAN PATH

                                                                                                   30                                                                                                                                                                                           30m
                                                                                              TERM m                                                                                                                                                                                          (27­38m)
                                                                                                    INATIO                                                                                                                                                                                    Tolerance 09
                                                                                                (27        N
                                                                                                           ­38m
                                                                                                       Tolera )
                                                                                                                                                                                                                                                                                                                                                     TO PRODUCTION ST
                                                                                                             nce




                                         Manifest                                                                                                                                                                                                                                                     Signs required for works which will be in progress for longer than 14 days may be installed in a more
                                                                                                                                                                                                                                                                                                        permanent manner on posts sunk into the ground. Check that underground utilities are not located
21 x 700mm Cone                                                                                                                                                                                                                                                                                                          below and making holes is approved by the relevant authority. Ensure regular site
                                                                                                                                                                                                                                                                                                                            inspection, maintenance and securing practices occur in there circumstances.
 2 x Multi Message (TC1169 Road Work Ahead, TC1174 Do Not Overtake, TC1332 Worker Symbolic)                                                                                                                                                                                                                                                                     (as per AGTTM, Part 3, Clause 2.5.3 ­ Signs)
 2 x Multi Message (TC1170 End Road Work, TC1177 Drive Safely, BLANK (Y) Blank Yellow)
 2 x T5­Q02 Chevron Delineator
                                                                                                                                                                                                                                                                                                                         0.3m                           On kerbed roads in built­up areas where signs are mounted on posts adjacent
                                                                                                                                                                                                                                                                                                          ROAD                                   to a footpath or where vehicle parking may occur, they should be placed a minimum
 1 x Multi Message (TC2217 Footpath Closed, T8­2(L) Pedestrians Left, Use Other Footpath)                                                                                                                                                                                                                 WORK
                                                                                                                                                                                                                                                                                                          AHEAD                                         of 300 mm clear distance behind the kerb and erected a minimum 2.2 m above
                                                                                                                                                                                                                                                                                                          REDUCE SPEED
 1 x Multi Message (Use Other Footpath, T8­2(R) Pedestrians Right, TC2217 Footpath Closed)                                                                                                                                                                                                                                                                      the level of the kerb or footpath to the underside of the sign, to reduce
 1 x TC UTE w/ Arrowboard                                                                                                                                                                                                                                                                                                                                    interference from parked vehicles. Where neither pedestrians nor parked
                                                                                                                                                                                                                                                                                                      2.2m
                                                                                                                                                                                                                                                                                                                                                         vehicles have to be considered, E.g. on a traffic island or median, a mounting
 1 x Traffic Controller                                                                                                                                                                                                                                                                                                                                                                        height of 1.5 m may be more appropriate.
                                                                                                                                                                                                                                                                                                                                                                                (as per AS 1742.3, Clause 4.3.2 ­ Positioning of devices)
JELYN GRACE SORIANO
CLIENT: RG STRATEGIC                                                                                                                                                                                                                         CONSTRUCTION OF DRIVEWAY
THIS (TGS) SHALL BE READ IN CONJUNCTION WITH NOTES 01              LOCATION:                                                                                                   53­57 RENE STREET          TERM:           SHORT               Evolution Traffic Management
                                                                                                                                                                                                                                                                                                                                                                                   APPROVED BY TM DESIGNER:
                                                                                                                                                                                                                                                                                                                                                                                           STEVE JW ROBERTS
IT HAS BEEN DEVELOPED TO ALLOW THE CLIENT TO                       SUBURB:                                                                                                     NOOSAVILLE                 ROAD TYPE:      TWO WAY              572 Curtin Ave East, Eagle Farm                                                                                                                QDTMR TMD# 647
CONDUCT WORKS AT THE LISTED LOCATION AND TO DISPLAY
                                                                   1ST CROSS ST:                                                                                               LEO ALLEY ROAD             POSTED SPEED: 50 KPH                        Queensland 4009                                                                                                               EVOLUTION JOB NUMBER:
A COMMITMENT TO TRAFFIC AND PEDESTRIAN MANAGEMENT,
REPORTING, AND REVIEWING. AN ON SITE RISK ASSESSMENT               2ND CROSS ST:                                                                                               PRODUCTION STREET          OPERATION:      SHOULDER CLOSURE     PO Box 432 Northgate, Qld 4013                                                                                                                    440432905
SHALL BE CONDUCTED PRIOR TO ERECTING ANY TRAFFIC                   UBD MAP REF#:                                                                                               18:E5                      TRAVELLED PATH: PAST                        Ph: 1300 880 481.                                                                                                                      REFERENCE ID:        REV#     PAGE:

CONTROL DEVICES.                                      NOT TO SCALE GPS/CHAINAGE:                                                                                               ­26.4177220, 153.0430460   AADT:           <1000              TMR REGISTRATION NUMBER: 0323                                                                                                         EVO 253125                       00 03 of 04

Page 16

                                                                                                                                                                                                                                                                          OPS­FORM­025 TRAFFIC GUIDANCE SCHEME (QLD) | BEST PRINTED IN A3 SIZE
                                                                                                                                                                                                                                                                                 Signs required for works which will be in progress for longer than 14 days may be installed in a more
                                                                                                                                                                                                                                                                                   permanent manner on posts sunk into the ground. Check that underground utilities are not located
                                                                                                                                                                                                                                                                                                    below and making holes is approved by the relevant authority. Ensure regular site
                                                                                                                                                                                                                                                                                                       inspection, maintenance and securing practices occur in there circumstances.
                                                                                                                                                                                                                                                                                                                                           (as per AGTTM, Part 3, Clause 2.5.3 ­ Signs)

                                                                                                                                                                                                                                                                                                 0.3m                         On kerbed roads in built­up areas where signs are mounted on posts adjacent
                                                                                                                                                                                                                                                                                  ROAD
                                                                                                                                                                                                                                                                                  WORK
                                                                                                                                                                                                                                                                                                                       to a footpath or where vehicle parking may occur, they should be placed a minimum
                                                                                                                                                                                                                                                                                  AHEAD                                       of 300 mm clear distance behind the kerb and erected a minimum 2.2 m above
                                                                                                                                                                                                                                                                                  REDUCE SPEED
                                                                                                                                                                                                                                                                                                                                      the level of the kerb or footpath to the underside of the sign, to reduce
                                                                                                                                                                                                                                                                                                                                   interference from parked vehicles. Where neither pedestrians nor parked
                                                                                                                                                                                                                                                                             2.2m
                                                                                                                                                                                                                                                                                                                               vehicles have to be considered, E.g. on a traffic island or median, a mounting
                                                                                                                                                                                                                                                                                                                                                                     height of 1.5 m may be more appropriate.
                                                                                                                                                                                                                                                                                                                                                      (as per AS 1742.3, Clause 4.3.2 ­ Positioning of devices)

                                    50




                                                                           TO L
                                                                                                                                                                                           REFER TO TGS 253125
                                                                                              CLIENT TO PROVIDE                                                                                FOR WORKS
                                                                                            TEMPORARY PRAM RAMP



                                                                               E
                                                                               OA
                                                                                                                                30                                                                                                                                     30m                                          CLIENT TO PROVIDE

                                                                                 LLE
                                                                                                                              (27­ m                                                                                                                               TERMINATION                                    TEMPORARY PRAM RAMP
                                                                                                                                  3
                                                                                                                             Tole 8m)
                                                                                                                                 ranc                                                                                                                                (27­38m)
                                                                                                                                      e
                                                                                    Y RD                                                              TAPER (6m)                                   (65m)                                                             Tolerance
                                                                                                        08
                                                                                                                                                                                                                                                      05




                                                                                                    DO
                                                                                                                        05



                                                                                                   NO




                                                                                                                                                                                                                                         FOOTPATH
                                                                                                                                                                                                                                                     PEDESTRIANS
                                                                                                                                                                                                                        LONG TERM SIGN


                                                                                                                                                                                                                                          OTHER
                                                                                                 TO                                                                                                   #53­57




                                                                                                                                                                                                                                           USE
                                                                                                                                                                                                                                                                                                          08
                                                                                                    V




                                                                                                                   N
                                                                                              ER




                                                                                                                                                   FOOTPATH




                                                                                                                                                                                                                                                                                                        DRIVE SAFELY
                                                                                                                                                                       LONG TERM SIGN
                                                                                                                                     PEDESTRIANS




                                                                                                                                                                                                                                                                                                                                        LONG TERM SIGN
                                                                                                                  SIG




                                                                                                                                                    OTHER
                                                                                                 AH ORK
                                                                                             TAK




                                                                                                                                                     USE
                                                                                                  W AD




                                                                                                                                                                                                                                          FOOTPATH
                                                                                                                                                                                                                                           CLOSED
                                                                                                              RM
                                                                                                   EA

                                                                                                    RO
                                                                                             E
                                                                                                      D




                                                                                                              TE




                                                                                                                                                            FOOTPATH
                                                                                                             NG




                                                                                                                                                                                                                                                                                                                       WORK
                                                                                                                                                                                                                                                                                                                       ROAD
                                                                                                                                                             CLOSED




                                                                                                                                                                                                                                                                                                                        END
                                                                                                        LO




                                                                                                                                                                                                                                                                                                                                                                 50
                                                                       N
                                                                    SIG

                                                                         RO ND
                                                                        WO AD
                                                                   M



                                                                          RK
                                                                          E
                                                                   R




                                                                                     LY
                                                                TE




                                                                                                                                                                                                                                                                                                 LONG TERM SIGN




                                                                                                                                                                                                                                                                                                                               DO NOT OVERTAKE
                                                                                                                                                                                                                                                                                                                  AHEAD
                                                                                                                                                                                                                                                                                                                  WORK
                                                                                   FE




                                                                                                                                                                                                                                                                                                                  ROAD
                                                              G
                                                              N




                                                                                SA
                                                           LO




                                                                             IVE




                                                              08
                                                                           DR




                                                                                                                                                                                        PEDESTRIAN PATH                                                                                                           08


                                                                                                 30                                                                                                                                                                    30m
                                                                                             TERM m                                                                                                                                                                   (27­38m)
                                                                                                 INATIO                                                                                                                                                               Tolerance
                                                                                                  (27­38
                                                                                                 Tolera )
                                                                                                         m
                                                                                                                  N                                                                                                                                                                                                     TO PRODUCTION ST
                                                                                                       nce




                                         Manifest
21 x 700mm Cone
 2 x Multi Message (BLANK (Y) Blank Yellow, TC1174 Do Not Overtake, TC1169 Road Work Ahead)
 2 x Multi Message (TC1170 End Road Work, TC1177 Drive Safely, BLANK (Y) Blank Yellow)
 2 x T5­Q02 Chevron Delineator
 1 x Multi Message (TC2217 Footpath Closed, T8­2(L) Pedestrians Left, Use Other Footpath)
 1 x Multi Message (Use Other Footpath, T8­2(R) Pedestrians Right, TC2217 Footpath Closed)

JELYN GRACE SORIANO
CLIENT: RG STRATEGIC                                                                                                                                                                                                AFTERCARE
THIS (TGS) SHALL BE READ IN CONJUNCTION WITH NOTES 01              LOCATION:                                                                            53­57 RENE STREET               TERM:           LONG         Evolution Traffic Management
                                                                                                                                                                                                                                                                                                                                                         APPROVED BY TM DESIGNER:
                                                                                                                                                                                                                                                                                                                                                                 STEVE JW ROBERTS
IT HAS BEEN DEVELOPED TO ALLOW THE CLIENT TO                       SUBURB:                                                                              NOOSAVILLE                      ROAD TYPE:      TWO WAY       572 Curtin Ave East, Eagle Farm                                                                                                               QDTMR TMD# 647
CONDUCT WORKS AT THE LISTED LOCATION AND TO DISPLAY
                                                                   1ST CROSS ST:                                                                        LEO ALLEY ROAD                  POSTED SPEED: 50 KPH                 Queensland 4009                                                                                                             EVOLUTION JOB NUMBER:
A COMMITMENT TO TRAFFIC AND PEDESTRIAN MANAGEMENT,
REPORTING, AND REVIEWING. AN ON SITE RISK ASSESSMENT               2ND CROSS ST:                                                                        PRODUCTION STREET               OPERATION:      AFTERCARE     PO Box 432 Northgate, Qld 4013                                                                                                                   440432905
SHALL BE CONDUCTED PRIOR TO ERECTING ANY TRAFFIC                   UBD MAP REF#:                                                                        18:E5                           TRAVELLED PATH: PAST                             Ph: 1300 880 481.                                                                                                        REFERENCE ID:         REV#    PAGE:

CONTROL DEVICES.                                      NOT TO SCALE GPS/CHAINAGE:                                                                        ­26.4177220, 153.0430460        AADT:           <1000       TMR REGISTRATION NUMBER: 0323                                                                                                        EVO 253126                       00 04 of 04

Page 17

a

G

STRATEGIC

STRATEGIC SOLUTIONS,
CREATIVE THINKING

rgstrategic.com.au

 

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.