Log in to see the plans as drawn4. Construction Methodology
4.1 Demolition and Excavation
Existing services within the site have been located and either capped if redundant or modified if
they are to be used as temporary services for the works.
Minor excavation work will be required on site as per the approved Operational Works Water and
Sewer Plan (03-1159-C1 revision A) contained in RAL21/0028.
4.2 Construction Sequence and Planning
The locations and types of plant may vary depending on the results of more detailed planning as
the design solidifies and the availability of plant is confirmed. There will be 3 distinct phases requiring
different material handling logic to construct the building efficiently and minimise impact on
surrounding streets and neighbours.
The phases are:
• Phase 1: Site establishment and preparation, site excavation,
• Phase 2: Disconnection of services, water and sewer works, driveway and crossover works,
and connection of new works, and
• Phase 3: Landscaping, cleaning and site reinstatement.
Each phase will not happen in isolation and the staging of them may coincide.
4.3 Rubbish Removal
A designated waste collection area will be provided for onsite that does not receive a substantial
amount of runoff from upland areas and does not drain directly to water body.
Rubbish will be removed from site by a licenced waste contractor ensuring that it is managed to
comply with Noosa Council and their contractor’s requirements. It will be taken to the to a transfer
facility.
Disposal of waste collection bins are to be clearly marked '"conventional waste”, "recyclable" and
"regulated waste".
The Principal Contractor will ensure that all containers are fitted with lids and that waste collection
is scheduled to prevent the containers from overfilling.
RG Strategic Preliminary Construction Management Plan 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.