Prelim Construction Management Plan[1]

of 17

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
            Ask what they expect you to do and write it down in as much detail as possible.

       4. Decide what can be done. Even if you believe the complaint is unjustified, it may be
            worthwhile trying to make the customer happy to keep their business. All it may require is
            a simple explanation. Sometimes it is worth ‘walking the extra mile’, and doing more than
            you feel you need to, or are obliged to, for the customer.

       5.   Arrange a second opinion to confirm your view. In some instances, this second opinion
            may show up things you hadn’t noticed.

       6.   Keep records. Writing everything down reduces the chance of misunderstanding. Many
            contractual disputes arise because nothing is in writing, or the details are ambiguous.

       7.   Fix the problem. Tell the customer what solution you can offer and make sure they
            understand. If they accept the solution, act straight away and resolve the matter quickly
            and efficiently.



3.8 Existing Infrastructure

Existing infrastructure will be protected during construction. The selected Contractor shall clean off
any debris deposited on the road. Dial Before You Dig enquiries will be undertaken prior to all
excavation works.



3.9 Fencing

2 metre high temporary fencing will secure the site. Security gates will be used on all access points
onto the site.




RG Strategic                         Preliminary Construction Management Plan                         7
Log in to download the original file

Prelim Construction Management Plan[1].pdf · 2.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.