Court Judgement 17 March 2021 - Case D186 of 2019
ANNEXURE A
Approved Plans
1. Any vessels (including vessels not owned by the applicant) associated with the marine
use of the facility:
a. may be moored to the northern pontoon, and be located outside, or partially
outside, of the approved lease area only if the mooring of that vessel in that
location is:
i. temporary; and
ii. for a purpose associated with the marine use of the facility, and not for
any other purpose;
but
b. must not be otherwise moored or stored outside, or partially outside, of the
approved lease area.
2. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following table
unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
26236-J1 D Jetty Plan and Details prepared by SCG 12 October 2017
Consulting Engineers as amended by
Project BA for Minor Change
Application Annotated 12.10.2018
26236-S2 C Jetty Plan and Details prepared by SCG 12 October 2017
Consulting Engineers
180908 As Constructed Survey of new Jetty and 27 September 2018
Pontoon in Lot 163 on CP907408
3. All structures associated with the jetty and pontoon must be constructed wholly within
the approved area
4. Structures must be designed and constructed such that they are free standing within the
waterway and are not connected to or behind the revetment wall or rock wall
5. Structures must be designed and constructed such that they do not place additional
vertical or lateral loads onto the existing revetment wall that may compromise the long
term stability and/or durability of the wall. Upon completion of works, a certification by
RPEQ must be provided to Council in this regard.
6. All structures must have no detrimental effects on stormwater drains and/or easements.
7. No boatlifting devices are to be attached or moored at the structures for the purpose of
elevating a vessel above the water without Council approval.
8. The jetty and deck areas must be constructed in a manner to render the underside area
vermin proof
9. There must be no electrical reticulation system carrying electricity in excess of 24 volts
beyond the revetment wall unless all switches and power outlets are positioned above
the 1%AEP flood level.