3. FINAL-160721-BA4090-Town Planning Report
Attached to the e-mail MCU16/0084 & OPW16/0157 Development Application IDAS Forms, Planning report & Plans email 1 of 3.
F.3 BUSINESS USES CODE – FOR ALL BUSINESS USES
Specific Outcomes Probable Solutions Response
14. 16 Effects of use
Electricity Infrastructure
O18 The development does not S18 .1 No solution provided O18 Complies
adversely impact on existing or
future electricity supply The proposal is to be developed
infrastructure; on a site that has an existing
building improved on the land.
AND Due to this improvement, the
existing or future electricity
supply infrastructure will not be
adversely impacted.
O19 All uses and works maintain S19.1 Development for uses S19.1 Complies
an adequate safe distance from adjacent to or within 50m of an
electrical infrastructure including existing electricity substation The proposal is not within 50m of
substations, overhead incorporates noise attenuation electricity substation.
powerlines, power poles and measures to mitigate noise
transformers. impacts;
AND
S19.2 Buildings and structures Not Applicable
(including swimming pools,
sheds, tennis courts and The site does not contain
outbuildings) are not constructed overhead electricity transmission
under overhead electricity lines, or electricity easements.
transmission lines, or within
electricity easements.
Noise
O20 Development is designed No solution provided. O20 Complies
and sited to avoid noise
emissions that unreasonably The proposed service station and
diminish the amenity of the area food outlet is located in an
or surrounding uses. industry zone which anticipates
an increase in noise emission
compared to other zones. The
proposal will maintain the level of
amenity of the industry zone.
Mechanical plant and equipment and storage areas
URBIS
FINAL-160721-BA4090-TOWN PLANNING REPORT APPENDICES
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.