identified on Lot Layout Plan Titling Features RL40 Issue A dated 08.02.24.
Onsite Works
9. Prior to sealing of the plan of survey the following works must be undertaken in
accordance with an Operational Works approval:
a. the proposed Lots or building pads are to be filled in accordance with the
Overall development layout plan RL30 Revision C, to achieve a minimum
reduced level of RL 3.43m (AHD);
b. all filling works must be designed to prevent ponding within the proposed lots
and not direct runoff on to other private properties or create additional ponding
on adjacent properties;
c. the vehicle access driveways from Lake Weyba Drive to proposed lots 1-3 are
to be constructed from the road formation to the house pad level in accordance
with the Overall development layout plan RL30 Revision C, and Council’s
Standard Drawings;
d. the internal road (cul-de-sac turnaround extension off Sail Street) as shown on
Overall development layout plan RL30 Revision C, and to Council’s Standards;
e. clearly visible pavement changes must be constructed at the threshold of the
internal road (cul-de-sac turnaround extension off Sail Street) which clearly
demarcates the transition from the public road system to the private community
title scheme land;
f. clearly visible signage must be erected at the threshold of the internal road (cul-
de-sac turnaround extension off Sail Street), which clearly indicates to motorists
and pedestrians that they are entering a private road system;
g. the vehicle access driveways from the cul-de-sac to lots 4-8 are to be designed
and constructed in accordance with Council’s Standard Drawings, with the
driveway to Lot 4 extending to the end of the access handle;
h. all civil works within the site area are to be certified by a Registered Professional
Engineer of Queensland (RPEQ);
i. any civil works required by the approved Flood Emergency Management Plan,
the Bushfire Management Plan,
j. rehabilitation works required by the Rehabilitation Plan (excluding ‘maintenance
period’ requirements).
Boundary Encroachments
10. Prior to the sealing of the survey plan certification must be submitted to Council from a
Registered Cadastral Surveyor (Qld) which certifies that:
a. the setback/s to any new boundaries for any existing buildings remaining on the
site;
2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.