Attachment A to Judgment for 19Aug 2024 (6)
Very large file (32.8 MB): the original may take a few minutes to open or download. The page text below is quick to read.
b. comply with the relevant provisions of the planning scheme and the Building Act
1975, unless varied by this Decision Notice;
c. all constructed public access and roadworks (including associated fill batters
and retaining walls) are fully contained within a dedicated reserve or registered
easement;
d. all utility services and connections (eg. Electricity, telecommunications, water,
sewerage) are wholly located within the lot they serve or alternatively included
within an easement;
e. all retaining walls and structure are fully contained within the lot they retain;
f. any fill and retaining structures, including fill batters, are wholly contained within
the subject site and not on adjacent properties;
g. for the community title scheme, the road pavement changes required by this
Decision Notice accurately demarcate the boundaries of the public and private
land
Flood Emergency Management Plan
11. All works must be carried out in accordance with the approved Flood Emergency
Management Plan prepared by SLR Consulting (FEMP).
12. The Applicant is to notify all prospective purchasers of the proposed lots that the site is
subject to flooding hazard and provide them with a copy of the FEMP.
13. The FEMP (and associated procedures) must be complied with at all times. The Body
Corporate and the owners of the proposed lots, including successive landowners, are
responsible for implementing the FEMP.
14. All owners and occupiers of the proposed lots, including successive landowners are to
be provided with a copy of the FEMP (and procedures for the purposes of implementing
the FEMP), for which the Body Corporate is responsible.
15. The Body Corporate is responsible for maintaining and providing suitable information
packs/ kits to all owners and occupiers of the proposed lots. The information packs
must include details in relation to flooding hazard, the FEMP and emergency flood
procedures. A copy of the information packs/kits must be submitted to Council prior to
the sealing of the survey plan.
16. The Applicant and the owners of the proposed lots are not permitted to undertake
works within the proposed lots that would undermine the operation and implementation
of the FEMP.
17. Prior to the sealing of the plan of survey, the Applicant is to install onsite, or secure an
agreement for the use of, a flood height gauge to indicate depth of flooding to residents
and occupiers of the site as required by the FEMP. The gauge will be installed to
Bureau of Meteorology (BOM) specifications, and will connect to a visual signal and
audible siren within the site. This is to allow for site specific flood monitoring in
conjunction with reviewing the BOM weather warnings consistent with the FEMP.
18. The Body Corporate is responsible for ensuring the ongoing operation, management,
maintenance (which includes replacement) and testing of the flood height gauge and
3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.