SPA Decision Notice - 010.2010.00000916.001 [As Published] · 172010.916
2010/916
Relevant Period
2. The Preliminary Approval for Building Work lapses if the use has not happened by
29 July 2012, unless an application to extend the currency is approved by Council.
Security Bond
3. Security in the form of a cash bond or trading bank guarantee to the sum of $1,500 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for building works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
Building Design
4. The building height shall not exceed 8.0 metres above the natural ground level, finished
ground level and 2 storeys.
5. The new works shall be finished with muted/environmental tones which are non-reflective and
match the colours and tones of surrounding vegetation when seen from the beach or water.
Landscaping
6. A minimum of 20% of the site shall be retained as soft landscaping.
7. Existing vegetation greater than 2m in height within the frontage of the site shall be retained.
8. The road reserve shall be landscaped with a mixture of native landscaping in accordance with
Table 6.1, 6.2 & 6.3 of PSP3 - Landscaping Plants & Guidelines for suitable
coastal/beachfront areas (attached for your convenience).
Water Storage
9. All new hot water systems installed shall be either solar systems; electric heat pump systems;
or gas systems (LPG or natural).
General
10. The development shall be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood due to the creation of excessive noise, lighting
nuisance, or other emissions.
Earthworks
11. Earthworks required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or concentrate or direct overland flow on to an
adjoining property.
Sediment and Erosion Control
12. Sediment and erosion control measures shall be in place prior to the building works. If such
measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued. Such fines
can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system or natural waterways.
5 REFERRAL AGENCY CONDITIONS
Not applicable.
Page 2 of 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SPA Decision Notice - 010.2010.00000916.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 54 KB (small file)
- File type
No other editions are linked here.