PROCEDURE C
Monitoring of Water Quality
C1. GENERAL
The procedures outlined below are provided to monitor and manage water quality in open excavations and
run-off collection in treatment areas. Contingency measures are also provided for treatment and discharge of
minor amounts of water.
C2. OBJECTIVES
Appropriately monitor waters entering open excavations
Appropriately manage waters to be discharged from open excavations
Appropriately monitor and treat (if required) run-off collected in treatment areas
Appropriately monitor groundwater to identify water quality changes that may indicate ASS impact
Comply with conditions of licences, permits or other approvals issued for the project
C3. STATUTORY REQUIREMENTS AND GUIDELINES
1) State Planning Policy – state interest guideline, Water quality, August 2014
2) Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines V4.0, 2014. Dear, S-E.,
Ahern, C. R., O'Brien, L. E., Dobos, S. K., McElnea, A. E., Moore, N. G. & Watling, K. M. Department of
Science, Information Technology, Innovation and the Arts, Queensland Government
3) Environmental Protection Act 1994
4) Environmental Protection Policy (Water) 2009
C4. IMPLEMENTATION MEASURES
The following provides a list of the environmental control measures for management of surface water and
groundwater at the site:
Water quality monitoring will be undertaken in accordance with C5
All surface water run-off and groundwater seepage within excavations is to undergo monitoring to
determine if treatment is required for quality correction prior to off-site discharge, or reuse on site
Agricultural lime or caustic soda will be kept on site at all times for pH adjusting of waters before
discharging
Discharge to surface waters, sewers or stormwater should meet with the requirements and conditions of
the disposal permit issued for the project
Two groundwater monitoring wells shall be installed external to the proposed basement excavation (one
on the northern side of the basement and one on the southern side). Groundwater monitoring wells
shall be monitored four times over a period of one month before earthworks and construction
commence to establish baseline levels of the following parameters;
Field measurements of pH, redox potential (Eh or ORP), dissolved oxygen, standing water level and
electrical conductivity (EC)
Laboratory measurements chloride, sulfate, total acidity, total alkalinity, dissolved aluminum
(filtered), and dissolved iron (filtered)
C5. INSPECTION AND MONITORING
C5 (a) Surface Water Monitoring
Waters from dewatering (if required) and all surface water run-off and groundwater seepage within
excavations shall be monitored prior to discharge during earthworks and construction works. Surface water
shall be monitored for pH, dissolved oxygen, suspended solids, oil, grease floating scum, litter and total and
dissolved aluminium and iron.
April 2019
J000799-003-R-Rev0 – Procedure C 1/3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Acid sulfate Management Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 8.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.