In addition to these measures, stockpiles and construction materials will not be stored within
the road reserve and shall be contained by downstream sediment fencing, as well as
covered when required.
3.2.1 Erosion and Sediment Control Monitoring
The control measures described above will be maintained in an effective operational
condition throughout the duration of the construction works.
Regular inspections will be carried out by the contractor and any defects in the erosion and
sediment control devices specified will be remedied as soon as practicable. Inspections to
be carried out (in accordance with the IECA Best Practice Erosion and Sediment Control
[BPESC]) are as follows:
1. Routine Inspection – is to be carried out daily while work is being carried out on site,
or weekly while works are not being carried out.
2. Preventative inspection – to be carried out before rain is forecast.
3. Reactive inspection – to be carried out after a rainfall event sufficient to mobilise
surface sediment on the site.
Documentation of any defects will also be carried out in accordance with BPESC, which
includes recording the date the defect was identified, a description of the defect, the cause
of the defect and measures that can be implemented to reduce the likelihood of the defect
occurring again. Once the device has been repaired, the date of repair and the solution
implemented will also be recorded in the documentation.
4. CONCLUSION
The assessment has described how stormwater run-off from the proposed development will
be managed to comply with the relevant requirements. In summary:
• During construction, erosion and sediment control measures will be employed as
described in Section 3.2. These measures are to be inspected and maintained
regularly during construction, as described in Section 3.2.1.
• As the site development area does not exceed the 2,500m² threshold to trigger the
requirements of SPP 2017, no stormwater quality targets are imposed on the site. It
is noted that the upgrade of the failing driveway access is expected to reduce
potential sediment and gross pollutants entering the downstream waterway by
eliminating loose material and aggregates from the run-off (refer Section 3.1).
• The development will increase the impervious area by approximately 33m² resulting
in an increase to peak runoff from the site. This increase is to be mitigated with the
provision of a 3,000L underground stormwater detention tank (refer Section 3.1).
• A new kerb adaptor in Bottlebrush Avenue is proposed as the legal point of
discharge (refer Section 3.1)
Page 5 of 8
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.