3.3 Discussion of Results

With reference to the results detailed in Table 2.1, it can be seen that the proposed
mitigation system (“Case 3”) provides effective non-worsening of discharges in
comparison to the pre-development case (“Case 1”).

This is achieved by the inclusion of Detention Basin storage. It is to be noted that
the above analysis is considered to provide conservative results for the following
reasons:

« The effects of roof water collection systems proposed to be installed at the
site have been ignored.

40 CONCLUSIONS / RECOMMENDATIONS

We consider that the above accurately, and conservatively, models the stormwater
runoff characteristics of the subject catchment. Catchment areas, and _ individual
components of the proposed water quantity treatment systems, are detailed above.

We consider that this report demonstrates no net increase in stormwater run-off
discharging from the site in comparison to the pre development case.

5.0 LIMITATIONS OF THIS STUDY

This study has been tailored to investigate issues in the context of the proposal, and at
the area of interest, being Lots 399 & 400 Elanda Street, Sunshine Beach.

Individual sub-catchments situated above, and below the area of interest, may have
different hydrological / hydraulic influences. Hence, the information contained in this
report is not to be used outside of the subject area.

We consider that the study accurately reflects the conditions for the area of interest, at
the time the study was undertaken. The results of this study should be reviewed if
catchment / proposal conditions change in the future. Where applicable, and due to their
latent nature, subsurface conditions and/or water quality monitoring results may vary
significantly across the site and/or temporally in comparison to those described herein.

Notwithstanding the above, this report has been undertaken for the specific purposes of
Oak Investment Holdings Pty Ltd (via Contour Consulting Engineers), as detailed in our
correspondence to them, and is solely for the use of Oak Investment Holdings Pty Ltd
(via Contour Consulting Engineers Pty Ltd).

This report is only to be used in full, and may not be used to support objectives other
than those set out herein, except where written approval, with comments, are provided
by Duke Environmental.

Duke Environmental accept no responsibility for the accuracy of information supplied to
them by second and third parties.

 

4A07731SMP
January 2008
ATjs

Used in these records

About this file

File size
4.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2174 - Response to Information Request [As Published].pdf · 4.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.