You or your agent must supply, install and maintain any navigation lights, buoys, marks or signs
the Harbour Master considers necessary. Any lights, buoys, marks and signs must accord with
Maritime Safety Queensland’s requirements. Upon completion of the “Stage 1” works a series of
pile beacons are to be established along the length of the submerged channel closure and at the
end of the Groyne/Training Wall Structure. The number and spacing of the pile beacons will be
determined once. The extent of the “stage 1” works has been decided.

You or your agent should note that buoys or beacons will not be established by Maritime Safety
Queensland to mark the currently dominant” Middle Channel” The decision is consistent with
Maritime Safety Queensland policy with respect to establishment of navigation aids at coastal
bars.

You must adequately light the training wall structure. The contractor must position all lighting
so it does not cause a risk to the safe navigation of other vessels.

You, or your agent, must remove any obstructions and debris encountered during the works, and
dispose of them, as the Harbour Master requires.

Any ships and equipment you or your agent use must comply with the Transport Operations
(Marine Safety) Act 1994, the Transport Operations (Marine Safety) Regulation 2004 and the
Transport Operations (Marine Pollution) Act 1995.

The dredger will always maintain full communication with Coast Guard Noosa.

The Harbour Master must be satisfied that dredging operations are conducted in a manner that
ensures a suitable navigation channel is open to vessel traffic at all times.

All floating plant, equipment and pipelines shall be appropriately lit and/or marked to the
satisfaction of the Harbour Master. Any anchors deployed to be marked with yellow buoys and
fitted with Fl Yellow lights.

All vessels and/or floating plant engaged in the dredging operation must obtain or hold a valid
Certificate of Survey or a valid permit issued by Maritime Safety Queensland pursuant to the
Transport Operations (Marine Safety) Act 1994.

Works must be completed within two years from the date of this letter. If works are not
completed, you will need additional or amended comments from the Regional Harbour Master.

Maritime Safety Queensland does not need to be further consulted if all of the above conditions are

met.

A copy of this letter has been sent to the assessment manager.

Yours sincerely

my

Captain Glenn Hale
A/Regional Harbour Master (Brisbane)

Page 2 of 2

Used in these records

About this file

File size
1.7 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

MSQ concurrence response.pdf · 1.7 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.