Geotechnical Report
5.2 Risk Assessment
5.2.1 Potential Geotechnical Hazards
Based on our site observations, assessment of existing conditions provided above, and the form of the
proposed alterations and additions, we consider that the potential geotechnical hazards for the site are as
follows:
1. Deep seated slope instability.
2. Instability of existing retaining walls.
3. Instability of temporary excavation batters.
4. Instability of proposed pool walls.
It is important to be mindful that slope instability can occur at any time and it would be difficult or impossible
to predict when the identified potential hazards will occur. Also, we cannot predict when an extreme or
unusual event may occur (such as an earthquake, or 1 in 100 year rainfall event, etc.) and what impact it
would have on the stability of the identified potential hazards described above.
5.2.2 Risk Analysis
Our geotechnical assessment of the risk of instability is based on the methodology proposed by Australian
Geomechanics Society (2007c) ‘Practice Note Guidelines for Landslide Risk Management’ (Reference 1) and
the relevant site features described above.
Risk To Property
Table A below summarises our qualitative assessment of each potential landslide hazard and of the
consequences to property should the landslide hazard occur during and following construction of the
proposed alterations and additions. Based on the above, the qualitative risks to property have been
determined.
TABLE A: SUMMARY OF RISK ASSESSMENT TO PROPERTY DURING AND FOLLOWING CONSTRUCTION
Potential Landslide 1. 2. 3. 4.
hazard Deep seated slope Instability of existing Instability of Instability of
instability1 retaining walls2 temporary proposed pool
excavation batters3 walls2
Assessed Likelihood Barely Credible Rare Rare Rare
Assessed Major Medium Minor Medium
Consequences
Risk Very Low Low Very Low Low
Notes
1. Due to slope angles deep seated instability not expected to occur.
2. Existing retaining walls assumed to be engineer designed and new pool walls designed in accordance
with the advice presented in Section 6 of this report.
3. Assuming temporary batters are formed in accordance with the advice presented in Section 6 of this
report.
36409UR 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.