Decision Notice - Approved by Delegation of Authority OPW25 0059 (As Published) · OPW25/0059
20. The following must be complied with during the construction of the required
crossover/driveway:
a. the driveway surfacing must consist of either an approved hot mixed asphaltic concrete
or patterned/plain concrete.
b. the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car
Parking for longitudinal and crossfall gradients.
c. the driveway must be constructed so as to not concentrate or direct stormwater runoff
onto neighbouring properties
d. underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway
e. where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path
f. have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
to Council.
g. any stormwater kerb outlet in close proximity to the edge of the new driveway must be
provided with an approved kerb adaptor
h. any existing kerb sections requiring removal due to the works must be saw-cut and
removed to allow for a smooth and neat finish with the new driveway
21. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer.
Stormwater Drainage
22. The constructed driveway must not cause additional ponding on the road formation or the
road reserve.
Pathways
23. All pathways must be constructed in accordance with the following requirements:
a. All footpaths must comply with Council’s Standard Drawing SEQ R-065.
b. All paths must have a slip resistant surface.
c. Expansion and contraction joints must provide a flush finish. Installation of joints by
saw cutting is preferred to ensure a smooth ride for cyclists.
d. The required work includes any modifications to ensure the footpath finishes flush with
all existing service covers and the like, or alternatively these services are raised or
altered, so as not to create a pedestrian safety hazard.
24. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety.
b. be designed and constructed to comply with the Disability Discrimination Act (DDA),
Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
access and mobility.
Environment (Erosion and Sediment Control)
25. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination.
Page 4 of 8
Document Set ID: 23772241
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority OPW25 0059 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 152 KB (small file)
- File type
No other editions are linked here.