               The applicant has requested existing condition 64 be deleted.
               Assessment of Request
               Councils Senior Development Engineer has reviewed the request and agrees with the submission.
               It is noted that future Operational works applications can include further notes/ conditions about
               Acid Sulphate Soils.
               Recommendation
               It is recommended existing condition 64 be deleted.


               Existing Condition 66b
               66b.    Bonding of the existing mature Eucalyptus tereticornis (tree 79) within the 6 metre
               setback along Serenity Close prepared by a qualified person* in accordance with an approved
               methodology such as Burnley or Thyer.
               Applicant’s Request
               The applicant indicates that this condition is a double up of the tree bonding requirement of
               condition 69 which covers all trees to be retained.
               The applicant has requested existing condition 66b be deleted.
               Assessment of Request
               Councils Senior Environment Officer agrees with request noting that a total bond of $250,000 is
               required for the development.
               Recommendation
               It is recommended existing condition 66b be deleted.


               Existing Condition 66c
               66c. A revegetation/rehabilitation plan for the 6 metre setback fronting Banksia Avenue and
               Serenity Close and the Environmental Management and Conservation Zones.
               Applicant’s Request
               The applicant submits:
               There is a potential conflict between condition 66c and condition 75. While condition 66c requires
               a revegetation/rehabilitation plan for vegetation in the Environmental Management and
               Conservation Zone, condition 75 requires that the vegetation be managed to achieve a 'low fuel
               state'. Accordingly, to remove any uncertainty and potential conflict we request that Condition 70
               [sic 66c.] be amended as follows:
               66c. A revegetation/rehabilitation plan for the 6 metre setback fronting Banksia Avenue and
               Serenity Close and the Environmental Management and Conservation Zones. The
               revegetation/rehabilitation plan must have regard to the bushfire Site Management Plan required
               by condition 75.
               Assessment of Request

                                                                                                   Page 7 of 12

Document Set ID: 23616598
Version: 2, Version Date: 05/03/2025
Log in to download the original file

Negotiated Report (Representations made) 132008 176 05 (As Published).pdf · 371 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.