NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 8
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
Landscaping
1. The site is to be landscaped in accordance with Council’s Policy on Landscaping Guidelines and the
approved Landscape Plan numbered 0525 prepared by Tom Walsh Landscaping dated August 2006 and
may be amended by these conditions.
2. The landscaping plans referred to above are to be prepared and certified by a suitably qualified and
experienced Landscape Architect or Horticulturalist.
3. The landscape construction is to be implemented in accordance with the amended landscape plan,
planting schedule and horticultural industry best practices.
4. Prior to the commencement of all works, all trees to be retained except where required to be removed due
to building operations and footpath construction must be protected with barricade fencing to prevent
damage from soil stockpiling and compaction of the root zone, parked cars and machinery
5. Further screen planting of Acmena Hemilampra and Acmena Smithii species is required along the side
boundaries adjacent to car turning bays.
6. Hymenocallis Speciosa species shall be replaced with Dianella Caerulea species.
7. All native plant species located in group plantings shall not be subjected to any hedging maintenance
regimes.
8. All trees 45 litre and greater must be securely staked and tied to assist their growth during the
establishment period
9. The density of planting must achieve the set out requirements as detailed on the approved landscape
plan.
10. The applicant must ensure that all landscaping treatment does not unduly restrict/prevent access to
service meters within the site.
11. All trees must be located a minimum of a minimum of 1.0 metres from all services to prevent root/service
conflict and to provide future ease of maintenance requirements
12. All manholes, inspection pits and grates are to be raised to finished surface levels and kept free of cover
and be visible at all times to ensure prompt access in case of emergency.
13. This Development Permit lapses if the development has not happened by 10 August 2009, unless
application to extend the currency is approved by Council.
Land Development
14. The development shall be carried out in accordance with Engineering drawing No. 16078-OW1B dated 4
July 2007 by SCG Consulting Engineers or as modified herein.
15. Roof and surface runoff connection to Council’s kerb and channel shall be as shown on drawing No.
16078-OW1B dated 4 July 2007 by SCG Consulting Engineers. Kerb adaptors shall be used in the kerb.
16. The applicant shall ensure that no damage or disturbance occurs to the adjoining buildings and/or
structures and/or land. In this regard a suitably qualified Geotechnical Engineer shall supervise all
excavation and stabilisation works.
17. The Conditions Survey report of the adjoining structures and the associated monitoring plan as described
in Condition 45 of the Decision Notice File No: 2006/138 shall be submitted to Council prior to the “pre
start” meeting.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@3001d0f4\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0015CE09.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2006.00001101.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 33 KB (small file)
- File type
No other editions are linked here.