NOOSA COUNCIL IDAS Development Application Decision Notice 4 of 8
18. A bikeway/footpath 1.5 metres wide shall be constructed across the full frontage of the development. The
footpath shall have a slip resistant surface. The alignment, of which, shall be determined on site with
Council’s Construction Technical Officer. The expansion joints in any bikeway/footpath shall be “sawcut”
not trowel jointed.
19. To ensure Council’s sewer main is accessible for maintenance purposes and is protected from risk of
damage no structures requiring a building permit (eg. buildings, swimming pools, dividing walls exceeding
1m in height, raised terraces, etc) shall be constructed within this ‘zone of influence’ or within 1.5m of the
centreline of the sewer main, whichever is the greater. In this regard the existing sewer main that
traverses the site at the rear and the ‘zone of influence’ (taken as the area within a 45-degree angle
measured from the invert of the sewer main to the finished surface level) shall be accurately located,
determined and marked on site by a Licensed Surveyor prior to the commencement of any works.
20. Suitable root barrier shall be installed where proposed trees are adjacent to paths, pavement etc in
accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and Guidelines.
21. The turning areas located on either side of the access driveway shall be suitably sign posted to indicate
that the area is a “Turning Area Only” and that “No Parking is Permitted”.
22. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily installed into the
first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each rain event.
These devices are to remain in place during the civil works and construction phases of the development.
The location and type of device to be installed shall be established at the “pre start” meeting with
Council’s Construction Technical Officer and shall be installed prior to the commencement of any works.
23. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’ notice of
intention to commence works to arrange a “pre start” meeting regarding the civil works.
24. The principal contractor must have all the appropriate insurance and public liability documentation to carry
out the works. The principal contractor is also responsible to ensure that any sub contractors also have
the appropriate insurance and public liability documentation.
25. Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council’s
signed approved drawings and conditions by the applicant.
26. The Consulting Engineers for the project shall be currently Registered Professional Engineers of
Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
Council’s Construction Technical Officer or nominated staff.
27. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
(This person will be the contact for the project).
28. Council standards shall apply to these works unless otherwise modified herein.
29. The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
during the construction of the engineering works to ensure that Council property, road pavements or
facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
furniture etc.) are protected against any damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
Development and shall forthwith rectify the damage to that property or facility at its cost and to the
satisfaction of the Manager Land Development.
All rectification works are to be completed prior to the commencement of the use or, alternatively, the
Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
being paid by the Applicant to the Council prior to the commencement of the use.
In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
Applicant, such cost being paid prior to the commencement of the use.
30. The development of the site shall be carried out in such a manner as to prevent dust and/or sand
nuisance to residents and/or tenants in the vicinity of the development.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@3001d0f4\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0015CE09.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2006.00001101.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 33 KB (small file)
- File type
No other editions are linked here.