Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED]

of 20

Page text shows just the words. Original shows the document exactly as it was published.

                 69.    Storm water retention systems, gross pollutant traps and bio-retention basins must
                        maintain a minimum clearance of 1.5 metres from Council water supply and sewerage
                        infrastructure.
                 70.    Landscape planting within 1.5 metres of Council sewerage infrastructure must be
                        Council approved varieties and low growing when mature.
                 71.    The level of the existing sewer manholes must be adjusted to suit the proposed finished
                        surface levels. Work must be undertaken by Sunshine Coast Water at the applicants
                        cost.
                 72.    Landscape planting within 1.5 metres of Council sewerage infrastructure and 1.0 metres
                        from water supply infrastructure must be Council approved varieties and low growing
                        when mature.
                 73.    Construction works undertaken in the vicinity of Council water supply or sewerage
                        infrastructure must not adversely affect the integrity of the infrastructure. All costs
                        associated with repair, replacement or alteration of infrastructure must be met by the
                        applicant.
                        Service Easements (Sewer / Stormwater)
                 74.    A 3.0 metre wide easement must be provided over all Council sewers located in private
                        property that are not covered by an existing easement. A 4.0 metre wide easement
                        must be provided over Council sewers greater than 3.0 metres deep (where approved
                        by Council). Easements must be located centrally over the main.
                 75.    A registered easement shall be created over any stormwater drainage pipes within the
                        site that collect stormwater from a Council road or convey stormwater from any adjoining
                        property (for example, where drainage pipes are provided within the site to prevent
                        adjacent properties from additional ponding/flooding due to the subject site being filled).
                 76.    No building or other structure shall be constructed or encroach into an easement.
                        Construction Issues
                 77.    A Traffic Management Plan for the each construction phase of the development shall be
                        submitted to and approved by Council at least 5 working days prior to the
                        commencement of any Building works or at least 5 working days prior to the pre-start
                        meeting for Operational Works. The Traffic Management Plan shall be referred to the
                        Divisional Councillor for comment before approval and shall include but not be limited
                        to:
                        a.     Limiting the routes for the heavy vehicles to the major road network and prohibit
                               the use of the local roads as access to the site.
                        b.     Indicate provision for on-site and off-site parking for the required workforce.
                        c.     Indicate the location of loading and unloading areas.
                        d.     Indicate the location of any “holding” areas for heavy vehicles, and
                        e.     Operating hours.
                        f.     Maintaining clear pedestrian access around the site at all times.
                 78.    Construction staff shall not park on Serenity Close or elsewhere on-street. Parking shall
                        either be on site, an adjacent vacant site or at a suitable off-site location serviced via a
                        shuttle bus.
                 79.    A detailed Condition Survey must be carried out on existing structures, services,
                        adjacent buildings and roads prior to any excavation or construction works taking place
                        on site. If distress already exists, a photographic survey should be undertaken, the
                        distress measured and a plan to monitor changes to distress shall be implemented.




Document Set ID: 23307313
Version: 3, Version Date: 24/10/2024                                                                      Page 10 of 20
Log in to download the original file

Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED].pdf · 225 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.