Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED]
Remediation of any damages caused by construction of this development shall be
undertaken within 3 months of the completion of substantial works for this development.
80. Any significant dust and dirt accumulating on adjoining buildings as a result of this
development shall be removed at the end of substantial works if requested by the
affected bodies corporate.
Earthworks
81. Filling works required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or the blockage of, or interference with, any
natural watercourses.
82. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences and/or structures and/or lands that border the development site. Fences that are
affected shall be replaced prior to the Building Certifier issuing the Certificate of
Classification. In this regard any fences to be replaced shall be clearly shown on the
plans submitted for Operational Works approval.
83. Plans and details outlining the extent of earthworks required on site and any trees to be
retained shall be submitted to Council for approval prior to obtaining a Development
Permit for Operational Works.
84. All major excavations (including the basements and driveways) shall be shored to
prevent batters extending into areas and vegetation to be retained. All tress to be
retained shall be adequately tagged to Council’s satisfaction and enclosed with a barrier
fence to the drip line to prevent damage.
Acid Sulfate Soils
85. As the site is located below the 20m AHD and above the 5m AHD, any excavation works
consisting of 100m3 or greater which extends below 5m AHD must be carried out in
accordance with State Planning Policy 2/02 Planning and Managing Development
Involving Acid Sulfate Soils. In this regard appropriate testing and supporting
documentation prepared by a suitably qualified specialist shall be submitted to Council
for approval prior to obtaining a Development Permit for Operational Works.
Site Stability
86. A Geotechnical Engineer or similar qualified expert shall assess the soil condition on
site, determine the soil classification, establish whether any measures are required to
protect the stability of adjoining buildings and/or structures and/or land, and make
recommendations on the type of foundation system(s) best suited for the proposed
development. The recommendations of this report shall be incorporated into the design
and construction of the proposed development.
Erosion and Sediment Control
87. Any person acting on this permit shall prevent erosion and sediment export from leaving
the site. Site control measures such as silt fencing, controlled gravel access to the site
and controlled disposal of waste, will be necessary.
Plans detailing the methods of controlling erosion and sediment are required to be
submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
Contributions Towards Council Infrastructure
88. The applicant must pay contributions towards trunk infrastructure in accordance with the
following Planning Scheme Policies and Council Policies:
a. Planning Scheme Policy 12 – Public Open Space Contributions;
Document Set ID: 23307313
Version: 3, Version Date: 24/10/2024 Page 11 of 20