Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED]

of 20

Page text shows just the words. Original shows the document exactly as it was published.

                 7.     Any rooftop plant or mechanical equipment extending more than 1 metre above the
                        roofline shall be screened using lightweight screening materials that visually integrate
                        with the building design.
                 8.     Balustrade materials visible from the street frontages shall be clear or translucent.
                        Amended Plans
                 9.     Prior to the issue of a Development Permit for Operational Works amended plans shall
                        be submitted for Council Approval indicating:
                        a.      The 3rd and 4th storeys of the development shall be amended to remove the
                                encroachment within the 10 metre setback to the Banksia Avenue frontage and at
                                the corner of Serenity Close and Banksia Avenue.
                        b.      The basement car parking level adjacent the corner of Serenity Close and Banksia
                                Avenue shall be amended to provide a minimum 6m setback to the frontage to
                                allow for deep plantings to be established.
                        Building Height
                 10.    The finished height of the building, including any rooftop plant or structures, shall not
                        exceed 15 metres above natural and finished ground levels.
                 11.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
                        certificate lodged with Council at completion of work confirming compliance with the
                        maximum allowable building height as required by either the conditions of approval or
                        the Planning Scheme.
                        Operating Hours & Deliveries
                 12.    The restaurants and bar are to operate between the hours of 6am and 12pm only.
                 13.    Business deliveries are to be undertaken between the hours of 6am to 7pm Monday to
                        Saturday and 8am to 5pm Sunday only.
                 14.    Service vehicles shall not attend the site outside the hours of 8am to 5pm.
                        Vegetation
                 15.    Existing trees on the site and within road reserves are to be retained except where
                        required to be removed due to building operations, requirements of the approved
                        Settler’s Cove Management Plans or the conduct of the approved use.
                 16.    The Koala and Glossy Black Cockatoo habitat trees identified for retention on plan L-
                        SD-1.01 (Rev. A) dated August 2009 by DBI Design Pty Ltd shall be retained.
                 17.    The existing Koala and Glossy Black Cockatoo habitat trees and any other trees within
                        setback and open space areas to be retained must be protected. As building works are
                        likely to impact the trees’ root zones, a qualified Arborist (having a minimum Diploma of
                        Arboriculture or ISA certification and a minimum of three years’ field experience) must
                        be contracted to prepare a Tree Management and Protection plan and shall:
                        a.      oversee installation of a hard temporary protection zone prior to commencement
                                of works with ‘no go’ signage in accordance with AS 4970-2009. All site workers
                                must be inducted in relation to the tree protection;
                        b.      supervise any works within the temporary protection zone;
                        c.      undertake hazard reduction and formative pruning as necessary; &
                        d.      provide certification that the trees were protected in accordance with the Arborist’s
                                recommendations.
                        The Tree Management and Protection Plan Shall be presented prior to or at the pre-
                        start meeting for the site.




Document Set ID: 23307313
Version: 3, Version Date: 24/10/2024                                                                       Page 3 of 20
Log in to download the original file

Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED].pdf · 225 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.