Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED]

of 20

Page text shows just the words. Original shows the document exactly as it was published.

                        The Arborist shall monitor the health and structural integrity of the trees to be retained
                        at least monthly during the construction period and quarterly for 12 months after
                        construction is completed. The developer shall rectify any decline in the health or
                        structural integrity of the trees, in accordance with the Arborist’s recommendations.
                 18.    Cleared vegetation is to be suitably processed by one of the following methods and
                        removed from the site:-
                        a.      Re-use for building materials.
                        b.      Processing through a woodchipper or shredder. The resulting mulch is to be
                                stockpiled loose in heaps of less than 1000 cubic metres, less than 2.5 metres
                                high with a minimum of 10 metres between edges of heaps.
                        c.      Disposal for firewood.
                        d.      Disposal for landscaping purposes.
                        e.      Transport to alternative site for breaking down materials provided that all
                                necessary permits have been obtained to allow the alternate site to be used for
                                this purpose.
                        The disposal method for clearing works is to be submitted in conjunction with an
                        application for a Development Permit for Operational Work. The Applicant is advised
                        that other methods may be considered provided full details of the method are submitted.
                        The Applicant is advised that burning off is an unacceptable method of disposal.
                        Fauna Spotter
                 19.    The Applicant must conform to the requirements of the Fauna Management Plan
                        Settler’s Cove Development Pty Ltd, May 2005, (or later updated and approved
                        versions) and implement particularly section 3.4, and section 4.2. A fauna spotter shall
                        be employed to oversee the removal of any native trees within the site. Prior to felling or
                        lopping all trees are to be checked for wildlife (eg. koalas, cockatoos, possums). If
                        wildlife species are present, the tree shall not be felled or lopped until the wildlife has
                        left the tree.
                        Landscaping
                 20.    The open space and setback areas are to be landscaped in accordance with Council’s
                        Policy on Landscaping Guidelines and a properly prepared Landscape Plan prepared
                        by a suitably qualifies Landscape Architect or Horticulturalist. Such landscaping is to be
                        completed prior to the premises being occupied and maintained at all times thereafter.
                        The Landscaping Plan shall include the following:
                        a.     Koala and Glossy Black Cockatoo food trees in accordance with the associated
                               Environmental Protection Authority (EcoAccess) approval conditions for the site
                               and the approved Settler’s Cove Ecological Restoration Plan and Landscape
                               Master Plan.
                        b.     Locations of nesting boxes for Glossy Black Cockatoos shall be indicated on the
                               landscape plans and installed on existing trees to be retained.
                        c.     Vegetation to adequately screen and provide filtered views of the development,
                               including as viewed from Serenity Close and Banksia Avenue, and shade
                               hardscaped areas, with plantings to include significant canopy trees.
                        d.     A minimum of twenty-five (25) native trees of a minimum bag size of 400L to
                               replace existing trees to be removed the site’s frontage.
                        e.     Street trees to the frontage of the site at appropriate centres and to provide shade
                               to any existing pathways.




Document Set ID: 23307313
Version: 3, Version Date: 24/10/2024                                                                     Page 4 of 20
Log in to download the original file

Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED].pdf · 225 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.