SERVICES & ORGANISATION COMMITTEE MEETING REPORT 8 FEBRUARY 2022
in the traffic flow and car parking. The site is home to up to nine community sporting
organisations with a combined membership of approximately 3,000 members.
The Noosa District Sports Complex Master Plan (NDSCMP), endorsed by Noosa Council on
13 January 2020, recommends the development of an internal road network providing
through road access in the sports complex. The proposed road alignment (relocated to the
western side of the existing fields) will significantly improve traffic flow and eliminate
pedestrian-vehicle conflict on the site, improve car parking access within the site and provide
safe pedestrian and cycle connectivity through the complex. Works include the realignment
of rugby league and touch football fields, roadworks, pathways, car parking, drainage works
and landscaping.
These works form the integral first stage of the delivery of the NDSCMP and must be
completed prior to any of the other works commencing.
2. Estimates
Concept designs were complete in 2020/2021 and detailed design has been completed in
2021/2022. Preliminary estimates prepared in early 2020 as part of the concept design
development put the project costs at approximately $2.7m. This figure is currently being
reviewed by a quantity surveyor as it does not include an increase due to the current heated
construction market which can conservatively be estimated at an 8.885% increase in
materials and resources in building construction costs as provided by the Non-Residential
Building and Construction PPI (Sept 2021).
3. Funding
Building Better Regions Funding Round 6 has been released which provides the opportunity
to gain a 50% contribution toward the completion of this project.
Previous Council Consideration
Nil
Finance
The following table provides a summary of the financial amendment requested pending a
successful outcome of the grant funding application:
Budget Funding 2022/2023 2023/2024 Total
Current Budget Council Contribution $900,000 $- $900,000
Proposed Budget if Council Contribution $900,000 $600,000 $1,500,000
application is BBRF Contribution $900,000 $600,000 $1,500,000
successful Total Project Costs $1,800,000 $1,200,000 $3,000,000
Risks & Opportunities
Risks
1. Not proceeding will increase safety risks at the site during peak usage times with potential to
result in possible injury to users.
2. Not proceeding will result in a higher cost to council to deliver this project in future years
Opportunities
1. If successful, the grant funding will reduce Council financial commitment to complete this project
by 50%
2. Improve the safety, accessibility and functionality of a site with high usage
Page 22 of 71
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.