Original source · versioned page text
Attachment C_R.B23636.001.02.SEMP_final_lowres
Very large file (26.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Noosa Spit SEMP Final Report 99
Proposed Implementation Pathway
5.2 Proposed Trigger-based Management Approach
In the context of the current project, the unacceptable impact is a breakthrough of Noosa Spit at Dog
Beach. Two triggers for enhanced management action are proposed:
• Tigger 1: Limited recreational beach width at Dog Beach and loss of vegetation (fallen trees)3
• Trigger 2: The width of vegetated land above high water has narrowed to 20 m or less
Upon realisation of the first trigger, implementation of beach nourishment and sand plugs (i.e. the
preferred option based on the MCA presented in Section 4.3) is proposed. This action is intended to
remain the preferred management strategy until it is no longer sustainable and/or delivering benefits
to Council and the community. It is anticipated that the works would be repeated several times
between now and 2040 and help to mitigate the risk of a breakthrough event.
The second trigger represents significant narrowing of The Spit width at Dog Beach and signals that
the beach nourishment strategy is not performing as intended. A notional 20 m width of land above
the high water mark represents the likely minimum development footprint required for land-based
construction of a seawall or similar shoreline protection structure. The trigger-based approach is
designed to avoid a seawall for as long as possible and only calls for consideration of this action if
beach nourishment is unable to maintain the risk of a breakthrough at an acceptable level.
The three key stages of a proposed implementation plan are summarised in Table 5-1 and illustrated
in Figure 5-2. The proposed actions are triggered when the approved activities of the current stage
of management are no longer maintaining the risks to an acceptable level. The ongoing beach
monitoring program and visual inspection of the shoreline can be used to assess the current stage
of management and determine whether planning for subsequent actions should commence. Stage
2 of the proposed plan could commence immediately, with the current condition of the shoreline
suggesting that Trigger 1 has been reached (see bottom panel of Figure 5-2). Implementation of the
proposed beach nourishment and sand plugs would effectively widen the beach and monitoring
would then focus on identifying when the Trigger 1 condition returns, thereby prompting the planning
for a subsequent nourishment and sand plug campaign to reinstate the beach width. Ongoing
resilience building actions, including revegetation and habitat management, are expected to continue
as part of routine maintenance.
3
The Trigger 1 shoreline position is approximated in Figure 5-2 using the HAT contour in 2016
G:\Admin\B23636.g.mpb.NoosaSpit_SEMP\R.B23636.001.02.SEMP_final.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.