63. In order to protect the vegetation within the Vegetation Protection Area an Environmental
Covenant(s) (as defined by Part 6 division 4A of the Land Title Act 1994) shall be created at
no cost to Council. The covenant(s) shall be for the protection of the site’s environmental
values so that it retains and enhances the vegetation and allows for fauna movement.
64. The existing vegetation within the 10m wide Landscape Buffer areas adjacent to the western,
northern and eastern boundaries shall be retained, with the exception of any bio-retention
basins, raingarden areas or rainwater tanks, and a 3metre strip adjacent to the buildings for
construction purposes. Plans shall be submitted to the Council for approval that clearly
indicates the vegetation retention areas prior to obtaining a Development Permit for
Operational Works. Temporary fencing shall be provided to protect these trees during the
construction phase.
65. Where retained trees are located in areas proposed to be filled on the site (or are located on
neighbouring allotments to the area to be filled), there will be a need to prevent fill material
from being placed on the tree’s root system. To this end, the design of any filling works will
need to incorporate terracing around the tree or a similar means of ensuring that the natural
ground level around the trees remains generally the same as existing. These measures shall
clearly be shown on the plans submitted for Operational Works approval and any drainage
required to drain these areas shall also be shown on the plans.
66. An environmental maintenance period of 12 months shall commence after the Landscaped
area has been re-vegetated and all declared & environmental weeds have been removed from
the entire property. Council’s appointed Environmental Officer shall sign the maintenance
period ‘on’ and ‘off’ after this work has been successfully completed. To this extent, the
Officer has the discretion to pause the maintenance period if work has not been carried out as
instructed or if lengthy time delays occur.
Erosion and Sediment Control
67. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
Contributions Towards Council Infrastructure
68. Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
upgrading various infrastructure at the rates applicable at the time of payment. An estimate
only of the contribution amounts under the current Council policies and requirements is
outlined in the table below:
Contribution Required For: Amount:
PSP12 – Public Open Space Contributions (Park) $13,086
PSP16 – Sewerage Headworks Contributions $31,492
PSP17 – Water Supply Headworks Contributions $27,331
PSP20 – Pathway Trunk Network Contributions $13,911
TOTAL Contribution Amount = $ 85,820
Please note, that these amounts are all subject to variations in the Consumer Price
Index, All Groups Brisbane from March 2008 until the date of payment.
Page 9 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00000738.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 185 KB (small file)
- File type
No other editions are linked here.