Hydraulic Assessment 29 August 2024
Attached to the e-mail Operational Works Application OPW25/0049 - Cover Letter, DA Form 1, Hydraulic Assessment 29 August 2024 - 38 Barina Ct_ Pomona - Email 1 of 2.
To maintain the integrity of the spillway and prevent any potential obstructions or weakening of the structure, it is required to trim or remove
tree roots that have encroached upon the existing spillway area. Uncontrolled growth of vegetation can undermine the structural soundness
of the spillway, reducing its effectiveness and increasing the risk of overtopping. Regular maintenance should be conducted to ensure that
the spillway remains clear and fully operational at all times.
The design of the spillway should incorporate a minimum base width of 1 meter to effectively handle the expected flow of water. Additionally,
the spillway should have side batters with a minimum slope of 1:2 (vertical to horizontal). This ensures structural stability and facilitates the
safe passage of water through the spillway during peak discharge events. The maximum level of the spillway overflow should be 111.24 m
AHD, to ensure the 1m dry freeboard is maintained.
3.2.1.2 Spillway Channel Protection
It is proposed to incorporate dumped rock into the spillway and channel outlets to prevent erosion as a result of concentrated lateral flow
through the spillway. The principal design features and adopted rock protection of the downstream channel is summarised below for two
options:
(1) Maintain the existing channel profile with 1m base width; and
(2) Widen the base of the channel to 2m width – the purpose of widening the base is to reduce the required d50 and dumped rock
thickness.
Table 3.5: Spillway Channel Design Parameters
Parameter Result
Design Discharge 2.88 m3/s
Batter Slopes 1H:2V
Longitudinal Grade 10 %
Option 1 – Maintain 1m base width
D50 Rock Dimension 500
Dumped Rock Thickness 1000
Option 2 – Increase base width to 2m
D50 Rock Dimension 300
Dumped Rock Thickness 600
Energy dissipation at the outlet of the spillway channel is provided by a batter chute outlet structure. The rock pad has been designed to
control soil erosion adjacent to the outlet and to dissipate the flow energy, with parameters informed by the TUFLOW hydraulic model
results.
Table 3.6: Rock Pad Design Parameters
Parameter Result
Velocity of Flow into Outlet Structure 5.0 m/s
Depth of Approach Flow 0.30 m
Mean Rock Size, d50 400 mm
38 BARINA COURT, POMONA I BBNE00000_0020-REP-001-0 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.