Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

2019-06-11 Services & Organisation Committee Agenda

of 109

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (16.3 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

SERVICES & ORGANISATION COMMITTEE MEETING AGENDA                                           11 JUNE 2019


REPORTS FOR CONSIDERATION OF THE COMMITTEE

1                        1718T129 - NOOSA NORTH SHORE CAMPGROUND REFURBISHMENT - STAGE 1
                         CONSTRUCTION
DOCUMENT INFORM AT ION




Author                             Project Officer, Paul Brennan
                                   Infrastructure Services Department

Index                              ECM / Projects (T1) / Noosa North Shore Beachfront Campground – Cap.
                                   Work 500661
                                   ECM / Project and Contract / 1718T129
                                   ECM / Subject / Project Management / Council Properties

Attachments                        1.   Noosa North Shore Campground Refurbishment – Stage 1 Works
                                        Tender Evaluation



EXECUTIVE SUMMARY
Not applicable.

RECOMMENDATION
That Council note the report by the Project Officer to the Services & Organisation Committee
Meeting dated 11 June 2019 and award tender 1718T129 for the construction of the Noosa North
Shore Beachfront Campground Refurbishment - Stage 1 works to Midson Construction (Qld) Pty
Ltd for the lump sum price of $2,275,678 excluding GST.

REPORT
1.                       Master Planning and Design

Council undertook a master planning exercise for the Noosa North Shore Campground in 2016.
Several options were developed for refurbishing and upgrading the facilities based around a
number of desired outcomes, including (amongst others) the need to improve some long-term
dilapidated environmental elements, respond to changing camping and caravanning customer
expectations and demographics, adjust property boundaries via State Government approval to
capture actual campground space usage, and provide a long-term strategy for the provision and
management of water and wastewater infrastructure that better satisfies customer demand and
environmental constraints for a site located within the Great Sandy National Park.

At the conclusion of this master planning process a preferred option for campground
refurbishment works was selected that recommended a specific mixture of asset renewal and the
provision of new and upgraded infrastructure, based on ensuring a required return on investment
for the business activity. In 2017 a detailed design process using specialist consultants
commenced to capture the outcomes of the preferred option, and this concluded in July 2018.

2.                       Lot Boundary Revocation and Realignment of Southern Boundary

A Material Change of Use (MCU) was approved by Council in August 2017 in order to allow the
process of negotiating the adjustment of the property boundaries to progress with the State
Government. The intent of these negotiations is to formally move the southern boundary of the
site south into national park land to best reflect the historical camping area, and adjust the
eastern boundary westwards to remove the majority of sensitive coastal dune land from camping
and allow revegetation work in these areas.

                                                                                            Page 3 of 109
Log in to download the original file

2019-06-11 Services & Organisation Committee Agenda(PDF, 16MB).pdf · 16.3 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.