Skip to the record
The first. The best. The only NoosaWatch™.

Original source · versioned page text

Mcu

Attached to the e-mail MCU19/0013 - Withdraw Representations.

of 22

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Noosa Council documents




                                                              Officer:            Billy Glover
                                                              Direct Telephone:   53296109
                                                              Our Reference:      MCU19/0013 & RAL19/0003
                                                              Your Reference:     n.a

               9 May 2019


               RF Erharter
               C/- Pivotal Perspective Pty Ltd
               4/59 Mary St
               NOOSAVILLE QLD 4566
               [email protected]



               Dear Sir
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 9 May 2019, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU19/0013 & RAL19/0003

                   Street address:              10 Opal St Cooroy Qld 4563

                   Real property description:   Lot 6 RP 82318

                   Planning Scheme:             The Noosa Plan (8 June 2018)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
                      Development Permit for Material Change of Use - Multiple Housing - Type 2 Duplex
                      Development Permit for Reconfiguration of a Lot - Community Titles Scheme (2 Lots)
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval for Material Change of Use and Reconfiguring
               a Lot is 6 years starting the day that this development approval takes effect.
               4.      ASSESSMENT MANAGER CONDITIONS

                                                      Material Change of Use
               PLANNING
                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use commencing, and then compliance maintained at all times while the use continues.




                                                PO Box 141                 P. (07) 5329 6500      [email protected]
                                                TEWANTIN QLD 4565          F. (07) 5329 6501      www.noosa.qld.gov.au
                                                                                                                Page 1 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                         Print Date: 13 May 2019, 4:45 PM
Log in to download the original file

MCU.pdf · 4.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 21 pages

Page 2

Noosa Council documents




                      Approved Plans
               2.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                          Plan No.             Rev.   Plan/Document Name                            Date

                          -                    -      Site, Subdivision and           Preliminary 29/01/2019
                                                      Services Layout Plan
                                                      As annotated by Council

                          V.1 – 29.04          -      Site Cover Plan,        drawn    by    Toth 10/04/2019
                                                      Environmental

                          GJGSCN190173 2       E      Site Plan, drawn by G. J Gardner Homes        17/01/2019

                          GJGSCN190173 3       E      Lower Floor Plan, drawn by G. J Gardner 17/01/2019
                                                      Homes

                          GJGSCN190173 4       E      Elevations, drawn by G. J Gardner 17/01/2019
                                                      Homes

                          GJGSCN190173 6       E      Roof Catchment Plan, drawn by G. J 17/01/2019
                                                      Gardner Homes

                      Nature and Extent of Approved Use
               3.     Both dwellings must be fully constructed prior to the issue of the Plan Seal approval for the
                      Community Titles Scheme.
               4.     The total site cover of the development must not exceed 40%.
                      Building Height
               5.     The maximum height of the development must not exceed 8 metres above the finished
                      ground level and the natural ground level.
                      Performance Bond
               6.     Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must
                      be submitted to Council, to secure performance of all conditions of this approval, prior to the
                      issue of a Development Permit for Operational Works. The cash bond or trading bank
                      guarantee will be returned on performance of the conditions of approval less any costs
                      incurred by Council in respect of enforcing performance of this permit. Council reserves the
                      right to call upon the bond or guaranteed sum to effect compliance with conditions.
                      Screening Vegetation
               7.     Screening vegetation must be planted along the eastern boundary for the extent of the new
                      dwelling on the new lot 2, in accordance with PSP 3 Landscaping Plants and Guidelines and
                      an Operational Works approval.
                      Water & Sewer Connections
               8.     An underground connection to reticulated water and sewerage must be provided to the
                      development site in accordance with the standards and requirements of Northern SEQ
                      Distributor–Retailer Authority (Unitywater).
               9.     A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the development site.




                                                                                                        Page 2 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                 Print Date: 13 May 2019, 4:45 PM

Page 3

Noosa Council documents




                      Building Appearance
               10.    All air conditioning units or other mechanical equipment must be located at ground level, or
                      otherwise fully enclosed or screened such that they are not visible from the street frontages
                      nor adjoining properties.
                      Roof Form
               11.    Eaves on the new dwelling unit must be 600mm in width. 450mm wide eaves will achieve
                      this solution provided there is a 150mm wide gutter that brings the total width to 600mm.
                      Protection of Privacy
               12.    To ensure privacy is protected between adjoining properties, any window/s, deck or the like
                      that overlooks or has the potential to overlook the private open space or habitable room
                      windows of neighbouring properties must either:
                      a.      have a minimum window sill height or 1.5 metres above floor level.
                      b.      be fitted with translucent glazing.
                      c.      be fitted with a fixed external screen positioned in such a way to obscure direct view.
                      Fencing and Walls
               13.    Any street fencing must be set back an average of 1 metre from the front property boundary.
                      Any fencing on the front boundary must either:
                      a.      not exceed a maximum height of 1.2m.
                      b.      be of open construction.
               14.    The area of land between the fence and the front property boundary must be densely
                      landscaped to screen any fencing from the street.
               15.    The existing fence along the Opal Street frontage may be retained, however any future
                      fencing must comply with the fencing and walls conditions of this Decision Notice.
                      Clothes Drying Areas
               16.    Each dwelling unit must be provided with access to an outdoor clothes line which is screened
                      from public view.
                      Community Management Statement
               17.    Any proposed Community Management Statement required for the development pursuant to
                      the Body Corporate and Community Management Act 1997 must be submitted to Council for
                      endorsement at the same time as submission of the Building Format Plan (or similar) to
                      Council for compliance assessment.
               18.    All clauses and by-laws of the proposed Community Management Statement must accord
                      with the requirements of this Decision Notice.
                      External Works
               19.    Opal Street must be upgraded for the length of its frontage to the subject site. The works
                      must be undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      kerb and channel on an alignment that is an extension of the existing kerb and channel
                              to the west of the subject site and joins smoothly to the kerb and channel to the east of
                              the site
                      b.      widening and sealing of the existing road pavement
                      c.      any necessary adjustments or modifications to the existing surface and piped
                              stormwater drainage systems in Opal Street
                      d.      any necessary adjustments to the existing property access




                                                                                                          Page 3 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                   Print Date: 13 May 2019, 4:45 PM

Page 4

Noosa Council documents




                      In this regard, specifications and plans detailing this work must be prepared in accordance
                      with Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
                      Drainage and Earthworks.
                      Site Access and Driveways
               20.    A sealed access driveway must be provided from Opal Street and Opal Lane to all parking
                      and manoeuvring areas of the development. The works must be undertaken in accordance
                      with an Operational Works approval and must include in particular driveway crossovers
                      generally in accordance with Council’s Standard Drawings RS-049 and RS-050.
                      Stormwater Drainage
               21.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge.
               22.    All stormwater drainage (including roof water overflow from the rainwater storage system)
                      must be collected and discharged so there is no net increase in stormwater runoff from the
                      site. The works must be undertaken in accordance with an Operational Works approval and
                      be generally in accordance with the Proposed Duplex Integrated Water Management Plan –
                      Version 0 dated April 2019 prepared by Callaghan & Toth Civil, Environmental and Hydraulic
                      Engineers.
                      Electricity and Telecommunication Services
               23.    Reticulated electricity and telecommunication services must be provided to each lot in
                      accordance with the standards and requirements of the relevant service provider.
               24.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               25.    Certification must be submitted to Council from all relevant service providers which certifies
                      that the development has met the requirements of this Decision Notice and all applicable
                      legislation at the time of construction.
                      Easements
               26.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               27.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               28.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               29.    All earthworks and associated batters/walls must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.
                      Damage to Services and Assets
               30.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.



                                                                                                       Page 4 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                Print Date: 13 May 2019, 4:45 PM

Page 5

Noosa Council documents




                                                         Reconfiguration of a Lot
                      When Conditions Must Be Complied With
               31.    Unless otherwise stated, all works required by the conditions of this Decision Notice must be
                      completed prior to submission of the subdivision plan to Council for compliance assessment.
                      Approved Plans
               32.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                           Plan No.              Rev.   Plan/Document Name                            Date

                           V.1 – 29.04           -      Site Cover Plan,         drawn    by   Toth 10/04/2019
                                                        Environmental

               33.    All lot numbering on the subdivision plan to be submitted to Council for compliance
                      assessment must remain as shown on the Approved Plans.
               34.    The development must be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
                      lighting nuisance or other emissions.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

                      Building and Construction Industry (Portable Long Service Leave) Levy
               1.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
                      Co-ordination of Operational Works Assessment
               2.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
                      Preparation of a Preliminary Construction Management Plan
               3.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      b.      provision for safe pedestrian access across the frontage of the site both during daily
                              construction and after daily construction has ceased.
                      c.      traffic management during all aspects of the construction phase including:
                              i.       a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction.
                              ii.      maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased.
                              iii.     proposed fencing to the site during the construction phase of the development.
                              iv.      approval of the Traffic Management Control Plan by the Department of Transport
                                       and Main Roads (DTMR) for any works on State controlled roads.



                                                                                                          Page 5 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                   Print Date: 13 May 2019, 4:45 PM

Page 6

Noosa Council documents




                              v.       provision for worker car parking.
                      d.      maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures.
                      e.      works programme identifying key components of the works and their respective
                              durations.
                      f.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic, services and other relevant issues.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager.
                              ii.      dispute resolution procedures.
                      h.      it is acknowledged that the preliminary Construction Management Plan will be a draft
                              document requiring finalisation upon appointment of the Principal Contractor employed
                              to construct the works and a final document will be required to be submitted at the Pre-
                              Start Meeting for the project.
                      Community Title Scheme - Private Infrastructure
               4.     All private infrastructure for the development must be designed to meet the planning scheme
                      requirements unless otherwise agreed by the relevant authority.
                      Infrastructure Charges
               5.     This Development Permit will trigger an “Infrastructure Charge Notice” to be issued in
                      accordance with Council’s “Charges Resolution” made pursuant to the planning legislation
                      and regulations current at the time of issue.
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.
               9.     FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required                     Subject of the required Development Permit

                Development Permit for Operational Works                Frontage Works,      Access,   Landscaping        &
                                                                        Stormwater

                Development Permit for Building Works                   All building works

                Compliance Certificate                                  Plan Sealing

               10.    SUBMISSIONS

               Not applicable.
               11.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If




                                                                                                            Page 6 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                     Print Date: 13 May 2019, 4:45 PM

Page 7

Noosa Council documents




               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.




                                                                                                  Page 7 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                           Print Date: 13 May 2019, 4:45 PM

Page 8

Noosa Council documents




               12.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Billy Glover
               Development Planner


               Enc:   Appeal Rights
                      Approved Plans/Documents
                      Infrastructure Charge Notice
               cc.    Unitywater




                                                                                                       Page 8 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                Print Date: 13 May 2019, 4:45 PM

Page 9

Noosa Council documents




                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 9 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                                                           Print Date: 13 May 2019, 4:45 PM

Page 10

Noosa Council documents

 

GENERAL SITE PLAN NOTES
EARTHWORKS TO BE IN ACCORDANCE
WITH LOCAL COUNCIL REGULATIONS
‘AND NATIONAL CONSTRUCTION CODE,
VOL 2, SECTION 3.1.1 EARTHWORKS.

STORMWATER DRAINAGE DESIGN &

COMMUNITY TITLE SUBDIVISION
Total Lot Size = 1,007m2

 

DISCHARGE TO AS 3500, SECTION 3.1.2
STORMWATER DRAINAGE, NCC VOL2
AND LOCAL COUNCIL REQUIREMENTS.

DRIVEWAY CROSSOVER DESIGN,
CONSTRUCTION AND FINISH TO LOCAL
COUNCIL REQUIREMENTS.

‘SERVICES LEGEND
UNDERGROUND ELECTRICAL

Alfresco to be
reduced in size in
accordance with the
site cover plan

 

Proposed Lot |= 513m)
Preposed-batd—O4m2
Shared fence easement (6m2 (0.3m x 20m))

Sewer Easement = 274m2

 

 

    
   
 
 

OVERHEAD ELECTRICAL
RAINWATER DRAINAGE

 

  

s STORMWATER
7— TELSTRA
—"— WATER

Stormwater Easement (~15m2)

Landscaping in accordance with Planning Scheme Policy 03

- 2.x street trees to Opal St

 
   

- Dense landscaping around perimeters and in front of Opal St fence

DEVELOPMENT DETAILS

Density = 2 x 3+ beds (6.6)

Site Gover =220+-220-=410-(44%)-
Plot Ratio = 137 + 144 = 281m2 (27%)
Parking = 4 spaces

Landscaping = 496m2 (49%)

* New driveways and crossovers in
accordance with RS-049 & RS-050

 

 

 

Existing Feiiee

 

 

Fn

Kitchen
I

 

 

 

 

 

 

 

 

 

 

 

OPAL STREET

 

 

\ ‘TOP Pi
Easements fot Services (inidcative)

- Sewer easement(1.5m either side of existing pipe)

ensure non-worsening situation to adjoining properties

 

TOP CONDUIT RL: 108.04

 

 

‘SEWER RISING MAIN POTHOLE

new fence

- Sewer connections to be confirmed (Subject to Unitywater Approval)

- Water to new buildings (Subject to Unitywater Approval)

- Electricity to new building clear of water and sewer lines (Subject to Operational Works Approval)

- Stormwater for new building to include a 5k Litre above ground water tank for detention of new building
roof area directed to existing field inlet within Opal St (Subject to Operational Works Approval)

- All other stormwater from driveways and hardstand areas to be directed to landscaping areas to

50,209mm 172° 1" 2" SEWER RISING MAIN POTHOLE __|
‘TOP CONDUIT RL: 108.01

~~ Proposed
Lot 2

 

LL SEWERRISING MANPOTHOLE
‘TOP CONDUIT RL: 107.96

 

APPROVED PLANS
MCU19/0013 & RAL19/0003
NOOSA COUNCIL
9 MAY 2019

 

 

 

Scale 1:300

10,089mm 262° # 2"

  

 

     
         
 

US SEWERRISNG MAN
Son

SEWER COVPLED ONLY

0 1 2 3 4 5m

Site, Subdivision and
Preliminary Services
Layout Plan

Date: 29/01/2019

 

 

Documentiieilihe 2086BAN2 0808396
Version: 2\/esision!Dattes By UBD 12/01/2019

Print Date: 13 May 2019, 4:45 PM

Page 11

Noosa Council documents




                                                                                                                                      Toth Environmental
                                                                                                                                            Environmental &
                                                                                                                                            Hydraulic Engineers




                                                                       25.6m2 of existing
                                                                       outdoor covered
                                       Lot 1 - 507m2                   area to be removed
                                       Site Cover = 44%
                                              250m2


                                                                        Common Property 6m2
                                                                        (fence line 300mm wide)



                                                                                                                                      Site Cover Plan
                                                                                                                                      V.1 - 29.04


                                                    Lot 2 - 498m2
                                                    Site Cover = 36%




                                                      180m2



                                                                                                  Total Site Cover = 404.4m2 (40%)




                                                                                                              -
                                                                                                    APPROVED PLANS
                                                                                                  MCU19/0013 & RAL19/0003
                                                                                                     NOOSA COUNCIL
                                                                                                        9 MAY 2019
                                                                                                              -




Document Set ID: 20861499
                  20856346
                  20853003
Version: 2,
         1, Version Date: 13/05/2019
                          30/04/2019
                          10/05/2019                                                                                             Print Date: 13 May 2019, 4:45 PM

Page 12

Noosa Council documents

Docume:

 

PATHWAY & DRIVEWAY NOTES:

ALL PATHWAYS AND PAVEMENTS SHALL HAVE A
MINIMUM FALL OF 1 IN 100 (1%)

THE MAXIMUM GRADE OF DRIVEWAYS SHALL
NOTEXCEED 1 IN 5 (20%). WHERE GRADES ARE
NEAR THE MAXIMUM, A TRANSITION ZONE AT
EITHER END MAY BE REQUIRED. REFER TO BCA
VOLUME 1, D2.10 FOR GRADES TO REQUIRED
EXIT RAMPS.

CHECK WITH LOCAL AUTHORITY
REQUIREMENTS PRIOR TO CONSTRUCTING ANY
DRIVEWAYS, PATHWAYS OR CROSSOVERS
BETWEEN THE PROPERTY BOUNDARY AND
ROAD KERB.

CLEAR THE AREA OF ALL TOPSOIL AND
ORGANIC MATTER.

PROVIDE ALAYER OF SAND A MINIMUM OF
20mm THICK UNDER THE SLAB, COMPACTED
‘AND LEVELLED.

AN OPTIONAL 0.2um POLYETHYLENE MOISTURE
BARRIER MAY BE PROVIDED UNDER THE SLAB IN.
SALINE AREAS, LAPPED 200mm AT JOINS AND.

TAPED,
SLAB THICKNESS SHALL BE:
PEDESTRIAN PATHWAYS - 75mm THICK WITH 1
LAYER SL52 MESH,
VEHICULAR DRIVEWAYS [TO 3t GROSS) -
100mm THICK WITH
1 LAYER SL62 MESH.

30mm MINIMUM TOP COVER TO ALL
REINFORCEMENT, CONCRETE STRENGTH SHALL
BE N20 MINIMUM.

 

 

 

 

 

 

 

© t+
- |©
oO t | |
N oO |
2 8
x ou hiszal 16660 6690
x oT
| ao Bu Dwelling Bu 1
oad 110.47 tT 110.48 2
5 | 8s = 32 |
|
} lu Le 50.247
31200 [oo 3520
\

 

 

 

 

 

piled Only SEWER LINE

 

 

 

 

 

  

 

\
. 1
_ Propose RESIDENC!

 

 

 

 

 

 

 

 

|
Std

 

 

 

\ PAD LEVEL 107.600m

 

>= -FFL107.900m— —}-

 

 

 

 

 

 

 

 

 

 

 

 

  

261°59'30"

    

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

REAL PROPERTY DESCRIPTION:

LOT 6 ON RP: 82318

SITE AREA 501.17sqm.

SITECOVER —195.35sqm (38.98%)

LOCALITY COOROY

LOC.GOV. NOOSA SHIRE COUNCIL
2

SITE NOTES:

POSITION OF DWELLING TO BE CONFIRMED BY
CLIENT PRIOR TO ANY SITE WORKS

ALL STORM WATER, DOWN PIPES, RAIN WATER
TANKS & SITE DRAINAGE TO BE SIZED & LOCATED,
BY THE HYDRAULIC CONSULTANT/PLUMBER IN.
ACCORDANCE WITH BCA VOL 2 3.1.2 & 3.5.2 AND
@DC MP4.2/LOCAL PLANNING SCHEME HOUSE
CODE

BUILDER TO ENSURE THAT ACTUAL SEWER LINE AND.
MANHOLE POSITIONS MATCH THOSE AS SHOWN
BASED ON LOCAL AUTHORITY DOCUMENTS. ANY
DISCREPANCIES MUST BE BROUGHT TO THE
ATTENTION OF BESPOKE SOLUTIONS PTY LTD AND
RESOLVED PRIOR TO COMMENCEMENT OF

 

 

Lu
JOINTS ARE REQUIRED IN ALL CONCRETE 5 — <
PATHWAY AND DRIVEWAY SLABS - 9 CONSTRUCTION
3
2
ISOLATION JOINTS MUST BE PROVIDED WHERE £1) | oo! CORPO MING RETIOD OR ate PRIOR TO
ABUTTING EXISTING STRUCTURES, 3}?
a)s =| <t COMMENCEMENT OF ANY WORKS. FINISHED
EXPANSION JOINTS SHALL BE PROVIDED AT 15 >| oa FLOOR LEVEL IS TO BE ABOVE THE MINIMUM LEVEL
METER CENTRES IN ALL DIRECTIONS. N12 al. Lo AS PER LOCAL AUTHORITIES REQUIREMENTS & TO
DOWEL BARS AT 400 CENTRES ALONG THE SPB | oO COMPLY WITH BCAVOL2 3.1.2.3
JOINTS IN 100mm THICK SLABS, —
§}8 eS | THE FINISHED SURFACE IMMEDIATELY
CRACK CONTROL JOINTS SHALL BE PROVIDED \ Existing So SURROUNDING THE DWELLING, 1000mm WIDE, |S
AT3 METER MAXIMUM CENTRES AND AT \ A\ sewer LINE _\. Garden S—2—_|_|_+-_— 4 TO FALL AWAY FROM THE DWELLING AT A SLOPE
LOCATIONS WHERE THERE IS A LIKELIHOOD A Sy . Top Conduit \ gen Uy /| OF 1 IN 20 MINIMUM TO AN EARTH DRAIN AS
CRACK 2 , RL108.01 Z | / | INDICATED ON THE SITE PLAN.
o a i /
WOULD OCCUR [.e. RE-ENTRANT CORNERS) 105.63 \ SURFACE DRAINAGE IS TO DISCHARGE EVENLY
JOINTS SHALL BE LOCATED SO THE LONGEST - yee X WITHIN THE SITE AND WITHOUT NUISANCE TO
SIDE OF ANY SLAB PANEL IS NO MORE THAN 1.5 ‘S107 63 ‘SEWER LINE \ , ADJOINING PROPERTIES.
TIMES THE LENGTH OF THE SHORTEST SIDE. ANY ° \ \ L_!
ANGLE FORMED BETWEEN JOINTS OR JOINTS
ALL SUB-FLOOR AREAS MUST BE GRADED TO AVOID
"AND THE SLAB EDGE SHALL BE NO LESS THAN, 1122 Sewer Rising | 50.256 LT sewer Rising Main Pothole JHE PONDING OF WATER
75°, DUE TO THE VARYING NATURE OF OMP Main Pothole Top Condit RL:107.96
PATHWAYS AND DRIVEWAYS, ITIS ADVISABLE
TO PROVIDE JOB SPECIFIC DESIGN TO ENSURE 6000 SAX NA SUCPE AS DER BCR ANE I Y.1 FOR
DES NSTRAINTS ARE CONSIDERED IN THE WALL THE SITE SPECIFIC SOIL TYPE, REFER ALSO TO BCA
CLAUSE 3.2.2.4 FOR SLAB EDGE SUPPORT ON
5/RP82318 SLOPING SITES.
THESE NOTES ARE PROVIDED AS A GENERAL
SPECIFICATION ONLY. \ SITE PLAN 1000 MAXIMUM HIGH TIMBER RETAINING WALLS
‘ WITH 65@ AG PIPE BEHIND (TO DISCHARGE TO
REFERENCE SHOULD BE MADE TO ‘CEMENT, \
CONCRETE & AGGREGATE AUSTRALIA - GUIDE i200 APPROVED PLANS BOO TO BE WHOL CONGAINED WINTHRL THE
TO CONCRETE FOR HOUSING 2007, PATHS AND / .
DRIVEWAYS’ AND ‘RESIDENTIAL CONCRETE MCU19/0013 & RAL19/0003 SITE ONLY IF INDICATED ON THE PLANS.
DRIVEWAYS AND PATHS, JULY 2005) NOOSA COUNCIL THE HEIGHT OF FENCES, INCLUDING THE HEIGHT
OF RETAINING WALLS ARE NOTTO EXCEED 2.0m
9 MAY 2019 ABOVE FINISHED GROUND LEVEL, ONLY IF
INDICATED ON THE PLANS AND TO LOCAL
AUTHORITY APPROVAL.
THESE DRAWINGS AND DESIGN ARE E COMNENTS DATE
COPYRIGHT AND WILL NOT BE USED oo PROJECT JOB SPECIFICATION BY BUILDER TAKES SITE PLAN
/ OR REPRODUCED BY ANY MEANS, f BY PLANS PROPOSED RESIDENCE PRECEDENCE OVER THESE PLANS
—_ Sp) WHOLLY OR PARTLY WITHOUT PRIOR A feanonos| ax | ew
GJ. Gardner, Bowes | 7 seek senseuren + ere custom cu Sue Giasvenae | ROWECTSTAS
—_ GJ GARDNER HOMES CONSTRUCTION DRAWINGS
Sunshine C t North < Penne AC Be SCALE HEET SIZE] CLASS | WIND ] ISSUE
unsnine Goast No DO_NOT SCALE FROM THIS DRAWING 2 faniana] ac [wr Jowricoxtnciovatrnes CLIENT LOCATION ro cl :
2/171 Noosa Eumundi Rd PH: 07 4 702324 VERIFY ALL DIMENSIONS PRIOR TO E_[i7ia008 | AK | RW | AWENDED CONSTRUCTON DRAWINGS ERHARTER, Robert LOT 6 ON RP82318 INDICATED a
Noosaville , Qld COMMENCEMENT OF ANY SITE WORKS 10 OPAL LANE DRAWING FILENUMBER ] PAGE
AND REFER ANY DISCREPANCIES TO GJGSCN190173 2
. BESPOKE BUILDING DESIGN COOROY, QLD

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

iment Se}

pnt Set ID: 20863009
Wetion’ 2 Merson Dates 36/08/2019

Print Date: 13 May 2019, 4:45 PM

Page 13

Noosa Council documents

 

450|, 16660 690|, [450
220 70 70 7 70 70 90 220 FLOOR AREAS:
3300 ool, 1950 _ || 950 1830 || 1500 [| 1400 |) 4250 LL 450
70 17 DWELLING 154.18 m?
2230 __ || 1000 3570 2 GARAGE 38.65 m?

220 2
Tl 1000 |} 10860 LL 920 | PORCH 2.52 mi ,
TH | Total 195.35 mi

 

 

 

 

 

 

 

 

 

 

 

 

L450
L450

8 Fone 061g atSSGD aie PGS og r WALL LEGEND
t it EXTERNAL WALLS

zy MASONRY VENEER
- 70mm TIMBER STUD FRAME

 

 

 

220

 

 

 

 

 

 

loath 1450¢!

 

 

| 900

° - 10mm PLASTERBOARD LINING [GENERAL]
Ss - 6mm VILLABOARD LINING (WET AREAS)

== -LINEA-BOARD CLADDING {UNO}
- 70mm TIMBER STUD FRAME (UNO)
- 10mm PLASTERBOARD LINING [GENERAL]
- 6mm VILLABOARD LINING (WET AREAS)

INTERNAL WALLS
<== - 70mm TIMBER STUD FRAME (UNO)

- 10mm PLASTERBOARD LINING [GENERAL]
a - 6mm VILLABOARD LINING (WET AREAS)

REFER TO ENGINEERS DETAILS FOR
ARTICULATION JOINTS IF REQUIRED

LEGEND:
Cl DENOTES- 112x112 TIMBER POST

BATH

wetties |

 

 

2290
2290

3220
3470
1518
3470
3910

 

 

 

 

 

2500

 

1270 |, 930 | 1270
a
720cs
/

ino

 

 

 

 

 

 

 

70

 

 

 

 

 

 

 

 

 

 

 

2640

 

pechven —t T

o
BED 2 \Os8 /O CH2700mm ENTRY 7 etoom eh

FAMILY [sconce | | (Js
laminate STORAGE ||g20cs,. “+4 UL

1530
1030

 

 

 

1630
| 1350 [70

 

 

 

 

3800
7

 

 

11400
3200
1518

=
220), |,
1

50

7

7
11400

 

 

© DENOTES - PHOTOELECTRIC SMOKE ALARM TO
BCAVOL 23.7.2 & AS 3786

© DENOTES- GAS BOTTLE/HWS LOCATION AS PER
Ww AS 5601

 

 

 

 

 

70
7420

DINING

Taminate

@ DENOTES- WHIRLY BIRD ON ROOF

 

5890
5890
3450
6320
5700
6140

GARAGE [ 7}
‘concrete © DENOTES- SKYLIGHT

3200

1518

 

3800

FLOOR PLAN NOTES:

TERMITE PROTECTION IS TO BE PROVIDED IN
ACCORDANCE WITH PART 3.1.3 OF THE BCA VOL
AND AS 3660.1

 

3000x900)
|
|

 

 

70
io |)
1

 

 

00],

30mm sgd rebate

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

220

“ 2438SGD dp Ps TET -2418SGD  GXG)

PROVIDE A STATEMENT OF PROTECTION METHOD
FROM A TERMITE MANAGEMENT
PROFESSIONAL IN CONJUNCTION WITH THESE
DRAWINGS AT THE TIME OF SUBMISSION FOR
BUILDING APPLICATION APPROVAL.

 

 

 

 

 

 

 

 

 

 

220

 

 

 

 

 

450,
1
450|,

70 70 70 220
3300 1070 | 6380 2240 || 2100 sd | 6i0 TOILET DOORS TO BE PROVIDED WITH LIFT-OFF

APPROVED PLANS 2130 _ 1100 : 7480 veto seeesr6 WINDOWS AND DOORS ARE
221 70
MCU19/0013 & RAL19/0003 sa00 | 4270 Lino 6020 | [220 AS PER BUILDERS SPECIFICATIONS UNO
CONSTRUCTION IS NOTTO COMMENCE PRIOR TO
NOOSA COUNCIL 450/ 17350 q 1 Laso FULL APPROVAL BEING GRANTED IN WRITING BY
9 MAY 2019 | 7 THE CERTIFIER AND LOCAL AUTHORITY

MECHANICAL VENTILATION TO BE IN
ACCORD. WITH THE BCA PART 3.8.5 & AS 1668.2

»\, LOWER FLOOR PLAN GAS BOTILE LOCATION AS PER AS56O1

100 20mm STONE BENCHTOPS THROUGHOUT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

THESE DRAWINGS AND DESIGN ARE
COPYRIGHT AND WILL NOT BE USED
fy OR REPRODUCED BY ANY MEANS
——— | | (oe) wtouty on parm without PRIOR
G G rdn HOMES SSE) WIRIITEN PERMISSION FROM
J. 7 a. er, GJ GARDNER HOMES 7
Sunshine Coast North [50 Nor scate FROM THIS DRAWING x SCION ORANG CLIENT LOCATION ae cl -
21171 Noosa Eumundi Rd PH: 07 54 702324 VERIFY ALL DIMENSIONS PRIOR TO E 7 [RH IA A ERHARTER, Robert LOT 6 ON RP82318 INDICATED a
Noosaville , Qld COMMENCEMENT OF ANY SITE WORKS 10 OPAL LANE DRAWING FILE NUMBER] PAGE

[AND REFER ANY DISCREPANCIES TO
BESPOKE BUILDING DESIGN COOROY, QLD GJGSCN190173 3

pen PROJECT JOB SPECIFICATION BY BUILDER TAKES | DATE

PROPOSED RESIDENCE PRECEDENCE OVER THESE PLANS LOWER FLOOR PLAN
CUSTOM. CLIENT SALES CHRIS McNEIL PROJECT STATUS

CONSTRUCTION DRAWINGS
SCALE HEETSIZE] CLASS | WIND | ISSUE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Docume: Hy 19
Wetion’ 2 Merson Dates 36/08/2019 Print Date: 13 May 2019, 4:45 PM

 

Page 14

Noosa Council documents

 

COLORBOND ROOF SHEETING

‘LINEA’ WEATHERBOARD FIXED TO MANUF. SPECS. NOTES:
CLADDING (or similar) COLORBOND FASCIAS AND GANGNAIL TRUSSES TIED DOWN, BRACED,
GUTTERS FABRICATED AND INSTALLED TO TRUSS

   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

GFCL jo MANUFACTURERS SPECIFICATIONS.
2700 = ~
GF WH SS = — — FACE AND SILL BRICKS IN ACCORDANCE
30 = — WITHAST225 AND SAA. MASONRY CODE AS3700.
POWDERCOAIED ALUM
= WINDOWS AND DOOR FRAMES
2.4x4.8 PANEL-LIFT-DOOR = SELECTED FACE AND SILL
co) BRICKS
GEFL_ _ is — 112x112 TIMBER POST ON GAL. STIRRUPS APPROVED PLANS
0 ® ARN ORT ORRRORRORRRRORRRRRORORRORR TR ORTRORRE- MCU19/0013 & RAL19/0003
/ {$2 setectep timer FRONT
( 1 ‘ T1400 ENTRANCE DOOR NOOSA COUNCIL
~~ $$ wtevr ar 9 MAY 2019
GFECL
2700
GFWH — TE =
2400 Hf { =|
Grrl _ 4 oe
0 SI IIIT NSS SY SBI SS BI SYST SSISI SI SI ISIBS SI SI NSTI SIPS SI SIBSIST EIST ST NT SIS BY SI RISD BIST SIS PISS IIE.

/\ ELEVATION 2
\ /) 42400

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2700 _ ihe
GFWH vO
2400

L 4 4
GFFL {
0 SISVRV AVY SY AY VY SIT BY ST SY SI STIS SI ST NY NT NY SST SSIS RI SIS SII SV IOI STS

 

 

 

(nm ELEVATION 3
\ 3 1: 100

/

    

 

 

WHIRLY BIRD

GFCL
2700
GF WH

2400

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DISS IIIS OTIS OS OY OS IV SIV IVS SOI ISOS IOI DVIS SII IOS OSI ISIS SIS SION

ELEVATION 4

1:100

 

 

(4

QO?

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THESE DRAWNGS AND DESIGN ARE DAE
PROJECT JOB SPECIFICATION BY BUILDER TAKES
GR REPRODUCED BY ANY MEANS. PROPOSED RESIDENCE PRECEDENCE OVER THESE PLANS ELEVATIONS
— WHOLLY OR PARTLY WITKOUT PRIOR cuENT
G rdn HOME. " CUSTOM SALES CHRIS McNEIL PROJECT STATUS
J. G aLaNer, Homes. serene somes CONSTRUCTION DRAWINGS
Sunshine Coast North [9 Notscate FROM THIS DRAWING CLIENT LOCATION ce coe as | me SE
2/171 Noosa Eumundi Rd PH: 07 4 702324 VERIFY ALL DIMENSIONS PRIOR TO E ERHARTER, Robert LOT 6 ON RP82318 INDICATED 9
Noosaville , Qld, COMMENCEMENT OF ANY SITE WORKS 10 OPAL LANE DRAWING FILENUMBER ] PAGE
[AND REFER ANY DISCREPANCIES TO GIGSCNIS0I73 4
Docum BESPOKE BUILDING DESIGN COOROY, QLD

 

 

 

ent Set ID: 20863009
Wetion’ 2 Merson Dates 36/08/2019 Print Date: 13 May 2019, 4:45 PM

Page 15

Noosa Council documents

Documpnt Set. :.20863008
we a CERO, Dates 36/08/2019

 

The LYSAGHT® Spacer Insert has the following overflow cay

* Overflow capacity of 1.25L/s/m length of gutter when
installed as follows;
~The gutter is set at the highest practical level,
i.e. barb 6 of the Spring Clip
~The gutter slope of 1:500 or greater.

pacity based on testing:

Sping Clip
Barb-6

J aie 1

Gutter- Quad 115 Hi-Front,

- Amaximum LYSAGHT® Spacer Insert spacing of 1200mm
- The LYSAGHT® Spacer Insert is positioned next to the }

Over-strap
- The Over-strap is positioned next to the Spring Clip

5

NOVALINE® Fascia

as detailed in the brochure titled LYSAGHT NOVALINE®

Fascia System

/ GUTTER DETAIL

NTS

\

 

pr

pp

 

dp

 

APPROVED PLANS
MCU19/0013 & RAL19/0003
NOOSA COUNCIL
9 MAY 2019

 

 

 

dp

 

 

5 Area
40 m?

Area
35 m?

(6 DOWNPIPES REQUIRED @40sqm/DP)
6 DOWNPIPES PROVIDED

2°

Area
30 m?

 

TOTAL ROOF CATCHMENT
AREA 222 m?

 

Area
40 m?

 

 

 

 

 

 

 

 

1: 100

  

ROOF CATCHMENT PLAN

dp

dp

ROOFWATER DRAINAGE GENERAL NOTES:

ALL ROOFWATER DRAINAGE SYSTEMS MUST BE
CONNECTED TO A STORMWATER DRAINAGE
‘SYSTEM COMPLYING WITH BCA PART 3.1.2,
DRAINAGE OR AS/NZS3500.

THE ROOF DRAINAGE SYSTEM MUST BE PROVIDED.
WITH AN OVERFLOW TO PREVENT THE BACKFLOW
(OF WATER INTO THE BUILDING.

THE AREA SPECIFIC RAINFALL INTENSITY MUST BE
SELECTED FROM BCA TABLE 3.5.2.1 OR FROM
AS/NZS3500.

GUTTERS AND DOWNPIPES MUST BE SELECTED
FROM BCA TABLE 3.5.2.2 OR FROM AS/NZS3500.

EAVES GUTTERS MUST BE INSTALLED AT A FALL NOT
LESS THAN I IN 500 WITH SUPPORT BRACKETS AT
1.2m MAXIMUM CENTRES.

BOX GUTTERS MUST BE INSTALLED AT A FALL NOT
LESS THAN TIN 100, IN ACCORDANCE WITH
AS/NZS3500.3.

THE WIDTH OF VALLEY GUTTERS SHALL BE IN
ACCORDANCE WITH AS/NZS3500.3 AND BCA PART
35.2,

REFER TO ROOF SHEETING MANUFACTURERS.
SPECIFICATIONS FOR LIMITATIONS ON SHEET
OVERHANGS INTO VALLEY GUTTERS.

THE MAXIMUM ROOF CATCHMENT AREA FOR
VALLEY GUTTERS IS 20m2.

VALLEY GUTTERS ON ROOFS PITCHED LESS THAN
12.5° MUST BE DESIGNED AS BOX GUTTERS.

DOWNPIPES MUST SERVE NOT MORE THAN 12
METRES OF GUTTER LENGTH FOR EACH DOWNPIPE
WHICH MUST BE LOCATED AS CLOSE AS POSSIBLE
TO VALLEY GUTTERS.

EAVES GUTTERS MUST BE PROVIDED WITH AN.
OVERFLOW SYSTEM WHERE DOWNPIPES ARE

LOCATED MORE THAN 1.2 METRES FROM A
VALLEY GUTTER

TABLE 3.5.2.1 RAINFALL DURATION INTENSITY
5 MINUTE DURATION RAINFALL INTENSITY
NOOSA HEADS - 20YEARS —_258mm/h
-100YEARS 331mm/h
TABLE 3.5.2.2 GUTTER & DOWNPIPE SELECTION
FROM TABLE A & B

40sqm - A - MEDIUM RECTANGULAR GUTTER or
D- 125mm D GUTTER

FROM TABLE C.
90mm DIAMETER DOWNPIPE

TABLE 3.5.2.3 OVERFLOW VOLUME
FROM TABLE A

350mm/h —12.0m GUTTER [email protected] (L/s/m) = 14.4L/s
FROM TABLE B

350mm/h- 40sqm =3.9(L/5)

USE CONTROLLED BACK GAP (SEE DETAIL)
= 1.25 L/s/m x 12.0m = 15.0L/s

 

 

PAIQNy,

GJ. Gardner. somes ©

THESE DRAWINGS AND DESIGN ARE
COPYRIGHT AND WILL NOT BE USED.
(OR REPRODUCED BY ANY MEANS
WHOLLY OR PARTLY WITHOUT PRIOR
WRITTEN PERMISSION FROM -

GJ GARDNER HOMES

 

 

 

 

 

Sunshine Coast North

2/171 Noosa Eumundi Rd PH: 07 54 702324
Noosaville , Qld.

DO NOT

 

SCALE FROM THIS DRAWING
VERIFY ALL DIMENSIONS PRIOR TO
COMMENCEMENT OF ANY SITE WORKS
AND REFER ANY DISCREPANCIES TO
BESPOKE BUILDING DESIGN

PROJECT
PROPOSED RESIDENCE
CUSTOM

PRECEDENCE OVER THESE PLANS

JOB SPECIFICATION BY BUILDER TAKES

 

DATE
ROOF CATCHMENT PLAN

 

(CLIENT

SALES. CHRIS McNEIL

PROJECT STATUS
CONSTRUCTION DRAWINGS

 

 

 

 

 

 

 

 

 

 

 

 

CLIENT
ERHARTER, Robert

LOCATION

LOT 6 ON RP82318
10 OPAL LANE
COOROY, QLD

 

‘SCALE HEET SIZE] CLASS | WIND | ISSUE
INDICATED] AS la E

 

 

 

 

 

DRAWING FILE NUMBER PAGE
GJGSCN190173 6

 

 

Print Date: 13 May 2019, 4:45 PM

 

Page 16

Noosa Council documents


                                                                 PO Box 141, Tewantin, QLD 4565
                                                                 Phone (07) 5329 6500         Fax (07) 5329 6501
                                                                 Email: [email protected] Website: www.noosa.qld.gov.au
                                                                 ABN 97 969 214 121




                            INFRASTRUCTURE CHARGES NOTICE

          To:       RF Erharter                                       Infrastructure Charges Notice No: N1439
                    C/- Pivotal Perspective Pty Ltd                                          Revision:   0
                    4/59 Mary St
                    NOOSAVILLE QLD 4566                                                  Date of Issue: 13 May 2019


          Notice is hereby given that this infrastructure charge notice is levied by the Noosa Shire Council on the
          described land in accordance with the planning legislation applicable at the time of issue.

          DEVELOPMENT AND LAND TO WHICH THE INFRASTRUCTURE CHARGE APPLIES:

             Development Approval Reference:            MCU19/0013 (& RAL19/0003)
             Land / Property Address:                   10 Opal Street, COOROY QLD 4563
             Real Property Description:                 Lot 6 RP 82318

          INFRASTRUCTURE CHARGE LEVIED BY COUNCIL ISSUED UNDER:
                •   Noosa Shire Council Charges Resolution (No.3) 2018 (effective 24 September 2018)


                *NET INFRASTRUCTURE CHARGE PAYABLE =                                           $17,215.00
                                                                                         Planning Regulation at
                                                                 *Current at:           2018-2019 Financial Year

          *SUBJECT TO AUTOMATIC INCREASE PROVISION:
          The net infrastructure charge amount payable is subject to automatic indexation to the time of making
          payment. Indexation is applied annually per Financial Year using variations applicable to the “maximum
          amount” possible to be issued under the Planning Regulation 2017 as amended in accordance with the
          legislation from the stipulated base date to the time of issue and payment.

          NOTE:
            • The Council Infrastructure Charges calculation details are provided on page 3 of this notice.
            • Separate Infrastructure Charges may be issued by Unitywater as applicable.

          DATE FOR PAYMENT OF THE INFRASTRUCTURE CHARGE
          The Infrastructure Charge is to be paid to NOOSA COUNCIL as follows:

              DEVELOPMENT PERMIT TYPE                               DUE DATE FOR PAYMENT
                                                 When the change happens
             Material Change of Use
                                                 (i.e. on completion of development &/or commencement of use)

            *CONTACT COUNCIL 5 days PRIOR TO MAKING PAYMENT FOR THE CURRENT AMOUNT DUE.




                                         PO Box 141            P. (07) 5329 6500    [email protected]
                                         TEWANTIN QLD 4565     F. (07) 5329 6501    www.noosa.qld.gov.au         ICN - Page 1
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                                   Print Date: 13 May 2019, 4:45 PM

Page 17

Noosa Council documents


          REFUND PROVISION:
          Where the value of a “Trunk” Infrastructure Offset exceeds the Net Infrastructure Charge Payable, a refund
          will be provided in accordance with Clause 12.4 of Council’s Resolution.

                                       TERMS OF REFUND                                           REFUND AMOUNT
             Not Applicable                                                                                           $0.00

          INFRASTRUCTURE CHARGES TAKEN TO BE A RATE:
          A levied charge is, for the purpose of its recovery, taken to be rates of the local government that levied
          the charge. Within the meaning of the Local Government Act, this means:
             a.    an infrastructure charge may be recovered by court action for a debt;
             b.    an infrastructure charge may be recovered from the person for the time being owning the
                   relevant land, regardless of who was the owner or other person upon whom the charges was
                   imposed;
             c.    Interest is payable on overdue payments; and
             d.    If charges are unpaid for 3 years, the land can be sold to recover the outstanding charges.

          INTEREST ON OVERDUE CHARGES:
          Compound interest at the rate of 11% per annum calculated daily is payable on all infrastructure
          charges outstanding after the due date shown on this charges notice.

          GOODS AND SERVICES TAX:
          The federal government has determined that rates and utility charges levied by local government will
          be GST free. Accordingly, no GST is included in this infrastructure charges notice.

          INFRASTRUCTURE CHARGES ENQUIRIES:
          Enquiries regarding this infrastructure charges notice should be directed to Council’s office:
             • Phone (07) 5329 6211 or 5329 6449 during office hours; or
             • E-mail: [email protected]

          METHODS OF PAYMENT:


                                       Cheque or money order to be made payable to: Noosa Council
             Mail
                                       PO Box 141, Tewantin, QLD 4565


                                       Noosa Council, 9 Pelican Street, Tewantin
             In Person
                                       Office hours: 8.30 am to 4.30 pm Monday to Friday (excludes public holidays)

                                       Mastercard or Visa only
             Credit Card               Note: All payments made by credit card will incur a 0.5% surcharge to reflect the
                                       cost of fees charged for credit card transactions.

                                       Payment by electronic transfer direct to Council’s Bank Account is only
             Direct Bank Transfer      available by special arrangement. Contact Infrastructure Enquiries at:
                                       [email protected]

          SPECIAL NOTES:
          Nil




                                        PO Box 141               P. (07) 5329 6500   [email protected]
                                        TEWANTIN QLD 4565        F. (07) 5329 6501   www.noosa.qld.gov.au        ICN - Page 2
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                                   Print Date: 13 May 2019, 4:45 PM

Page 18

Noosa Council documents


        INFRASTRUCTURE CHARGE CALCULATION DETAILS:
        The infrastructure charge is calculated in accordance with Council’s Infrastructure Charges Resolution incorporating the charge apportionment (break-up) agreement with Unitywater in
        compliance with the planning legislation and regulations applying at the time of issuing the notice.

         NOOSA SHIRE COUNCIL CHARGES RESOLUTION (No.3) 2018 (Effective 24 September 2018)
                                                                                                                                                                                                                    Base Date at          1/07/2018
         INFRASTRUCTURE CHARGE CALCULATION                                                                                                                               MCU19/0013 & RAL19/0003                      Planning          At 2018-2019
                                                                                                                                                                                                                    Regulation =        Financial Year
                                                                                                                                             Colum n 6
                                Colum n 1
                         Use under The Noosa Plan
                                                                                                                                              COUNCIL                                Council Charge Calculation
                                                                                                                                              CHARGE
                                                                      Colum n 2                          Colum n 3
                                                                                                                                            Per Table 10.1                                    EXISTING                  NET               CHARGE
                                                                  Developm ent class                  Unit of m easure                                                  APPROVED
                                                                                                                                    (Charges breakup) of Adopted
                                  Defined use                                                                                                                                                    (QTY)            CHARGEABLE              AMOUNT
                                                                                                                                         Charge in Column 6                (QTY)
                                                                                                                                       ($ per unit of measure)                                  (Credit)               (QTY)                  $

         Detached house (& Residential Lot Reconfiguration)            Residential             3 or more bedroom dw elling (Lot)            $17,215.35                                              1.0                  -1.0                 -$17,215.35

         • Community Residence
                                                                                                 3 or more bedroom dw elling                $17,215.35                        2                                           2                   $34,430.70
         • Ancillary dw elling unit
         &
         Multiple housing                                              Residential                   2 bedroom dw elling                    $12,296.67                                                                    0                        $0.00
         • Type 2 Duplex
         • Type 4 Conventional
                                                                                                     1 bedroom dw elling                     $8,371.00                                                                    0                        $0.00
         • Type 5 Relocatable

                                                                                                                                                                                        Sub-Total, Residential =                             $17,215.35


                                                                                                                                                                                                                                         At 2018-2019
                                                                                                                                                                                                                                        Financial Year

                                                                                                                                                         CALCULATED INFRASTRUCTURE CHARGE =                                               $17,215.00

                                                                                                                                   Other                                                                                                          $0.00
                                                                                                                                                                     Council Policy “Infrastructure Charges Rebates For Community
                                                                                                      REDUCTIONS                   Rebate                                                                                                         $0.00
                                                                                                                                                                     Organisations”

                                                                                                                                   Trunk Infrastructure Offset                                                                                    $0.00

                                                                                                                                                    *NET INFRASTRUCTURE CHARGE PAYABLE =                                                  $17,215.00
         ALLOCATION OF LEVIED CHARGE TO TRUNK INFRASTRUCTURE NETWORKS
         The infrastructure charge payable will be allocated to Council “Trunk ” infrastructure network s in accordance with Council’s Resolution as follows:

                                                                                       Column 4
                                                                                                                                                                                                                                                                  * Net
                                                                 Allocation of Council infrastructure charge to trunk                      Calculated                                         Reductions
            Council “Trunk” Infrastructure Network                                                                                                                                                                                         * Total           Infrastructure
                                                                               infrastructure networks                               Infrastructure Charge
                         (Table 10.2)                                                                                                                                                                                                    Reductions         Charge Payable
                                                                                                                                     (At Planning Regulation
                                                                                                                                                                                                                                                              At 2018-2019
                                                               Residential Development        Non-Residential Development                   2018-2019)                      Other                Rebate                Offset                                Financial Year


         Transport              (Charge Type: icA3trans)                 40%                                 85%                                         $6,886.00                  $0.00                 $0.00                 $0.00              $0.00           $6,886.00
         Public Parks & Land for Community Facilities
                                                                         50%                                 15%                                         $8,608.00                  $0.00                 $0.00                 $0.00              $0.00           $8,608.00
                                (Charge Type: icA3parkCF )

         Stormwater             (Charge Type: icA3storm )                10%                                100%                                         $1,721.00                  $0.00                 $0.00                 $0.00              $0.00           $1,721.00

                  * Subject to Automatic Increase Provision until date of payment.                      *TOTALS =                                    $17,215.00                     $0.00                 $0.00                 $0.00              $0.00          $17,215.00


                                                                                                       PO Box 141                             P. (07) 5329 6500                   [email protected]
                                                                                                       TEWANTIN QLD 4565                      F. (07) 5329 6501                   www.noosa.qld.gov.au                    ICN - Page 3
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                                                                                                                                                                              Print Date: 13 May 2019, 4:45 PM

Page 19

Noosa Council documents


                                                                    PO Box 141, Tewantin, QLD 4565
                                                                    Phone (07) 5329 6500         Fax (07) 5329 6501
                                                                    Email: [email protected] Website: www.noosa.qld.gov.au
                                                                    ABN 97 969 214 121


               DECISION NOTICE ABOUT THE DECISION TO GIVE
                   AN INFRASTRUCTURE CHARGES NOTICE
          1.      PRELIMINARY

          Infrastructure charges are triggered and issued on development approvals as a contribution towards the cost
          of "trunk" infrastructure provided to service development and are governed by “Charges Resolutions” adopted
          by local government in accordance with the planning legislation and regulations current at the time of issue.
          Infrastructure Charges Notices are issued separately by both Council and Unitywater relating to their
          specified “Trunk” infrastructure networks.


          2.      THE DECISION AND REASONS FOR IT

          The planning legislation provides for the following:
             a) authorises local governments to do either or both of the following for development approvals in relation
                to trunk infrastructure—
                 (i) adopt, by resolution, charges for development infrastructure and levy the charges;
                (ii) impose particular conditions about development infrastructure; and
             b) authorises local governments, for non-trunk infrastructure, to impose particular conditions about
                development infrastructure; and
             c) provides for a regulation to govern local government adopted charges and charges by distributor-
                retailers under the SEQ Water Act for trunk infrastructure.
          On 6 February 2014, Noosa Council adopted the "Noosa Shire Council Adopted Infrastructure Charges
          Resolution (No.1) 2014" to replace the "Sunshine Coast Regional Council Adopted Infrastructure Charges
          Resolution (No.4) 2011" that translated across to Noosa Council on 1 January 2014. The resolution has effect
          on development approvals and charge notices issued from 6th February 2014 to 15 February 2015 in
          accordance with the legislation current at the time of issue.
          On 12 February 2015, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.2) 2014" to
          replace the "Noosa Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to include legislative
          amendments that commenced on 4 June 2014. The resolution has effect on development approvals and charge
          notices issued from 16th February 2015 to 27 October 2016 in accordance with the legislation current at
          the time of issue.
          On 20 October 2016, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.2) 2014
          (Amendment 1)" to reflect adopted amendments made to the planning scheme. The resolution has effect on
          development approvals and charge notices issued from 28th October 2016 to 23rd September 2018 in
          accordance with the planning legislation current at the time of issue.
          On 20 September 2018, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.3) 2018"
          replacing the "Noosa Shire Council Charges Resolution (No.2) 2014 (Amendment 1)" to reflect the current
          planning legislation, regulation and LGIP. The resolution has effect on development approvals and charge
          notices issued from 24th September 2018 in accordance with the planning legislation current at the time of
          issue.
          Council’s decision and reason/s for issuing the infrastructure charge is because the development results in an
          increase in the type/s and/or quantity in use/s on the site and therefore places additional demand on
          infrastructure. The determination of additional demand on infrastructure correlates directly to the
          infrastructure charge calculation undertaken in accordance with Council’s Charges Resolution and the planning
          legislation. Refer also to Queensland State Government Fact Sheet: “Local government infrastructure
          framework, Calculating additional demand and existing use credits”.


                                          PO Box 141              P. (07) 5329 6500    [email protected]
                                          TEWANTIN QLD 4565       F. (07) 5329 6501    www.noosa.qld.gov.au         ICN - Page 4
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                                      Print Date: 13 May 2019, 4:45 PM

Page 20

Noosa Council documents


          The Infrastructure Charges Notice includes “Special Notes” (if applicable) on page 2 and together with the
          infrastructure charge calculation on page 3, provides full and factual details to enable the applicant to review
          and if required, for making a submission to Council on the infrastructure charge issued in relation to any of
          the following:
                1.    the types and quantities of uses approved by the development permit for the site which may relate to:
                      a. the total development of the site; or alternatively,
                      b. just the additional development to that existing on the site.
                2. the types and quantities of existing or previously existing “lawful” uses to be used as existing credits
                   in calculations relating to the total development of the site (applying to calculations under 1. a. above);
                3. offsets for “trunk” infrastructure that is contained in a development permit condition to be provided
                   by the development for crediting against the infrastructure charge calculation (if applicable); and
                4. any other mitigating items (if applicable) that impact the net infrastructure charge amount payable.
          Should the applicant believe these details to be incorrect or an omission exists, the applicant may make
          representation/s to Council on the Infrastructure Charges Notice providing full supporting particulars with
          documentation to enable review of the additional information to be conducted. Where representations are
          agreed and verified as being correct, the representation/s will form the basis for a negotiated/amended
          infrastructure charges notice to be issued as applicable.


          3.         INFRASTRUCTURE CHARGE NOTICES

          3.1        TRIGGERS FOR INFRASTRUCTUE CHARGES & ISSUING OF NOTICES
          The triggers for issuing infrastructure charges are defined in the planning legislation and are generally
          triggered by the issue of a development permit for either:
          (1) Reconfiguration of a lot; or
          (2) Material Change of Use of Premises; or
          (3) Building Works; or
          (4) Other development.
          Under the planning legislation, infrastructure charges are not imposed by condition on a development permit -
          they are an action that follows the issue of a permit. So consequently, charges may be imposed in cases where
          a development permit for a lot reconfiguration or material change of use of premises has previously been
          granted, but a development permit for building works is yet to issue.


          3.2        DUE DATE FOR PAYMENT OF INFRASTRUCTUE CHARGES
          (1) A levied charge becomes payable—
                (a) if the charge applies for reconfiguring a lot— when the local government that levied the charge
                    approves a plan for the reconfiguration that, under the Land Title Act, is required to be given to the
                    local government for approval; or
                (b) if the charge applies for building work—when the certificate of classification or final inspection
                    certificate for the building work is given under the Building Act; or
                (c) if the charge applies for a material change of use—when the change happens; or
                (d) if the charge applies for other development—on the day stated in the infrastructure charges notice
                    under which the charge is levied.
          (2) The recipient of an infrastructure charges notice and the local government may also agree to other
              arrangements for payment.




                                            PO Box 141              P. (07) 5329 6500    [email protected]
                                            TEWANTIN QLD 4565       F. (07) 5329 6501    www.noosa.qld.gov.au        ICN - Page 5
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                                       Print Date: 13 May 2019, 4:45 PM

Page 21

Noosa Council documents


          3.3     LEVIED CHARGE TAKEN TO BE A RATES
          A levied charge is, for the purpose of its recovery, taken to be rates of the local government that levied
          the charge.
          Within the meaning of the Local Government Act, this means:
          (1) an infrastructure charge may be recovered by court action for a debt;
          (2) an infrastructure charge may be recovered from the person for the time being owning the relevant land,
              regardless of who was the owner or other person upon whom the charges was imposed;
          (3) INTEREST IS PAYABLE on overdue payments; and
          (4) if charges are unpaid for 3 years, THE LAND CAN BE SOLD to recover the outstanding charges.


          3.4     INTEREST ON OVERDUE INFRASTRUCTURE CHARGES
          Compound interest at the rate of 11% per annum calculated daily is payable on all overdue infrastructure
          charges outstanding after the due date for payment as applying to the infrastructure charges notice.


          3.5     GOODS AND SERVICES TAX
          The federal government has determined that rates and utility charges levied by local government will be
          GST free. Accordingly, no GST is included in this infrastructure charges notice.


          3.6 USE OF INFRASTRUCTUE CHARGES COLLECTED
          Under the planning legislation, a levied charge paid to a local government must be used to provide trunk
          infrastructure. Council’s planning scheme identifies trunk infrastructure in Schedule 9.2-Schedule of Works
          of its Local Government Infrastructure Plan (LGIP). https://www.noosa.qld.gov.au/view-the-noosa-plan


          4.      INFRASTRUCTURE CHARGES ENQUIRIES

          Infrastructure charges enquiries should be directed to the appropriate entity as follows:
          (1) Council Infrastructure Charges enquiries should be directed to Noosa Council’s office:
                Phone: (07) 5329 6211 or 5329 6449 during office hours; or
                E-mail: [email protected]
          (2) Unitywater Infrastructure Charges enquiries should be directed to Unitywater’s office:
                Phone: 1300 086 489 or (07) 5431 8333 during office hours; or
                E-mail: [email protected]


          5.      RIGHTS OF APPEAL

            Prior to making an appeal about an infrastructure charge notice, the recipient must first suspend the
            appeal period and make written representations to Council about the infrastructure charges notice in
            accordance with the planning legislation.
            If Council agrees or agrees in part with the representations, a Negotiated/Amended Infrastructure
            Charges Notice will be issued accordingly with details of Council’s decision.
            If Council does not agree with the representations, the Infrastructure Charges Notice issued remains
            unchanged and details of Council’s decision will be provided.
            The appeal period for the infrastructure charges notice starts again when Council gives the decision notice
            about the representations to the recipient.
            The applicant may appeal against Council’s decision on representations and a copy of the relevant appeal
            provisions from the Planning Act 2016 is provided on the following page.


                                         PO Box 141              P. (07) 5329 6500   [email protected]
                                         TEWANTIN QLD 4565       F. (07) 5329 6501   www.noosa.qld.gov.au        ICN - Page 6
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                                   Print Date: 13 May 2019, 4:45 PM

Page 22

Noosa Council documents




                                       PO Box 141          P. (07) 5329 6500   [email protected]
                                       TEWANTIN QLD 4565   F. (07) 5329 6501   www.noosa.qld.gov.au        ICN - Page 7
Document Set ID: 20863195
Version: 1, Version Date: 13/05/2019                                                             Print Date: 13 May 2019, 4:45 PM

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.