SPECIAL MEETING AGENDA 27 JANUARY 2021
500557 – A Design Features - Carpark Area 2 prepared by Noosa 22 October
DA04 Council 2020
500557 – D Design Features – Pathway Connection prepared by 22 October
DA05 Noosa Council 2020
500557 – A Library Carpark Reconfiguration Plan prepared by 22 October
DA06 Noosa Council as annotated by Council 2020
500557 – A Design Features - Carpark Area 3 prepared by Noosa 6 October
DA07 Council as annotated by Council 2020
Currency Period
3. This development approval lapses if the use has not happened by 29 January 2027,
unless an application to extend the currency period is approved by Council.
Stormwater Drainage Management
4. Stormwater must be treated in accordance with the recommendations of the
Stormwater Quality Management Plan Revision 1 prepared by Callaghan and Toth
dated July 2020.
Flood Risk
5. All infrastructure with potential to be impacted by flood waters, including electrical and
plumbing fixtures and pump-room plant and equipment is to be located above 1%AEP
flood level corresponding to year 2100 planning period.
6. An automatic flood warning system incorporating both an audible and visual alarm is
to be provided to alert visitors to evacuate the site as soon as flood waters begin to
impact the playground and with sufficient warning time to ensure full site evacuation
prior to evacuation routes becoming inundated.
7. The playground design is to be amended to eliminate the risk of isolation of all site
areas by rising flood waters. This may involve either modification to site levels or
provision of linking elevated walkways and evacuation routes which remain flood-free
until each area of the site which the evacuation routes service is itself inundated.
8. The playground design and associated flood model is to be amended to eliminate any
increases in the flood levels affecting over-floor flooding at adjacent buildings for all
flood events.
9. Provide an updated flood emergency preparedness and management plan which
incorporates the above changes and which includes RPEQ certification that the
proposed final playground design achieves an acceptable and tolerable level of flood
risk. This plan must be completed and certified prior to commencing works on site.
Car parking
10. 56 additional car spaces must be provided prior to the commencement of the use of
the playground. The car parking is to be provided in the following manner:
a. Lower Mill Road (22 additional formally sealed and line-marked spaces)
b. Maple Street road reserve (12 formally sealed and line-marked spaces)
c. Southern side of Mary River Road west of the tennis courts (22 spaces) be
constructed as an overflow parking area.
11. The overflow parking area must be monitored for a full week in school holidays and a
full week outside of school holidays after the playground has been fully operational for
three months (and again at six months). The results of the surveys must be provided
to Council’s Manager Development Assessment.
12. The overflow parking area must be formally sealed and line-marked if regular use is
identified at either period of monitoring referred to in Condition 11.
Page 7 of 41
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.