               60.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               61.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               62.    All fill and associated batters must be undertaken in accordance with an Operational Works
                      approval and contained entirely within the subject site unless written permission from the
                      respective landowner(s) is provided to Council. The works must be generally in accordance
                      with STP Consultant’s Earthworks/Track Layout Plan (STP22-0347 SKC03) dated 23 March
                      2023.
               63.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               64.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
                      LANDSCAPING
                      Landscaping Works
               65.    The development site must be landscaped. The works must be undertaken in accordance
                      with an Operational Works approval and the Noosa Plan for that specific area and must
                      include in particular:
                      a.      the works shown on the approved Landscape Concept plans shown in the Approved
                              Plans
                      b.      vegetation clearing within the site is to be offset through the rehabilitation of the area
                              of vegetation adjacent to Cooyar Street. The area is to incorporate revegetation works
                              that offset all native vegetation removal that is proposed on the site.
                      c.      control of all weeds species listed in the following standards and legislation:
                              i.       declared plants under the Land Protection (Biodiversity Act 2014 and sub-
                                       ordinate Regulation 2016).
                              ii.      Noosa Local Government Area Pest Management Plan 2015-2019.
                              iii.     The area west of the new water tank and pump house on the norther side of the
                                       entry driveway must be heavily revegetated with trees shrubs and ground covers
                                       to sufficiently screen the infrastructure from Cooyar Street. Detailed landscape
                                       plans must be submitted and approved as part of an Operational works.
               66.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               67.    All landscape works must be maintained generally in accordance with the approved design
                      for the life of the development.


                                                                                                          Page 9 of 13
Document Set ID: 23351231
Version: 3, Version Date: 14/11/2024

Used in these records

About this file

File size
194 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 132001.210127.4.pdf · 194 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.