RFI - Attachment 4B - Flora and Fauna Assessment Rev 5
Native Foresters
• If possible, works will occur outside breeding season.
• Machinery hygiene protocol enforced during works to reduce potential to spread weeds.
• Weed management plan within retained vegetation to ensure Singapore daisy infestation is controlled, as well as other RIP’s.
3. Ensure that, where interfering with koala habitat results in a
significant residual impact, and offset if delivered:
a. at a multiplier of 6 (unless the offsets calculator It is proposed to establish a total rehabilitation area of 1.8 hectares to mitigate impacts to Koala habitat. The
is a greater amount) and otherwise in rehabilitation will involve:
accordance with the requirements of the • A dedicated Koala Tree Offset planting for Lot 77 which will nominate an offset in suitable habitat which is larger than the koala
Queensland Environmental Offsets Policy at the habitat to be cleared of 1.02ha. The rehabilitation area is to be designed to improve and or create vegetated Koala movement
time of the project approval; or corridors and provide for the offset of koala trees.
• Within the Koala rehabilitation works a minimum of 0.21ha of designated revegetation aimed to achieve RE 12.5.3 (Eucalyptus
racemosa subsp. racemosa woodland on remnant Tertiary surfaces (DES, 2022), to mitigate the impacts to Endangered RE.
As a significant residual impact is not relevant for this proposed clearing, the requirement for a 6 to 1 offset is not
necessary. Council is proposing a 1.8 ha Offset for the 1.02 ha of area been cleared.
b. at a multiplier of 6 (unless the offsets calculator “as above”
is a greater amount) and otherwise in
accordance with the requirements of the
Queensland Environmental Offsets Policy at the
time of the project approval, except for the offset
site location preferences if the public sector
entity has a pre-existing offset; or
c. as an alternate compensatory action, where the N/A
development is for Transport Infrastructure, and
the alternate compensatory action includes:
i. the design, prior to the
commencement of impacts, of a
Koala Management Plan that:
a) demonstrates that the alternate N/A
compensatory action will deliver
a conservation outcome equal
to, or greater than, would
otherwise be achieved through
the delivery of a land-based
offset in 3 (a) or (b) above; and
b) demonstrates that the alternate N/A
compensatory action is based
Noosa Landfill & RRC – northern section – Fauna and Flora Assessment – REV4 46
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.