Performance outcomes Acceptable outcomes Compliance
Major Electricity Infrastructure
PO2 Complies with PO2.
Development does not increase risk to No acceptable outcome provided The electricity transmission line corridor is 119m wide. The
community health or safety, or the operation proposed secondary dwelling is setback 27.9m from the
and reliability of major electricity infrastructure easement and greater than 58m (approx.) from the overhead
lines and will not increase risk to community health or safety or
the operation of the electricity infrastructure.
PO3 AO3.1 Alternate solution to A03.1 proposed
Development involving a sensitive land use is With the exception of class 10 buildings, buildings The secondary dwelling is setback 27.9m from the transmission
sufficiently separated from major electricity associated with a sensitive land use maintain line easement. The proposed secondary dwelling is setback
infrastructure and substations to minimise the a setback of at least: greater than 58m (approx.) from the overhead lines. The
likelihood of nuisance or complaint. proposed siting of the secondary dwelling clearly provides
adequate separation and does not compromise the operation
a) 50 metres from a transmission substation; of the electricity infrastructure.
b) 10 metres from any other substation; and
c) 30 metres from a transmission line easement.
AO3.2 Complies with A03.2
Buildings are not located within an easement for a The proposed secondary dwelling is not located within the
distribution line. easement.
PO4 AO4 Not relevant to this application. The proposed secondary
Development adjoining substations are located For development adjoining substations, noise dwelling does not adjoin a substation.
and designed to avoid noise nuisance from emissions do not exceed 5db(A) above background
infrastructure. noise level at the sensitive receptor of
a building associated with a sensitive land use,
measured in accordance with AS1055.
PO5 AO5 The majority of the site is occupied by easement containing
Wherever practicable new lots and buildings are Buildings are orientated so that the majority of overhead electricity lines running through the site in a
orientated to avoid direct overlooking of outdoor living areas and windows of habitable rooms north/south direction. It is not possible to avoid direct
electricity infrastructure. face away from towers or other major electricity overlooking of electricity infrastructure.
infrastructure.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.