Project Hazard Risk Management Ozcare Noosa RACF 23-04-2024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
3.9 HAZARD RISK / MANAGEMENT
Woollam Constructions will manage risk, by implementing the following five steps Risk Management Process;
3.9.1 Hazard Identification and Reporting
Hazards identified during the course of the project, which are unable to be controlled immediately, will be reported, and
corrective / preventive controls will be implemented to minimize the likelihood and consequences of the hazard.
After consultation, if controls cannot be implemented to reduce the hazard to As Low as Reasonably Practicable, a risk
assessment of the hazard must be conducted using the Risk Assessment Form and the following details reported;
• description of the hazard
• control measures outlined as to how the hazard will be eliminated or minimized;
• identifying who will be responsible for implementing the control measures;
• hazards to be assessed using the risk calculator located in section 3.9.2 of the WHSMM and taking into account
available information on the hazard including any records of incidents, illness and disease;
• participants in the Risk Assessment process
Recommended control measures identified from the Risk Assessment, will be implemented in the form of Safe Work Method
Statements.
OHS Management Manual / 14/02/2024 / Page 24 Approved by - HSEQT Manager
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard Risk Management Ozcare Noosa RACF 23-04-2024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 550 KB (small file)
- File type
No other editions are linked here.