Drains catchment B 0.038 0.041 0.047 0.053 0.058 0.081 0.104
Post Development
(Mitigated)
The PC DRAINS Hydraulic Modelling has demonstrated the proposed mitigated peak discharge flow
rates will not exceed the total pre development flows for all design storms. Refer Appendix D for the
drains results.
6.3.5 Total Post Development Mitigated Discharge
The post development rational method results displayed in Table 6.3 for catchment A has been added
to the mitigated catchment B results from PC DRAINS displayed in Table 6.5. Table 6.6 summarises
the total post development site discharge.
Table 6.6 – Total Post Development Mitigated Peak Discharge
Catchment Q1 Q2 Q5 Q10 Q20 Q50 Q100
(m3/s) (m3/s) (m3/s) 3 (m3/s) (m3/s) (m3/s)
(m /s)
Rational Method 0.028 0.034 0.051 0.063 0.076 0.095 0.105
Catchment A Post
Development
Drains Catchment B 0.031 0.038 0.044 0.052 0.057 0.061 0.109
Post Development
(Mitigated)
Total Site Discharge 0.059 0.072 0.095 0.115 0.133 0.156 0.217
SCG Consulting Engineers Page 21 SCG Ref: 31131(SWMP)
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (RFI - SWMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.