Request to Change Current Application · OPW11/0023

of 66

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (10.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.

1
    * Relative results for hydraulic conductivity of 50mm/hour and 200mm/hr for the filter media in
    bioretention cell.

                               Table 5 - MUSIC Modelling Results - Pollutant Reduction




                                            Flow (ML/yr)                                    26.3
                                            Total Suspended Solids (kg/yr)                   469
                                            Total Phosphorus (kg/yr)                        4.69
                                            Total Nitrogen (kg/yr)                          44.9
                                            Gross Pollutants (kg/yr)                          0.0


                               Table6 - MUSIC Modelling - Mean Annual Residual Loads




    4.0       Impacts on Receiving Waterways


    Stormwater harvesting demand from the site will represent around 1.2 ML per year, compared to
    the original annual average runoff volume of approximately 7.5ML per year and a residual post-
    developed annual average runoff volume of 16.4ML per year (refer Table 5)1. Therefore stormwater
    harvesting will not reduce the total volume of water discharging from the site compared to the pre-
    developed condition and will not have an impact on downstream receiving waterways.



I   The proposed stormwater detention will maintain the peak runoff flow rates close to the original
    (pre-developed) flow rates (see Table 1), so the sedimentation/detention basin will have no adverse
    impact on downstream receiving waterways.




    5.0       Monitoring of Treatment Train


    Monitoring of the performance of the treatment train shall be conducted as follows, for a period of
    three years from the completion of the development;




    5.1       TSS and Gross Pollutant


              The majority of TSS and gross pollutants is expected to originate from areas of car parks and
              other paved road surfaces. Therefore most TSS and GP collection is expected to occur in the
              gross pollutant traps installed on the bioretention cell inlets.                            Observation of the
              bioretention basin should be undertaken duirng routine maintenance, but not less than


    i The original runoff volume is calculated by multiplying the site area of 2.33 Ha by the annual rainfall runoff of 1.6m and a
    typical runoff co-efficient of 0.2 (conservative).


I                                                                  11

Used in these records

About this file

File size
10.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Request to Change Current Application.pdf · 10.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.