Minor Change Existing Approval - RAL19 0018.01 (As Published)
d. a driveway that is safely trafficable in a 1%AEP event
e. any necessary traffic barriers and fall protection
f. services – underground and extended to the house site areas as part of the access
driveway works.
Concrete Bin Pad
17. A concrete bin pad for all lots must be constructed on the verge area located proximate to
the lots with the final location and configuration determined as part of the operational works
application. The bin pads must be in accordance with an Operational Work approval and
sufficiently sized to wholly accommodate 2 wheelie bins for each lot.
Stormwater Drainage
18. Stormwater runoff from the development (roads, driveways and building pads) must be
disposed of on-site without causing scour or damage to the subject site or any adjoining
property. The works must be undertaken in accordance with an Operational Works approval.
Condition 18 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Electricity and Telecommunication Services
19. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with an approval for Operational Works and the standards and requirements of
the relevant service provider.
20. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
21. Certification must be submitted to Council from all relevant service providers which certifies
that the development has met the requirements of this Decision Notice and all applicable
legislation at the time of construction.
Easements
22. An easement for drainage purposes must be registered in favour of Council against the title
of all lots which receive or convey stormwater from the roads. The easement must be of
sufficient width to fully contain all structures and the 1%AEP flows from the relevant
catchment.
23. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
24. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
25. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Page 5 of 15
Document Set ID: 24931816
Version: 3, Version Date: 13/07/2026