               NOOSA COUNCIL IDAS Development Application Decision Notice                                                            3




                                NOOSA                           Noosa Council Conditions
                                                                INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION


               Building
               1           The plans submitted for a Development Permit for building works are to comply with the approved
                           plans.
              2            Construction work associated with the 18 hole par 3 golf course element of the complex shall not be
                           permitted on Sundays, public holidays or between the hours of 6:00 pm and 7:00 am , provided that
                           these hours may be modified with specific approval from the Manager of Building.
               Health
              3            A grease arrester should be provided at the clubhouse (if food preparation or cooking occur). Include all
                           trade waste information on the hydraulic drawings.
              Engineering
              4            Prior to undertaking any excavation, the person acting on this permit shall contact public utility service
                           providers to ascertain the location of their underground services.
              5            For the following classes of work associated with development, a Development Permit for Operational
                           Works must be obtained prior to commencement of works relating to that class of work. The
                           application may combine any or all of these classes of work: -
                                       Access and/or carparking
                                       Drainage
                                       Frontage works
                                       Roadworks
                                       Site Filling
                                       Excavation of materials to fill another site
                                       Landscaping
              6            The person acting on this permit shall apply and obtain for all other necessary permits including crane
                           permits, road opening permits, hoarding permits, footpath occupation permits and/or any other
                           approvals required under any other Act.
              7            Before the issue a Development Permit for Operational Works, the Applicant shall sign a written
                           undertaking to be responsible for the full cost of repairs to road pavement, footpath, kerb and gutter, or
                           other Council property damaged as a result of construction of the proposed development.
                            If any Council property or facilities (such as underground drainage) is damaged by any person acting
                           under a condition of this permit, through any cause whatsoever in the course of, directly or indirectly
                           carrying out development, that person shall forthwith notify the Manager-Land Development and shall
                           forthwith rectify that damage at its cost and to the satisfaction of the Manager-Land Development.
                           Alternatively, the Applicant may request the Council to carry out the rectification works.
                           In all cases, Council reserves the right to carry out rectification works in an emergency and where no
                            reasonable attempt has been made to complete the rectification works as part of the development.
                           All costs incurred by Council in any rectification works shall be repaid to Council prior to the
                           commencement of the use.
              8            The Assessment Manager for building work shall ensure that all other permits required by this permit
                           have been obtained and outcomes from imposed conditions incorporated into the building plans prior to
                           issue of a Development Permit for Building W orks.
              9            All parking associated with the approved use shall be provided within the development site.

                           Formalised On-Site parking shall be for at least 80 car spaces, 2 Tourist Bus bays, including a
                           minimum of 10 spaces for staff. At least 4 spaces shall be clearly marked for disabled car spaces.

                           Additional contingency car parking shall be provided on site for at least another 10 car spaces and 1
                           Tourist Bus and expanded as necessary to meet demand.

                           The car parking areas shall be designed to comply with the provisions of AS 2890.1-1993 for user class
                           2.
               SMP o:\database\ipa\town planning\decision.doc


                                                                                                                 Print Date: 7 September 2021, 10:32 AM
Log in to download the original file

change to the approval - clubhouse use.pdf · 310 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.