INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 22 JULY 2014
ATTACHMENT 1
Page 31 of 49
INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 22 JULY 2014
ATTACHMENT 1
Scope of Works required for adaptation and re-use of Tait-Duke Cottage,
Tewantin
The following table lists most items of work required to relocate, restore and adapt the former Tait-
Duke Cottage for community uses, and appropriate responsibility for their implementation.
Relocation and provision of services. Noosa Council has advised it has a budget allocation for
this work.
[Work — sCd|NOtes i Responsibility
toilet additions verandah for reconstruction
Divide building and transport Provide all necessary permits House Removaiist
from Wallace Park to Earl
Street, Tewantin
oe TL
and re-join building halves
Restump building on new site | Minimum floor height 2.8m AHD | Restumper
Perimeter stumps round treated
hwd. Internal posts galv. SHS
verandah enclosure of walls
|Constructrearstairs | id Carpenter
to perimeter of building Plumber and Drainer
Provision of disabled access and toilet facilities. It is assumed that as Lessor, Noosa Council
will require the maximum achievable accessibility for the building’s community use. The current
drawings show basic provisions of an access ramp and accessible toilet — it is also likely that most
internal doors will require widening to provide full internal access. It is recommended that
specialist advice be sought on compliance with the Disability Discrimination Act, through an
Access Consultant or Sunshine Coast Access Advisory Network (SCAAN)
As this work is likely to be one of the major costs of adaptation, negotiation with Noosa Council
may be required to determine whether some or all of the costs can be absorbed into Council’s
relocation budget.
Construct access ramp and Note: Drawings are Carpenter or pre-fabricated
handrails to side of building approximate only, depending metal ramp supplier, and
complying with AS 1428.1 on final height of building concreter
ae)
walls as shown on plan
Smee |
accordance with AS 1428.1
Fit out toilets with pedestals, Licensed Plumber and possible
cisterns, basins, taps, sponsorship of Plumbing
handrails and hot water system Supplier
and connect to water and
sewerage
Page 31 of 49See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.