Original source · versioned page text
ASTP-Rspns_To_RFI
ITEM 5:
Issue – Earthworks Sections
Additional earthworks sections are required to accurately assess the proposed development.
Information Required
5. Provide additional earthworks sections through the areas highlighted in red below. The
additional sections must be prepared by a suitably qualified person (RPEQ) and include
the requested information in Item 4.
Figure 2 – Requested sections extracted from Barlow Shelley’s Bulk Earthworks Plan (C101, Rev. A).
RESPONSE
Please refer to the Engineering Responses and updated Engineering Plans in Attachments 3 and 4. The updated
Engineering Plans (Attachment 4) include the requested additional sections and information.
ITEM 6:
Issue – Retaining Wall
The sections of retaining structures shown in the below extract require further justification.
Figure 3 – Sections of retaining wall in question extracted from Barlow Shelley’s Bulk Earthworks Plan (C101, Rev.
A)