Skip to the record
The gold standard in government transparency.

Original source · versioned page text

2020-04-30 Ordinary Meeting Agenda

of 60

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

ORDINARY MEETING AGENDA                                                                                               30 APRIL 2020


Capital Revenue
YTD capital revenue of $6.8 million received comprises cash contributions from developers ($1.7
million) and capital grants ($5.0 million). Included in capital revenue is an unbudgeted grant for
bushfire disaster recovery ($1.3 million) and an early milestone grant payment for the Orealla bridge
replacement project ($1.4 million). Note that the timing of capital grant receipts are generally
dependent on the timing of grant conditions and also capital delivery performance, and that the timing
of the receipt of developer contributions (both cash and contributed) is unpredictable.

Figure 4: Capital Revenue by Type

 $6.0
                                                                        $5.0
 $5.0
                                                                                  YTD Budget ($m)
                                                                                  YTD Actual ($m)
 $4.0

 $3.0                                                $2.7


 $2.0          $1.7                   $1.7


 $1.0
                                                                                         $0.1                  $0.1
 $0.0
                      Contributions




                                                                                                 Contributed
                                                            Subsidies
                                                             Grants /




                                                                                                   Assets
                         Cash




Capital Program
Actual capital expenditure (excluding contractual commitments) is $15.5 million (YTD budget $19.8
million). Detailed discussion of progress in the delivery of the capital works program is provided
through a separate report by the Asset Planning Manager.

Figure 5: Capital Program Delivery Performance

$18.0                   $16.8

$16.0
                                             $13.6      YTD Budget ($m)
$14.0                                                   YTD Actual ($m)
$12.0
$10.0
 $8.0
 $6.0
 $4.0                                                                          $3.0
                                                                                             $1.9
 $2.0
 $0.0
                                Capital works                                    Other capital




                                                                                                                        Page 9 of 60
Log in to download the original file

2020-04-30 Ordinary Meeting Agenda(PDF, 4MB).pdf · 4.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.